PCA Case No. 2015-12
IN THE MATTER OF AN ARBITRATION UNDER THE AGREEMENT BETWEEN THE
GOVERNMENT OF THE REPUBLIC OF ARGENTINA AND THE GOVERNMENT OF THE
UNITED KINGDOM OF GREAT BRITAIN AND NORTHERN IRELAND FOR THE
PROMOTION AND PROTECTION OF INVESTMENTS, DATED 11 DECEMBER 1990
- and -
THE UNCITRAL ARBITRATION RULES (AS REVISED IN 2010)
- between –
ICS INSPECTION AND CONTROL SERVICES LIMITED (UNITED KINGDOM)
(the “Claimant”)
- and –
THE ARGENTINE REPUBLIC
(the “Respondent”, and together with the Claimant, the “Parties”)
ARBITRAL TRIBUNAL:
Mr. Jernej Sekolec (Presiding Arbitrator)
Mr. Pierre-Yves Tschanz
Prof. Dr. Domingo Bello Janeiro
SECRETARY TO THE TRIBUNAL:
Mr. Martin Doe Rodríguez
REGISTRY:
Permanent Court of Arbitration
29 April 2024
[Page i]
[Page iv]
| 10% Fee Cap | 10% fee cap established in Clause 3 of the Contract |
| 2000-2001 Resolutions | AFIP Resolutions Nos. 792/00, 822/00, 840/00, 910/00, 955/01, 1099/01, adopted between March 2000 and September 2001, excluding certain goods from the Programme |
| AFIP | Federal Administration of Public Income (Administración Federal de Ingresos Públicos) |
| Argentina (or the Respondent) | The Argentine Republic |
| Auditor | Private auditing firm selected by public tender to oversee together with SIGEN the work performed by Inspection Companies under the Programme |
| Award on Jurisdiction | Award on Jurisdiction issued by the Tribunal on 8 July 2019 |
| BIT | Bilateral investment agreement |
| CIF | Cost, Insurance and Freight |
| Claimant (or ICS) | ICS Inspection and Control Services Limited |
| Claimant’s Reply | Claimant’s Reply Memorial, dated 10 June 2020 |
| Committee | Committee for the Programme of Pre-shipment Inspection of Importations (Comité Ejecutivo del Programa de Inspección de Preembarque de Importaciones) |
| Contract | Agreement entered into by the Claimant and MECON on 11 March 1998, relating to the provision of auditing services by the Claimant in the context of the Programme |
| Decree 214/02 | Presidential Decree No. 214/02, dated 4 February 2002 |
| Decree 477/97 | Presidential Decree No. 477/97, dated 30 May 1997 |
| Decree 1060/2001 | Presidential Decree No. 1060/2001, dated 24 August 2001 |
| DGA | Argentine General Customs Directorate (Dirección General de Aduanas) |
[Page v]
| DGAJ | Argentina’s Directorate General of Legal Affairs |
| EMBI | Emerging Market Bond Index |
| Emergency Law | Law No. 25.561, enacted on 6 January 2002 |
| Executive Committee | Executive Committee of the Pre-shipment Inspection of Imports Programme (Comité Ejecutivo del Programa de Inspección de Preembarque de Importaciones) |
| FET | Fair and equitable treatment |
| First Acosta Statement | First Witness Statement of Amelia Acosta, dated 3 December 2019 |
| First Bianchi Report | First Expert Report of Alberto Bianchi, dated 16 December 2015 |
| First Comadira Report | First Expert Report of Julio Pablo Comadira, dated 4 December 2019 |
| First Cupello Statement | First Witness Statement of Angela Cupello, dated 3 December 2019 |
| First Dapena Report | First Expert Report of José P. Dapena, dated 2 December 2019 |
| First Dellepiane Report | First Expert Report of Santiago Dellepiane Avellaneda, dated 15 December 2015 |
| First Santamaría Statement | First Witness Statement of Juan Antonio Santamaría, dated 16 December 2015 |
| FPS | Full protection and security |
| Hearing on Jurisdiction | Hearing on jurisdiction held on 28 February and 1 March 2017 in The Hague, the Netherlands |
| Hearing on the Merits | Hearing on the merits held by videoconference on 6-9 and 12-14 April 2021 |
| ICS (or the Claimant) | ICS Inspection and Control Services Limited |
| ICS I arbitration | Arbitration proceedings commenced by the Claimant against the Respondent on 30 June 2009pursuant to Article 8 of the Treaty and the UNCITRAL Rules |
| ILC | International Law Commission |
[Page vi]
| ILC Articles | ILC Draft Articles on Responsibility of States for Internationally Wrongful Acts, 2001 |
| Inspection Certificate | Pre-shipment inspection certificate |
| Inspection Companies | Accredited inspection companies under the Programme |
| LPA | National Law of Administrative Procedures No. 19.549 |
| MECON | Ministry of Economy and Public Finances of the Argentine Republic (Ministerio de Economía y Finanzas Públicas de la República Argentina) |
| Ostram | Ostram Holding Services, a company constituted under the laws of the Cayman Islands and the assignee of ICS’s rights |
| Parties | The Claimant and the Respondent |
| PCA | Permanent Court of Arbitration |
| Pesos | Argentine pesos |
| Programme | The Programme of Pre-shipment Inspection of Importations, a government-supervised programme under which goods bound for import into Argentina would be inspected prior to shipment to Argentina |
| Ratti Statement | Witness statement of Eduardo Ratti, dated 29 November 2019 |
| Resolution 325 | MECON’s Resolution No. 325, approved on 10 January 2006 |
| Resolution 1106/98 | MECON’s Resolution No. 1106/98, approved on 9 September 1998 |
| Respondent | The Argentine Republic |
| Rejoinder | Respondent’s Rejoinder Memorial, dated 9 December 2020 |
| Second Acosta Statement | Second Witness Statement of Amelia Acosta, dated 30 November 2020 |
| Second Bianchi Report | Second Expert Report of Alberto Bianchi, dated 10 June 2020 |
| Second Comadira Report | Second Expert report of Julio Pablo Comadira, dated 3 December 2020 |
[Page vii]
