Notice: We are currently performing maintenance to improve the italaw platform. The site remains fully accessible. Thank you for your patience.

ICS Inspection and Control Services Limited v. Argentine Republic (II), PCA Case No. 2015-12

Short Name:

ICS v. Argentina (II)

Applicable Procedural Rules:
Seat of Arbitration:
Applicable Legal Instruments:
Economic Sector:
Amount of Damages:
US $9,661,391
Other Remedy:
The Tribunal ordered Respondent to pay Claimant USD 9,661,390.80 in principal plus compound interest at 12.8% annually. Each party to bear its own costs.

Available documents

21 Jul 2014
Notice of Arbitration
Document Details:
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's counsel
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Entities
Document Summary
This summary note is machine-generated. Always consult the original materials.


8 Jul 2019
Decision on Jurisdiction
Document Details:
PARTICIPANTS
Decision on Jurisdiction
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Claimant appointee:
Respondent appointee
Respondent appointee:
Tribunal/Panel chair
Chair/President:
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Other counsel
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Country
Print reporter
Document Summary
Decision on Jurisdiction
This summary note is machine-generated. Always consult the original materials.

Procedural Posture

This document is the Award on Jurisdiction issued on July 8, 2019, in PCA Case No. 2015-12, an arbitration conducted under the 1976 UNCITRAL Arbitration Rules and the 1990 United Kingdom-Argentina Bilateral Investment Treaty (BIT). The dispute arose from Argentina's alleged failure to pay for pre-shipment inspection and auditing services provided by the Claimant, ICS Inspection and Control Services Limited. The Respondent, the Argentine Republic, bifurcated the proceedings by raising preliminary objections to the Tribunal's jurisdiction and the admissibility of the claims.

Jurisdictional Objections and Parties' Positions

Argentina advanced three primary objections. First, it argued that the Tribunal lacked jurisdiction ratione temporis, asserting that the Claimant had assigned its contractual rights to a third-party affiliate (Ostram) and only reacquired them after the challenged measures were implemented, thereby constituting an abuse of process. Second, Argentina contended that the claims were purely contractual in nature and fell outside the Tribunal's jurisdiction ratione materiae, emphasizing that the underlying contract contained an exclusive forum selection clause in favor of Argentine courts. Third, the Respondent argued that the claims were inadmissible due to acquiescence and extinctive prescription, given the passage of time since the alleged breaches.

The Claimant maintained that it retained ownership of the investment as a whole despite the temporary assignment of specific receivables. It further argued that its claims were properly formulated as treaty breaches, invoking the BIT's umbrella clause, fair and equitable treatment (FET) standard, and full protection and security (FPS) provisions, which operate independently of the contract's forum selection clause.

Tribunal's Analysis and Findings

The Tribunal systematically dismissed the Respondent's jurisdictional objections. Regarding jurisdiction ratione temporis, the Tribunal determined that the temporary assignment of specific credits did not deprive the Claimant of its broader investment under the BIT, nor did it constitute an abusive corporate restructuring. Applying the prima facie standard, the Tribunal found that the Claimant had sufficiently pleaded breaches of the BIT's substantive protections, including the umbrella clause, which elevated the alleged contractual breaches to the international plane. The Tribunal further held that the exclusive jurisdiction clause in the underlying contract did not preclude it from exercising jurisdiction over claims founded on the BIT.

Decision

In its dispositive section, the Tribunal affirmed its jurisdiction to hear the Claimant's case under the UK-Argentina BIT. The Tribunal concluded that it was more prudent to join the Respondent's admissibility defenses regarding acquiescence and extinctive prescription to the merits phase of the arbitration, thereby ordering the continuation of the proceedings.



29 Apr 2024
Final Award
Document Details:
PARTICIPANTS
Final Award
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Claimant appointee:
Respondent appointee
Respondent appointee:
Tribunal/Panel chair
Chair/President:
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Other counsel
Claimant's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Document Summary
Final Award
This summary note is machine-generated. Always consult the original materials.

Procedural Posture

This document is the Final Award in PCA Case No. 2015-12, an arbitration conducted under the UNCITRAL Rules 2010 and the 1990 Agreement between the United Kingdom and the Argentine Republic for the Promotion and Protection of Investments (the "BIT"). The dispute arose from a 1998 contract between the Claimant, a UK company, and Argentina for the provision of auditing services related to a pre-shipment inspection programme for imports.

Principal Legal and Procedural Issues

The principal issues addressed by the Tribunal included whether Argentina breached Article 2(2) of the BIT—specifically the fair and equitable treatment (FET) standard, full protection and security (FPS), the prohibition against unreasonable or discriminatory measures, and the Umbrella Clause. The Claimant alleged breaches based on Argentina's application of a 10% fee cap, the forced conversion of US dollar-denominated invoices into Argentine Pesos ("pesification"), a 13% reduction of fees pursuant to Decree 1060/01, and the non-payment for alleged "Special Services." The Respondent raised preliminary defenses of acquiescence, estoppel, good faith, and extinctive prescription, alongside a defense of necessity under customary international law.

Parties' Positions

The Claimant argued that the 10% fee cap was inapplicable because Argentina failed to implement a functioning selection system for the audits. It further contended that its remuneration was a value obligation in US dollars, rendering pesification unlawful, and that it never consented to the 13% fee reduction. The Respondent maintained that its actions were strictly consistent with the Contract and Argentine law, arguing that the Claimant had tacitly consented to the fee cap and reductions by continuing to provide services. The Respondent further invoked the 2001-2002 Argentine financial crisis to support its necessity defense.

Tribunal's Reasoning and Findings

The Tribunal dismissed the Respondent's preliminary defenses, finding no factual basis for acquiescence, estoppel, or extinctive prescription. On the merits, the Tribunal determined that the Umbrella Clause encompassed the Contract. It held that the Claimant was contractually entitled to amounts exceeding the 10% fee cap because Argentina's failure to implement a workable selection system rendered compliance impossible. Regarding pesification, the Tribunal found that the Claimant's remuneration constituted a value obligation in US dollars, placing it outside the scope of the Emergency Law and Decree 214/02. The Tribunal also concluded that the 13% reduction under Decree 1060/01 was inapplicable, as the Claimant had not consented and the Contract had already expired. Concerning the Special Services, the Tribunal found that certain reports qualified for additional remuneration under Resolution 1106/98, though it applied a discount due to defective proof of costs. Because the Tribunal concluded that the Claimant's contractual entitlements fell outside the scope of the emergency measures, it deemed it unnecessary to decide on the Respondent's necessity defense.

Decision and Relief

The Tribunal declared that the Respondent violated the Umbrella Clause of the BIT. It ordered Argentina to pay the Claimant compensation in the principal amount of USD 9,661,390.80. Furthermore, the Tribunal awarded pre-award compound interest at an annual rate of 12.8 percent, reflecting the Respondent's median cost of borrowing. The Tribunal ordered that each party bear its own legal costs and half of the arbitration costs.



30 Apr 2024
Claimant's Press Release on Final Award
Document Details:
PARTICIPANTS
Claimant's Press Release on Final Award
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Claimant appointee:
Respondent appointee
Respondent appointee:
Tribunal/Panel chair
Chair/President:
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's counsel
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Entities
Document Summary
Claimant's Press Release on Final Award
This summary note is machine-generated. Always consult the original materials.


12 Jul 2024
Correction of the Final Award
Document Details:
PARTICIPANTS
Correction of the Final Award
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Chair/President:
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's counsel
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Document Summary
Correction of the Final Award
This summary note is machine-generated. Always consult the original materials.

Procedural Background

This document constitutes the Tribunal’s decision on a Request for Correction of the Final Award, submitted by the Respondent on May 29, 2024, pursuant to Article 38 of the 2010 UNCITRAL Arbitration Rules. The Respondent sought to rectify a computational oversight in the Final Award dated April 29, 2024, specifically concerning the calculation of compensation for Special Services. On June 7, 2024, the Claimant submitted its response, expressly agreeing to the mathematical corrections proposed by the Respondent, notwithstanding certain objections to the characterization of the request.

Tribunal's Analysis and Decision

The principal issue before the Tribunal was whether the Final Award contained an error in computation or omission of a similar nature warranting correction under Article 38. The Respondent demonstrated that while the Tribunal had applied a discount for defective proof to the principal amounts owed for Special Services, it had inadvertently failed to apply the corresponding discount to the Value Added Tax (VAT) amounts reflected on the relevant invoices.