| Second Cupello Statement | Second Witness Statement of Angela Cupello, dated 30 November 2020 |
| Second Dapena Report | Second Expert Report of José P. Dapena, dated 4 December 2020 |
| Second Dellepiane Report | Second Expert Report of Santiago Dellepiane Avellaneda, dated 10 June 2020 |
| Second Santamaría Statement | Second Witness Statement of Juan Antonio Santamaría, dated 10 June 2020 |
| SIGEN | National Internal Auditing Commission (Sindicatura General de la Nación) |
| Special Services | Alleged additional non-audit services performed by the Claimant |
| Statement of Claim | Claimant’s Statement of Claim, dated 16 December 2015 |
| Statement of Defence | Respondent’s Statement of Defence, dated 6 December 2019 |
| Tender No. 13/97 | Public tender process for the selection of the Auditor, launched on 30 May 1997 |
| Tender Terms and Conditions | Terms and conditions of Tender No. 13/97 |
| Treaty | Agreement between the Government of the Republic of Argentina and the Government of the United Kingdom of Great Britain and Northern Ireland for the Promotion and Protection of Investments, dated 11 December 1990 |
| Umbrella Clause | Obligation of the Contracting Parties to the Treaty under Article 2(2) to “observe any obligation it may have entered into with regard to investments of investors of the other Contracting Party” |
| UNCITRAL Rules | Arbitration Rules of the United Nations Commission on International Trade Law (as revised in 2010) |
| VCLT | Vienna Convention on the Law of Treaties, Concluded at Vienna on 23 May 1969 |
| WACC | Weighted average cost of capital |
[Page 1]
1. The Claimant in these proceedings is ICS Inspection and Control Services Limited (formerly known as Swipco Limited) (“ICS” or the “Claimant"), a company incorporated, constituted, and registered under the laws of England and Wales, with registered number 03186918, having its registered office at 5th Floor, 86 Jermyn Street, London SW1Y 6AW. The Claimant is represented in this case by:
Ms. Rajinder Bassi
Mr. Chris Colbridge (until 13 September 2023)
Mr. Philipp Kurek (until 13 September 2023)
Kirkland & Ellis International LLPMr. Samuel Wordsworth KC
Mr. Lucas Bastin
Essex Court Chambers
2. The Respondent in these proceedings is the Argentine Republic (the "Respondent" or "Argentina", and together with the Claimant, the “Parties”). The Respondent is represented in this case by:
Dr. Rodolfo Carlos Barra, Procurador General de la Nación
Dr. Carlos Alberto Zannini, Procurador General de la Nación (until 14 December 2023)
Dr. Horacio Pedro Diez, Subprocurador del Tesoro de la Nación (until 14 December 2023)
Dr. Sebastián Antonio Soler, Subprocurador del Tesoro de la Nación (until 14 December 2023)
Dra. Mariana Mabel Lozza, Directora Nacional de Asuntos y Controversias Internacionales
Procuración del Tesoro de la Nación
3. The Tribunal is composed of Mr. Pierre-Yves Tschanz (appointed by the Claimant), Professor Dr. Domingo Bello Janeiro (appointed by the Respondent), and Mr. Jernej Sekolec, appointed by the Secretary General of the Permanent Court of Arbitration (the “PCA”) in his capacity as the appointing authority in this matter. Their contact details are as follows:
Mr. Pierre-Yves Tschanz
Tschanz Arbitration
c/o Lawffice SA, 22 rue du Général-Dufour
[Page 2]
PO Box 315
1211 Geneva 4
Switzerland
Tel.: +41 22 500 1456
E-mail: [email protected]Prof. Dr. Domingo Bello Janeiro
Facultad de Derecho
Universidad de La Coruña
Campus de Elviña, s/n. 15071
La Coruña, Spain
Tel.: +34 981167000, ext. 1546
E-mail: [email protected]Mr. Jernej Sekolec
Scheibenbergstraße 38/2/32
A-1180 Vienna
Austria
Tel: +43 720 308 971
E-mail: [email protected]
4. The arbitration concerns the Claimant's allegation that the Respondent breached its obligations under Article 2 of the Treaty through the treatment accorded to the Claimant by Argentina in connection with an agreement entered into by the Claimant and Argentina's Ministry of Economy and Public Finances, the Ministerio de Economía y Finanzas Públicas de la República Argentina (formerly Ministerio de Economía y Obras y Servicios Públicos) (“MECON") on 11 March 1998, relating to the provision of auditing services by the Claimant (the “Contract”) in the context of a government-supervised programme under which goods bound for import into Argentina would be inspected prior to shipment to Argentina (the “Programme”).1
5. The following quotation from the Claimant's Statement of Claim summarises the main aspects of the dispute:
4. In summary, and as described in more detail below, the dispute between the parties (which has been the subject of numerous proceedings between the parties for more than a decade) arises with regard to the treatment accorded to the Claimant by the Argentine Republic (“Argentina” or the “Respondent”) in connection with an agreement entered into by the Claimant and Argentina's Ministry of Economy and Public Finances, the Ministerio de Economía y Finanzas Públicas de la República Argentina (formerly Ministerio de Economía y Obras y Servicios Públicos) ("MECON") on 11 March 1998, relating to the provision of auditing services by the Claimant (the "Contract") in the context of a government-supervised programme
1 Claimant's Statement of Claim, dated 16 December 2015, para. 4. See also, Respondent's Memorial on Objections to the Jurisdiction of the Arbitral Tribunal, dated 15 April 2016, para. 4. ↩
[Page 3]
under which goods bound for import into Argentina would be inspected prior to shipment to Argentina (the "Programme").