In light of the Parties' mutual agreement regarding the revised calculations, the Tribunal found the request justified. Consequently, the Tribunal ordered the correction of multiple quantum tables across fifteen specific paragraphs of the Final Award. The operative effect of this correction reduced the total compensation awarded to the Claimant for Special Services from USD 1,702,834.91 to USD 1,656,827.20, thereby decreasing the aggregate principal amount of the Award from USD 9,707,398.51 to USD 9,661,390.80. All other requests were dismissed, and a corrected version of the Final Award was annexed to the decision.



18 Feb 2026
Judgment of the Hague District Court (Dutch)
Document Details:
PARTICIPANTS
Judgment of the Hague District Court (Dutch)
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Claimant's counsel
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Country in which this occurs:
Print reporter
Document Summary
Judgment of the Hague District Court (Dutch)
This summary note is machine-generated. Always consult the original materials.

Procedural Posture

This judgment, rendered by the District Court of The Hague, addresses an application by the Republic of Argentina to set aside an arbitral award and a preceding interim award on jurisdiction issued in favor of ICS Inspection and Control Services (ICS). The underlying arbitration was conducted pursuant to the 1990 United Kingdom-Argentina Bilateral Investment Treaty (BIT). Argentina sought primary annulment based on the alleged lack of a valid arbitration agreement and subsidiary partial annulment concerning the tribunal's award of compound interest, alleging an excess of mandate and violations of public policy.

Jurisdictional Challenge

Argentina contended that the tribunal lacked jurisdiction, arguing that the underlying contract between ICS and Argentina contained an exclusive forum selection clause designating the Argentine federal courts, which purportedly superseded the BIT's arbitration offer. Applying a full standard of review to the jurisdictional question, the Court upheld the tribunal's competence. The Court affirmed the well-established distinction between contract claims and treaty claims, noting that ICS's claims were properly advanced under the BIT's umbrella clause. The Court concluded that the contractual forum selection clause did not explicitly exclude the investor's right to invoke the BIT's dispute resolution mechanism, thereby validating the formation of a binding arbitration agreement under international law.

Excess of Mandate and Public Policy

In its subsidiary claim, Argentina challenged the tribunal's award of 12.8% compound interest, arguing that the tribunal failed to apply Argentine law and that the resulting quantum was punitive, thereby violating Dutch public policy. The Court rejected these arguments, observing that the BIT permitted the application of international law to determine the appropriate reparation. The Court noted that the tribunal explicitly awarded the interest as compensatory damages to restore ICS to the position of an unsecured long-term lender to the State, rather than as a punitive measure. Emphasizing the strict limitations on judicial intervention in arbitral merits, the Court found no manifest violation of the tribunal's mandate or fundamental public policy.

Decision

The District Court of The Hague dismissed Argentina's application for annulment in its entirety. Furthermore, the Court ordered Argentina to bear the costs of the proceedings, enforceable with immediate effect.



31 Mar 2026
Petition to Recognize and Enforce Foreign Arbitral Award
Document Details:
PARTICIPANTS
Petition to Recognize and Enforce Foreign Arbitral Award
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Document Summary
Petition to Recognize and Enforce Foreign Arbitral Award
This summary note is machine-generated. Always consult the original materials.

Procedural Posture

This document is a Petition to Recognize and Enforce a Foreign Arbitral Award filed by the Petitioner against the Argentine Republic in the United States District Court for the District of Columbia. The Petitioner seeks judicial confirmation of a final UNCITRAL arbitral award issued on April 29, 2024 (as corrected on July 12, 2024), pursuant to the New York Convention and Chapter 2 of the Federal Arbitration Act (FAA).

Factual and Legal Background

The underlying arbitration concerned Argentina’s alleged breaches of the UK-Argentina Bilateral Investment Treaty (BIT) in relation to a 1998 contract for pre-shipment inspection auditing services. Following the Argentine economic crisis in 2001–2002, the State implemented emergency measures that unilaterally reduced the Petitioner's remuneration, devalued the local currency, and ultimately terminated the inspection program. The arbitral tribunal found Argentina liable for violating the fair and equitable treatment standard under Article 2(2) of the BIT. Consequently, the tribunal awarded the Petitioner USD 9,661,390.80 in principal damages, alongside 12.8% compounded annual interest.

Jurisdictional Basis and Relief Sought

In this enforcement proceeding, the Petitioner asserts that the District Court possesses subject matter and personal jurisdiction over Argentina under the Foreign Sovereign Immunities Act (FSIA). The Petitioner relies specifically on the arbitration exception (28 U.S.C. § 1605(a)(6)) and the implied waiver exception (28 U.S.C. § 1605(a)(1)), arguing that Argentina waived its sovereign immunity by becoming a signatory to the New York Convention. Contending that no grounds for refusal under Article V of the New York Convention apply, the Petitioner requests the entry of a judgment confirming the award and ordering Argentina to pay the principal amount plus all accrued pre-judgment and post-judgment interest.