5. The Contract provided that the Claimant, together with Argentina's National Internal Auditing Commission, the Sindicatura General de la Nación (“SIGEN”), was to audit the pre-shipment inspection of imports into Argentina (the "Ordinary Services").
6. In addition to the Claimant's Ordinary Services, Argentina also requested the Claimant to provide additional non-audit services on an ad hoc basis from time to time (the "Special Services”), which were to be remunerated based on the market value of such services.
7. The Claimant's fees for Ordinary Services were to be calculated as a percentage of the FOB, FOR or FOT2 value of each audited inspection certificate (invariably denominated in US Dollars), with the caveat that the Claimant's fees for each quarter could not be less than 4% of the amount invoiced by the inspection companies, nor exceed 10% of the amount invoiced by the inspection companies (the "10% Fee Cap"). In this respect, so as to enable the Claimant to comply with the 10% Fee Cap, the Contract required Argentina to implement an adequate selection system to identify shipments to be audited.
8. From the outset, there were significant issues with the selection of certificates to be audited. Despite its clear and unequivocal obligations to do so, and in spite of the Claimant's repeated complaints and requests, Argentina never implemented a functioning framework for the services to be rendered by the Claimant.
9. Argentina's failure to implement an adequate selection system made it impossible for the Claimant to comply with the 10% Fee Cap. As a matter of Argentine law, therefore, Argentina was precluded from invoking the 10% Fee Cap vis-à-vis the Claimant, who was consequently entitled to full payment of its Ordinary Service fees, irrespective of whether such fees were above or below the cap.
10. When Argentina decided to terminate the Programme in late 2001, the Claimant issued final invoices for services rendered and requested that Argentina settle all outstanding invoices.
11. On 6 January 2002, Argentina enacted Law 25.561 (the “Emergency Law”), repealing Law 23.928 (the "Convertibility Law") which for the last ten years had stabilised the exchange rate between the Argentine Peso and the US Dollar such that 1 Argentine Peso was equal to 1 US Dollar. The Emergency Law also granted special powers to the President to determine the exchange rate between the Argentine Peso and any other foreign currency. In this context, the President issued Decree 214/02 which provided that (i) obligations to pay sums of money in US Dollars existing as of the time of the enactment of the Emergency Law were to be translated into Argentine Pesos; and (ii) enforceable obligations to pay sums of money in US Dollars should be translated at a rate of 1:1, adding a Stabilisation Ratio (Coeficiente de Estabilización de Referencia “CER") published by Argentina's Central Bank.
12. Despite the Claimant's repeated demands for payment, the outstanding invoices remained unpaid. Accordingly, in March 2002 the Claimant filed an administrative claim seeking payment of its outstanding invoices.
13. In August and September 2002, whilst the administrative claim was still pending before MECON, the Comité Ejecutivo del Programa de Inspecciones de Preembarque de Importaciones (the “Committee") (the body responsible for the day-to-day supervision and enforcement of the Programme) wrote to the Claimant:
(a) rejecting the Claimant's invoices for Ordinary Services and demanding that:
(i) the invoices be reduced to comply with the 10% Fee Cap;
(ii) the invoices be pesified (i.e. re-issued in Pesos using the by then historic 1:1 US Dollar/Peso exchange rate); and
[Page 4]
(b) rejecting the Claimant's Special Services invoices.
14. Furthermore, in June 2003 Argentina wrote to the Claimant demanding a further 13% reduction of certain invoices, purportedly in accordance with Presidential Decree 1060/01 ("PD 1060/01").
15. In order to ease the Claimant's rapidly deteriorating financial position and to recover at least some of the outstanding amounts, the Claimant eventually gave in to Argentina's demands and re-issued reduced and pesified invoices (whilst expressly reserving its rights in respect of these wrongful reductions).
16. In December 2004, with the dispute between the parties still unresolved, the Claimant filed an updated and amplified administrative claim (taking into account the above wrongful reductions).
17. In 2006, after years of negotiations, Argentina finally paid the Claimant ARS 1,230,181.68 in part-payment of the Claimant's outstanding invoices. However, Argentina did not (and to date has not) made any payments in respect of:
(a) amounts above the 10% Fee Cap in relation to the Claimant's Ordinary Services invoices;
(b) amounts relating to Argentina's pesification of the Claimant's invoices;
(c) amounts relating to Argentina's 13% reduction of certain of the Claimant's invoices pursuant to its purported application of PD 1060/01; and
(d) any of the Special Services performed by the Claimant.
18. In light of Argentina's refusal to make any further payment to the Claimant in respect of its Ordinary and Special Services invoices, the Claimant formally notified Argentina of its claim under the BIT by notice of 27 November 2006.
19. Despite the Claimant's best efforts to settle the dispute, including a period of settlement discussions between December 2006 and April 2007, the parties failed to reach an amicable settlement. Accordingly, in June 2009 (with the administrative claim still unresolved) the Claimant commenced arbitration under the UNCITRAL Rules pursuant to the terms of the Agreement between the Government of the United Kingdom of Great Britain and Northern Ireland (the "UK") and Argentina for the Promotion and Protection of Investments (the "BIT"). In November 2010, Argentina formally objected to the Tribunal's jurisdiction on the basis that the Claimant had failed to first submit the dispute to the Argentine courts before commencing arbitration. In accordance with the Tribunal's First Procedural Order, the proceedings on the merits were suspended pending the Tribunal's determination of the question of jurisdiction under the BIT. Following an oral hearing in The Hague, the Tribunal rendered its Award in February 2012, finding that it did not have jurisdiction over the dispute due to the Claimant's failure to first submit the dispute to the Argentine courts for a period of at least 18 months.