Case Summary
This summary note is machine-generated. Always consult the original materials.

Case Overview

In ICS v. Argentina (II), the claimant, ICS Inspection and Control Services Limited, a company incorporated in England and Wales, initiated arbitration against the Argentine Republic under the 1990 Argentina-United Kingdom Bilateral Investment Treaty (BIT). The dispute arose from a 1998 contract under which ICS provided pre-shipment inspection services for goods imported into Argentina. ICS alleged that Argentina's measures, including the failure to pay for services rendered, constituted breaches of the BIT. In its Final Award, the Tribunal found that Argentina had breached the BIT's umbrella clause by failing to observe its contractual obligations and awarded the Claimant damages.

Procedural History

The Claimant initiated arbitration by a Notice of Arbitration dated July 21, 2014, under the UNCITRAL Arbitration Rules of 1976. The Permanent Court of Arbitration (PCA) acts as the administering institution. The Tribunal was constituted with Jernej Sekolec as President, appointed by the PCA Secretary-General, Pierre-Yves Tschanz, appointed by the Claimant, and Domingo Bello Janeiro, appointed by the Respondent. The seat of the arbitration is The Hague, Netherlands. Following the submission of written memorials on jurisdiction, a hearing was held at the Peace Palace in The Hague on February 28 and March 1, 2017. The Tribunal rendered its Award on Jurisdiction on July 8, 2019, addressing the preliminary objections raised by Argentina. After the case proceeded to the merits, a hearing was held by videoconference from April 6-14, 2021. The Tribunal issued its Final Award on April 29, 2024. Following the issuance of the Final Award, the Argentine Republic initiated proceedings before the District Court of The Hague to set aside the award. On February 18, 2026, the Hague District Court rendered its judgment, dismissing Argentina's application in its entirety.

Key Issues and Positions

Jurisdictional Objections

Argentina's jurisdictional challenge centered on three main arguments. First, it contested jurisdiction *ratione temporis*, arguing that ICS was not the owner of the investment when the dispute arose. This was based on a 2001 contract whereby ICS ceded its credits against Argentina to a third-party entity, Ostram Holding Services. Although ICS reacquired these credits in 2007, Argentina contended that ICS lacked title during a critical period and that the reacquisition was an abusive act of 'treaty shopping' to manufacture jurisdiction. Second, Argentina argued that the claims were fundamentally contractual and did not rise to the level of a treaty breach. It asserted that the dispute concerned non-payment under a services contract, which should be resolved by Argentine courts as stipulated in the contract's forum selection clause. Argentina contended that the BIT's umbrella clause could not transform a simple contract claim into a treaty claim. Third, Argentina raised defenses of acquiescence and extinctive prescription. It argued that by its conduct and prolonged inaction, ICS had acquiesced to Argentina's measures, thereby extinguishing its right to claim. Furthermore, it argued that the claims were time-barred under principles of international law.

Merits and Damages

On the merits, the Claimant alleged that Argentina breached the BIT's standards of fair and equitable treatment (FET), full protection and security (FPS), and the umbrella clause by taking four specific actions in breach of the services contract: (1) wrongfully withholding payments that exceeded a 10% fee cap; (2) unlawfully converting its USD-denominated invoices into devalued Argentine pesos ('pesification'); (3) unlawfully applying a 13% reduction to certain invoices pursuant to Decree 1060/01; and (4) failing to pay for additional 'Special Services' rendered at Argentina's request. Argentina countered that its actions were consistent with the contract and applicable Argentine law. It also raised a defense of necessity under customary international law, arguing that the measures were justified by the severe economic crisis of 2001-2002.