20. Following the Tribunal's Award on jurisdiction, the Claimant duly submitted the dispute to the Argentine courts in February 2012.
21. Almost two years elapsed, and despite having diligently pursued its claim, the proceedings had not (and still have not) even reached the evidentiary stage yet. Faced with the Argentine courts' inability or unwillingness to resolve the dispute in a timely manner, the Claimant had no choice but to once again resort to international arbitration under the BIT in order to finally be duly compensated (as it should have been more than a decade ago) for the services it has provided to Argentina.
22. Accordingly, by Notice of Arbitration dated 21 July 2014, the Claimant commenced arbitration proceedings against Argentina pursuant to Article 8 of the BIT and the UNCITRAL Rules.
23. In its Notice of Arbitration, and as further particularised in this Statement of Claim, the Claimant asserts that Argentina breached Article 2(2) of the BIT by:
[Page 5]
(a) failing to afford the Claimant's investment fair and equitable treatment;
(b) treating the Claimant's investment in an unreasonable or discriminatory manner; and
(c) failing to afford the Claimant's investment full protection and constant security; and
(d) failing to observe the obligations Argentina has entered into with regards to the Claimant's investment;
causing the Claimant a loss of USD 128 million.
24. Argentina has consented to this dispute being submitted to international arbitration under the UNCITRAL Rules through its offer to arbitrate made in Article 8 of the BIT. By filing its Notice of Arbitration and instituting proceedings against Argentina, the Claimant accepted Argentina's offer.2
6. The Respondent submits that the Claimant's claims are precluded on the basis of a number of preliminary objections, that the Claimant's claims have no merit and that, in any event, necessity under customary international law would preclude any unlawfulness of its conduct. The Respondent further submits that the Claimant is not entitled to the relief it seeks.
7. On 8 July 2019, the Tribunal issued its Award on Jurisdiction (the “Award on Jurisdiction”), in which it decided "that it has jurisdiction to consider the claims raised by the Claimant" and that it "defer[red] all questions not decided [in the Award on Jurisdiction] to the next phase of the proceedings", notably including the Respondent's defences pertaining to acquiescence and extinctive prescription.3
2 Statement of Claim, paras. 4-24 (emphasis and footnotes omitted). ↩
3 Award on Jurisdiction, paras. 379-380. ↩
[Page 6]
8. The Tribunal's Award on Jurisdiction recounts in detail the procedural history of this arbitration from its commencement up until the date it was rendered.4 The following sections recall only the key procedural details from the early phase of the proceedings and summarizes developments since 8 July 2019.
9. By Notice of Arbitration dated 21 July 2014, the Claimant commenced arbitral proceedings against the Respondent under the Arbitration Rules of the United Nations Commission on International Trade Law (the “UNCITRAL Rules") pursuant to Article 8 of the Agreement between the Government of the Republic of Argentina and the Government of the United Kingdom of Great Britain and Northern Ireland for the Promotion and Protection of Investments, dated 11 December 1990, entered into force on 19 February 1993 (the “Treaty”).5
10. Pursuant to Article 3(2) of the UNCITRAL Rules, arbitral proceedings are deemed to have commenced on the date on which the Notice of Arbitration was received by the Respondent, i.e., 1 August 2014.
11. On 20 November 2014, the Claimant appointed Mr. Pierre-Yves Tschanz as the first arbitrator.
12. On 18 December 2014, the Respondent appointed Professor Domingo Bello Janeiro as the second arbitrator.
13. On 8 June 2015, the Secretary-General of the PCA appointed Mr. Jernej Sekolec as presiding arbitrator.
14. On 29 July 2015, the Tribunal issued Procedural Order No. 1, which included Terms of Appointment for the Tribunal. Paragraph 12 of Procedural Order No. 1 foresaw the possibility for the Respondent to contest the Tribunal's jurisdiction as a preliminary matter.
4 Award on Jurisdiction, Section III. ↩
[Page 7]
15. On 16 December 2015, the Claimant submitted its Statement of Claim (the "Statement of Claim") accompanied by the witness statement of Juan Antonio Santamaría (the “First Santamaría Statement"), the expert report of Alberto Bianchi (the “First Bianchi Report"), and the expert report of Santiago Dellepiane Avellaneda (the “First Dellepiane Report").
16. On 15 April 2016, the Respondent submitted its Memorial on Objections to the Jurisdiction of the Arbitral Tribunal.
17. On 5 August 2016, the Claimant submitted its Counter-Memorial on Jurisdiction.
18. On 20 October 2016, the Respondent submitted its Reply-Memorial on Objections to the Jurisdiction of the Arbitral Tribunal.
19. On 9 January 2017, the Claimant submitted its Rejoinder on Jurisdiction.
20. On 15 February 2017, the Tribunal issued Procedural Order No. 2.
21. On 28 February and 1 March 2017, a hearing on jurisdiction was held at the Peace Palace in The Hague, the Netherlands (the “Hearing on Jurisdiction").
22. On 8 July 2019, the Tribunal issued its Award on Jurisdiction, in which the Tribunal decided:
a) that it has jurisdiction to consider the claims raised by the Claimant; and
b) to defer all questions not decided herein to the next phase of the proceedings.6
23. In particular, with respect to the Respondent's defences of acquiescence and prescription, the Tribunal held as follows:
The Tribunal considers it more prudent to postpone consideration of acquiescence and prescription to the merits stage
On the basis of the Parties' positions summarized above in paragraphs 369-378, the Tribunal accepts that the defences of acquiescence and extinctive prescription address the substance of the dispute and not the power of the Tribunal to rule on them. That characterization of the defences in itself would not necessarily prevent the Tribunal from ruling on the defences in the present award. Nevertheless, the Tribunal considers that the factual basis for reaching a decision on the defences may require an assessment of the Parties' behaviour and statements over a long period of time during and after the performance of the Contract, while the legal considerations may involve points of international law and the interaction of international and national law. Because of the complexity of those considerations, the Tribunal is of the
6 Award on Jurisdiction, para. 380. ↩
[Page 8]
view that it is more prudent to postpone these considerations to the merits stage, when the Tribunal will be sure that it has before it the complete factual and legal basis of the dispute.7
24. On 18 July 2019, the Tribunal issued Procedural Order No. 3, in which it established a procedural timetable for the merits phase of the proceedings.
25. By letter dated 15 August 2019, the Tribunal determined that a hearing on the merits would be held for up to five hearing days from 1 to 5 March 2021 (the “Hearing on the Merits").
26. By e-mail of 26 August 2019, the Tribunal adopted an amended procedural calendar which had been agreed upon by the Parties on 23 August 2019.
27. On 6 December 2019, the Respondent submitted its Statement of Defence (the "Statement of Defence") accompanied by the expert report of Julio Pablo Comadira (“First Comadira Report"), the expert report of José P. Dapena (“First Dapena Report”), the witness statement of Amelia Acosta (“First Acosta Statement”), the witness statement of Angela Cupello ("First Cupello Statement"), and the witness statement of Eduardo Ratti (“Ratti Statement").
28. On 7 February 2020, the Claimant submitted its requests for document production. On 27 February 2020, the Respondent submitted its responses and objections to the Claimant's requests for document production, and the Claimant thereafter submitted its responses to the Respondent's objections and requested a Tribunal decision on disputed requests on 9 March 2020.
29. On 3 April 2020, the Tribunal issued Procedural Order No. 4, ruling on the Claimant's document production requests.
30. On 10 June 2020, the Claimant submitted its Reply Memorial (the "Reply") accompanied by the second witness statement of Juan Antonio Santamaría (“Second Santamaría Statement"), the second expert report of Dr. Alberto B. Bianchi (“Second Bianchi Report”), and the second expert report of Santiago Dellepiane Avellaneda (“Second Dellepiane Report").
31. On 10 August 2020, the Respondent submitted its document production requests. On 1 September 2020, the Claimant submitted its responses and objections to the Respondent's document
7 Award on Jurisdiction, para. 379. ↩
[Page 9]
production requests, and the Respondent thereafter submitted its responses to the Claimant's objections and requested a Tribunal decision on disputed requests on 11 September 2020.
32. On 1 October 2020, the Tribunal issued Procedural Order No. 5, ruling on the Respondent's document production requests.
33. On 9 December 2020, the Respondent submitted its Rejoinder Memorial (the "Rejoinder") accompanied by the second expert report of Julio Pablo Comadira (“Second Comadira Report”), the second expert report of José P. Dapena (“Second Dapena Report"), the second witness statement of Amelia Acosta (“Second Acosta Statement"), and the second witness statement of Angela Cupello (“Second Cupello Statement").
34. On 26 January 2021, following a request by the Respondent, and after giving Claimant an opportunity to comment thereon, the Tribunal re-scheduled the Hearing on the Merits so that it would be held by videoconference for up to seven hearing days on 6-9 and 12-14 April 2021.
35. On 4 February 2021, the Tribunal circulated a draft of Procedural Order No. 6, regarding the upcoming Hearing on the Merits, for the Parties' comments.
36. On 23 February 2021, the Parties submitted simultaneously their notifications of the witnesses which they intended to cross-examine at the Hearing on the Merits.
37. On 11 March 2021, the Tribunal, the Parties, and the PCA held a pre-hearing videoconference.
38. On 15 March 2023, the Tribunal issued Procedural Order No. 6, regarding the Hearing on the Merits.
39. Between 6-9 and 12-14 April 2021, the Parties and the Tribunal held the Hearing on the Merits by videoconference.
40. The following persons participated in the Hearing on the Merits:
Tribunal
Mr. Jernej Sekolec (Presiding Arbitrator)
Mr. Pierre-Yves Tschanz
Prof. Dr. Domingo Bello Janeiro
[Page 10]
Claimant
Bassam Khoury
Carlos Schiopetto
Party RepresentativesSamuel Wordsworth
Lucas Bastin
Essex Court ChambersChris Colbridge
Philipp Kurek
Alexander Rayner
Kirkland & Ellis International LLPFederico Sivak
Lauren Winne
Berkeley Research GroupRespondent
Carlos Alberto Zannini
Sebastián Soler
Mariana Lozza
María Alejandra Etchegorry
José Ryb
Annabella Sandri Fuentes
María Laura Pessarini
Carolina Catanzano
Agustina Antoci Richieri
Julian Rivainera
Nicolás Duhalde
Emiliano Leanza
Adriana Cusmano
Daiana Ruth Baranchuk
Procuración del Tesoro de la NaciónPCA
Mr. Martin Doe Rodríguez (Secretary to the Tribunal)
Ms. Marihu Contreras Medina
Ms. Alejandra MartinovicCourt Reporters
Mr. David Kasdan
Mr. Dante Rinaldi
Ms. Eliana Da Silva
Ms. Regina SpectorInterpreters
Ms. Silvia Colla
Mr. Daniel Giglio
[Page 11]
41. The following fact and expert witnesses were examined at the Hearing on the Merits:
Fact Witnesses
Juan Antonio Santamaría
Amelia Ana Acosta
Angela Beatriz CupelloLegal Experts
Alberto Bianchi
Julio Pablo ComadiraDamages Experts
Santiago Dellepiane
Jose P. Dapena
42. The Parties and the Tribunal exchanged several communications between 11 May and 1 June 2021 concerning the corrections to the transcripts. On 2 June 2021, the Tribunal informed the Parties that it adopted the revisions agreed by the Parties but not the additional ones proposed by the Respondent relating to translation errors. The Tribunal further noted to the Parties that it would rely principally on the original language of argument and testimony in its deliberations.