Tribunal/Court Reasoning and Holdings

Jurisdiction

The Tribunal rejected Argentina's objection *ratione temporis*. It determined that ICS's 'investment' under the BIT was not limited to the monetary credits but encompassed its entire business operation in Argentina, including its office in Buenos Aires, personnel, and know-how, which it maintained throughout the period of the credit cession. The Tribunal found that the cession to Ostram did not divest ICS of its entire investment. It concluded that ICS held a protected investment at all relevant times and that the reacquisition of the credits in 2007 was not an abuse of process. Therefore, the Tribunal affirmed its jurisdiction over the dispute. The Tribunal also dismissed the objection that the claims were purely contractual. It reasoned that while the claims originated from a contract, the Claimant had framed them as breaches of specific BIT standards, such as fair and equitable treatment and full protection and security. The Tribunal held that, at the jurisdictional stage, it must accept the claims as pleaded on a *prima facie* basis. It found that the claims, as formulated, alleged violations of the treaty and were not merely contractual matters disguised as treaty claims. The Tribunal thus confirmed its jurisdiction to hear the treaty-based claims.

Acquiescence and Prescription

Regarding the defenses of acquiescence and prescription, which were joined to the merits, the Tribunal dismissed them in the Final Award. It found no significant period during which the Claimant was idle or failed to protest the measures. The Tribunal concluded that the Claimant had diligently pursued its claims through administrative, arbitral, and court proceedings from the inception of the dispute, negating any implied consent or acquiescence.

Merits

The Tribunal centered its merits analysis on the umbrella clause, which requires the host state to observe any obligation it has entered into with regard to an investment. It found that Argentina had breached its contractual obligations to ICS, and that these breaches constituted a violation of the umbrella clause. The Tribunal found it unnecessary to rule on the other alleged BIT breaches. The Tribunal upheld the Claimant's claims on three of the four main issues. First, it held that Argentina's application of the 10% fee cap was a breach of contract because the cap was conditioned on Argentina implementing a workable system for selecting which shipments to audit, a condition Argentina failed to fulfill. Second, it found that the 'pesification' of ICS's invoices was wrongful because the contractual obligation was a 'value obligation' (pegged to USD-denominated values) rather than a 'monetary obligation,' placing it outside the scope of Argentina's emergency pesification laws. Third, the Tribunal concluded that the 13% reduction under Decree 1060/01 was improperly applied because the contract had already expired and the decree's procedural requirements were not met. On the fourth issue, the claim for 'Special Services,' the Tribunal found that only 12 of the 21 services claimed qualified for separate remuneration. It dismissed the other claims as being part of the ordinary audit work, having been performed before the legal basis for their payment existed, or for lack of proof. The Tribunal also applied a 10% discount to the recoverable amounts for the upheld services due to deficiencies in the Claimant's proof of costs. The Tribunal found it unnecessary to rule on Argentina's necessity defense, as it had already determined that the emergency measures were inapplicable to the Claimant's contractual entitlements.

Quantum and Costs

Based on its findings on the merits, the Tribunal calculated the principal amount of damages owed to the Claimant. It awarded compensation for the amounts wrongfully withheld under the 10% fee cap, the losses from pesification, the improper 13% reduction, and the amounts due for the upheld Special Services. The total principal awarded was USD 9,661,390.80. The Tribunal also awarded pre- and post-award interest, compounded annually at a rate of 12.8%, which it determined based on the median of Argentina's sovereign borrowing cost during the relevant period. The Tribunal ordered each party to bear its own legal costs and to share the costs of the arbitration equally.

Set-Aside Proceedings

In the set-aside proceedings before the Hague District Court, Argentina argued primarily that a valid arbitration agreement was absent, contending that the contract's exclusive forum selection clause for Argentine courts superseded the BIT's offer to arbitrate. Argentina also challenged the award of 12.8% compound interest as a violation of its mandate and contrary to public policy. The Court rejected both grounds. It upheld the Tribunal's distinction between contract claims, governed by the forum selection clause, and treaty claims, which could be brought to arbitration under the BIT. The Court found that the contract did not explicitly waive the right to arbitrate treaty claims. Regarding the interest award, the Court held that its review was limited and found no violation of public policy, noting that the arbitrators had characterized the interest as compensatory, not punitive, and that a review of the correctness of the damage calculation was beyond the scope of a set-aside proceeding. The Court therefore dismissed Argentina's application to annul the award.

Disposition / Relief

In its Final Award of April 29, 2024, the Arbitral Tribunal found that Argentina had violated the umbrella clause of the Argentina-UK BIT. The Tribunal ordered the Argentine Republic to pay the Claimant compensation in the principal amount of USD 9,661,390.80. It also ordered Argentina to pay compound interest on this amount at an annual rate of 12.8% from the due date of each invoice until the date of payment. The Tribunal directed that each party should bear its own legal and other costs, and half of the costs of the arbitration.