[Page 12]
43. The Claimant requests the following relief:
(a) a declaration that Argentina breached Article 2(2) of the BIT;
(b) damages for breach of the BIT as set out in Section (D) [of its Reply];
(c) an order that Argentina pay all costs incurred in connection with these arbitral proceedings, including (but not limited to) the costs of the Tribunal, the appointing authority, as well as any legal and other fees, costs and/or expenses incurred by the Claimant, including legal fees, expert fees and costs in respect of the time spent by the Claimant's own employees;
(d) an order that Argentina pay post-Award interest on all sums awarded at the maximum permitted rate until payment in full; and/or
(e) such other relief as the Tribunal may deem appropriate.8
44. The Respondent requests the Tribunal to:
(a) to admit the defences raised by the Argentine Republic;
(b) to dismiss each and all of the claims put forward by Claimant; and
(c) to order Claimant to pay for all costs and expenses arising from these arbitration proceedings.9
8 Claimant's Reply, para. 209. ↩
[Page 13]
45. The question to be decided in the present phase of the proceedings concerns whether the Respondent has breached Article 2(2) of the Treaty and whether the Claimant is entitled to the damages it seeks. The resolution of this disagreement between the Parties depends on the proper interpretation of Article 2(2) of the Treaty.
46. Article 2 provides as follows:
ARTICLE 2
Promotion and Protection of Investment
(1) Each Contracting Party shall encourage and create favourable conditions for investors of the other Contracting Party to invest capital in its territory, and, subject to its right to exercise powers conferred by its laws, shall admit such capital.
(2) Investments of investors of each Contracting Party shall at all times be accorded fair and equitable treatment and shall enjoy protection and constant security in the territory of the other Contracting Party. Neither Contracting Party shall in any way impair by unreasonable or discriminatory measures the management, maintenance, use, enjoyment or disposal of investments in its territory of investors of the other Contracting Party. Each Contracting Party shall observe any obligation it may have entered into with regard to investments of investors of the other Contracting Party.
47. In addition to the relevant provisions of the Treaty, it is instructive to reproduce here the rules on the interpretation of treaties set forth in Articles 31 and 32 of the Vienna Convention on the Law of Treaties (the “VCLT”), which both Parties acknowledge govern the interpretation of the Treaty:
Article 31
General rule of interpretation
1. A treaty shall be interpreted in good faith in accordance with the ordinary meaning to be given to the terms of the treaty in their context and in the light of its object and purpose.
2. The context for the purpose of the interpretation of a treaty shall comprise, in addition to the text, including its preamble and annexes:
(a) any agreement relating to the treaty which was made between all the parties in connection with the conclusion of the treaty;
(b) any instrument which was made by one or more parties in connection with the conclusion of the treaty and accepted by the other parties as an instrument related to the treaty.
3. There shall be taken into account, together with the context:
[Page 14]
(a) any subsequent agreement between the parties regarding the interpretation of the treaty or the application of its provisions;
(b) any subsequent practice in the application of the treaty which establishes the agreement of the parties regarding its interpretation;
(c) any relevant rules of international law applicable in the relations between the parties.
4. A special meaning shall be given to a term if it is established that the parties so intended.
Article 32
Supplementary means of interpretation
Recourse may be had to supplementary means of interpretation, including the preparatory work of the treaty and the circumstances of its conclusion, in order to confirm the meaning resulting from the application of article 31, or to determine the meaning when the interpretation according to article 31:
(a) leaves the meaning ambiguous or obscure; or
(b) leads to a result which is manifestly absurd or unreasonable.
[Page 15]
48. In the following sections, the factual background discussed by the Parties in their submissions is summarized to provide context for the decision of the Tribunal. Where relevant, it is indicated where the Parties' respective accounts of the facts differ.
49. On 30 May 1997, the President of Argentina issued Decree 477/97 (“Decree 477/97”) approving a programme for the compulsory pre-shipment inspection of goods to be imported into its territory.10 The Programme had, among others, the objective of reducing or eliminating incorrect or imprecise import declarations, and as a result, detecting and combatting tax avoidance and evasion, unfair competition, and non-compliance with customs regulations.11
50. Pursuant to Decree 477/97, importers of consumer goods, passenger vehicles, and automobiles as well as any other goods determined by MECON were required to follow a procedure for the inspection of such goods prior to shipment.12 The importing company had to submit a request for inspection to one of the accredited inspection companies under the Programme (the “Inspection Companies").13 Thereafter, the Inspection Company would conduct a physical inspection, which would take place in most cases in the country of origin of the goods, and issue a pre-shipment inspection certificate (an “Inspection Certificate”) recording any inconsistencies between the physical inspection and the request for inspection.14
51. MECON was the enforcement authority for the Programme.15 MECON was responsible for issuing any clarifying or complementary regulations that were necessary for the proper implementation of the Programme and had the authority to select through a public tender the specialized companies that would undertake any implementing functions under the Programme.16
52. The Executive Committee for the Programme of Pre-shipment Inspection of Importations (Comité Ejecutivo del Programa de Inspección de Preembarque de Importaciones) (the “Committee")
10 Decree 477/97, Article 1 (C-6). ↩
11 Decree 477/97, Annex 1, Section (a) (“Objetivos del Programa”) (С-6). ↩
12 Decree 477/97, Annex 1, Section (g) (C-6). ↩
13 Decree 477/97, Annex 1, Section (f)(I)-(II) (C-6). ↩
14 Decree 477/97, Annex 1, Section (f)(III)-(VIII) (C-6). ↩
15 Decree 477/97, Article 6 (C-6). ↩
16 Decree 477/97, Article 6 (C-6). ↩
[Page 16]
was established as the body responsible for supervising the activities related to the Programme.17 The functions of the Committee included holding a registry of the system of pre-shipment inspection of importations and receiving, controlling and verifying the documentation provided by the Inspection Companies in order to claim payments for their services and coordinate the auditing tasks of the Inspection Companies.18
53. The Inspection Companies were to be selected by public tender and were bound to verify the compliance of the inspected goods with the regulations and standards specified in Decree 477/97.19
54. The tasks performed by the Inspection Companies were to be overseen by the National Internal Auditing Commission (Sindicatura General de la Nación) (“SIGEN”), as well as by a private auditing firm (the “Auditor”) to be selected by public tender.20
55. On 7 August 1997, a national and international public tender process for the selection of the Auditor was commenced by MECON (“Tender No. 13/97”).21 The terms and conditions of Tender No. 13/97 (“Tender Terms and Conditions”) outlined the services to be provided by the Auditor, indicating that the auditing company would “act independently and [would] verify the quantity, quality and customs classification of imported goods, at the point of their final destination for consumption, and will verify the prices" as per the applicable regulations.22 The Tender Terms and Conditions also specified that the “currency of payment” would be Argentine pesos ("Pesos") and that the fees for the auditing services would be paid by the Federal Administration of Public Income (Administration Federal de Ingresos Públicos) (“AFIP”).23
17 Decree 477/97, Annex I, Section (i)(I) (C-6). ↩
18 Decree 477/97, Annex I, Section (i)(I) (C-6). ↩
19 Decree 477/97, Article 6, Annex I, Section (c)(I) (C-6). ↩
20 Decree 477/97, Article 4 (C-6). ↩
21 MECON, Call for Public Tender No. 13/97, 7 August 1997, attaching Terms and Conditions (C-9). ↩
22 MECON, Call for Public Tender No. 13/97, 7 August 1997, attaching Terms and Conditions, Section VIII (C-9). ↩
23 MECON, Call for Public Tender No. 13/97, 7 August 1997, attaching Terms and Conditions, Sections V-VI (C-9). ↩
[Page 17]
56. On 17 October 1997, MECON approved the Resolution No. 1177/97, identifying the tariff codes of the goods that were subject to the Programme.24
57. On 24 November 1997, the Argentine General Customs Directorate (Dirección General de Aduanas) (“DGA") approved Resolution No. 396/97 setting forth the regulatory and operative provisions applicable to the Programme (“Resolution 396/97”).25 Resolution 396/97 reiterated that importers of consumer goods were required to submit an Inspection Certificate.26 Upon arrival to Argentina, the Inspection Certificates were subject to the selection regime in force.27 In this regard, Annex VIII to Resolution 396/97 established that the shipments could be processed by customs within three different channels:
a) green channel: which only required verifying the existence of an Inspection Certificate to release the goods from customs;
b) orange channel: which required a revision of the relevant documentation, that could lead to the release of the goods—if approved—or to a physical inspection; and
c) red channel: which required a verification of the relevant documents and a physical inspection of the goods.28
58. If, following a physical inspection, the customs agency verified that there were inconsistencies between the inspected goods and the Inspection Certificates that exceeded a given threshold, such inconsistencies would be reported to the Committee.29 In such circumstances, the Committee would process the relevant merchandise pursuant to the applicable regulations.30 Annex VIII
24 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex V (R-18). ↩
25 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997 (R-18). ↩
26 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex II, Section I (R-18). ↩
27 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex III, Sections 3.1, 4.1 (R-18). ↩
28 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex VIII (R-18). ↩
29 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex VIII (R-18). ↩
30 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex VIII (R-18). ↩
[Page 18]
further established that all the Inspections Certificates that recorded inconsistencies would be processed through the red channel.31
59. On 18 February 1998, the Claimant was declared the successful bidder of Tender No. 13/97.32
60. Thereafter, on 11 March 1998, the Claimant and MECON concluded the Contract, under which the Claimant agreed to oversee, together with SIGEN, the work performed by the Inspection Companies.33 The Contract stipulated that the following documents formed an integral part of the Contract:
a) Decree 477/97;
b) the Tender Terms and Conditions;
c) Technical Committee Notices Nos. 5 and 6;
d) the offers consisting of "Legal Documents, Background and Technical Proposal" and "Price Proposal"; and
e) the letter submitted by the Claimant, dated 3 October 1997, clarifying the price proposal.34
61. The Contract had an initial term of two years, renewable for an additional year.35
62. Under the Contract, the Claimant agreed to audit shipments of goods covered by the Programme by conducting physical inspections at the point of destination, as well as to verify the quantity, quality, tariff classification, and price of the relevant goods as per the applicable valuation rules.36 In particular, the Contract described the Claimant's audit obligations as follows:
CLAUSE ONE: PURPOSE OF THE CONTRACT – The “AUDITOR” undertakes, jointly with the NATIONAL SUPERVISORY AUTHORITY, to audit the pre-shipment inspection
31 DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997, Annex VIII (R-18). ↩
32 MECON, Resolution No. 218/1998, 18 February 1998 (C-11). ↩
34 Contract, Clause 2 (C-2). ↩
35 Contract, Clause 4 (C-2). ↩
36 Contract, Clauses 6-8 (C-2). ↩
[Page 19]
of imports companies, in accordance with the terms of the Specification Sheet and their Bid, which was awarded by MEyOySP Resolution No. 218/98 issued in Public National and International Tender No. 13/97, entered in the Dossier of the Register of the Ministry of Economy and Public Works and Services No. 090-000423/97 and to deliver the results of such task to the EXECUTIVE COMMITTEE in the form and with the frequency decided upon by the latter. All the information presented by the AUDITOR to the EXECUTIVE COMMITTEE must be duly sealed and signed by its legal representative and the AUDITOR undertakes to furnish all the clarifications and explanations which are requested of it.
[...]
CLAUSE SIX: The AUDITOR shall carry out the inspections at the pertinent Customs, taking care to maintain a suitable ratio according to the operations implemented at each, and in all cases must resolve upon the means required to undertake random controls, as well as to comply with the instruction imparted to it by the EXECUTIVE COMMITTEE of the PRE-SHIPMENT INSPECTION OF IMPORTS PROGRAMME, always ensuring that the values in question do not represent a base that may exceed the maximum fee referred to in clause three.
CLAUSE SEVEN: The AUDITOR shall in all cases verify the quantity, quality, classification and price, according to current appraisal principles.
CLAUSE EIGHT: Notwithstanding the specific instructions imparted in certain cases by the EXECUTIVE COMMITTEE, whether to audit specific operations or comply with certain conditions, the AUDITOR shall endeavour to ensure that the dispatches to be audited are determined prior to the arrival of the merchandise, by random means, to be fixed according to the criteria of the EXECUTIVE COMMITTEE and drawn up on the grounds of the reports furnished to it by the inspection companies and by the GENERAL CUSTOMS DEPARTMENT subordinate to the [AFIP], and must make the verification at the point of destination, except in those cases when for duly justified reasons it must be carried out at the place of origin, in which case prior approval by the EXECUTIVE COMMITTEE is required.37
63. In addition, the Claimant was also required to (i) maintain a database of independently assessed Cost, Insurance, and Freight (“CIF”) values for the relevant goods;38 (ii) provide the Committee with monthly reports of its audit operations;39 (iii) report on any defects observed and propose changes to the Programme;40 (iv) develop a manual of auditing procedures; (v) abide by any other instruction given by or submit any other reports requested by the Committee;41 and (vi) cooperate with SIGEN as necessary in order to comply with Decree 477/97.42 In particular, the Contract described these obligations as follows:
CLAUSE NINE: Without prejudice to the statements contained in the preceding clauses, the AUDITOR shall in all cases honour the instructions imparted to it by the EXECUTIVE COMMITTEE, presenting those reports requested as well as cooperate with the NATIONAL
37 Contract, Clauses 1, 6-8 (C-2). ↩
38 Contract, Clause 10 (C-2). ↩
39 Contract, Clause 11 (C-2). ↩
40 Contract, Clauses 13, 15 (C-2). ↩
41 Contract, Clause 9 (C-2). ↩
42 Contract, Clause 9 (C-2). ↩
[Page 20]
SUPERVISORY AUTHORITY in all matters required in order to fulfil the obligation imposed by Decree No. 477/97.
CLAUSE TEN: The AUDITOR shall establish its own CIF values, duly breaking down the cost, freight and insurance, and shall maintain an updated database thereof, for the purpose of the comparisons that may be necessary.
CLAUSE ELEVEN: The AUDITOR shall deliver a monthly report to the EXECUTIVE COMMITTEE, within the TEN (10) calendar days following the close of the calendar month, summarizing the details of the audited operations, comparing its data with those in the possession of the inspection companies and of the customs service, estimating, when pertinent, the incidence on collections ensuing from those differences that have been detected.
CLAUSE TWELVE: The AUDITOR shall, upon request by the EXECUTIVE COMMITTEE, analyse the discrepancies between the verifications made by the GENERAL CUSTOMS DEPARTMENT, subordinate to the [AFIP] and those carried out by the inspection companies, giving the EXECUTIVE COMMITTEE its opinion on the subject.
CLAUSE THIRTEEN: The AUDITOR shall inform the EXECUTIVE COMMITTEE concerning any defect it comes across upon performing its duties, both in the mechanics of the PRE-SHIPMENT INSPECTION OF IMPORTS PROGRAMME, as well as in the conduct of the inspection companies and the GENERAL CUSTOMS DEPARTMENT, subordinate to the [AFIP] and shall likewise make the analyses and draw up the report thereon requested by the EXECUTIVE COMMITTEE, for which purpose it shall request the necessary cooperation from the inspection companies and the GENERAL CUSTOMS DEPARTMENT. Moreover the AUDITOR undertakes, furnishing grounds therefor, to propose changes, deletions and incorporations to the selection criteria established by the EXECUTIVE COMMITTEE as well as changes in methodology and procedures carried out by the inspection companies, aimed at increasing their effectiveness, reliability and transparency.
CLAUSE FOURTEEN: The AUDITOR shall present to the EXECUTIVE COMMITTEE for its approval a manual of procedures dealing with the differing aspects referred to by this contract.
CLAUSE FIFTEEN: The AUDITOR shall analyse the information to which it has access, for the purpose of identifying any flaw in the Pre-Shipment Inspection of Imports Programme and propose the necessary corrective measures to the EXECUTIVE COMMITTEE.
64. For its part, MECON was to pay the Claimant 0.64% of the FOB, FOR, or FOT value of each audited Inspection Certificate. At the same time, the Contract provided that the Claimant's fees for each quarter could not exceed 10% of the amount invoiced by the Inspection Companies (the "10% Fee Cap"), for which purpose a selection system would have to be implemented to identify which shipments to audit. In particular, Clause 3 of the Contract provided as follows:
“THE AUDITOR” undertakes to perform this contract fully in accordance with its quotation included in its Bid in Envelope No. 2 and the clarification concerning the latter, that is, for the sum consisting of ZERO POINT SIXTY FOUR PERCENT (0.64%) of the FOB, FOR or FOT value declared on each inspection certification of audited merchandise. In no case shall the fee to be received by the AUDITOR surpass, during the respective quarter, TEN PERCENT (10%) of the amount invoiced by the inspection companies nor may it be under FOUR PERCENT (4%) thereof, for which purpose, the selection systems to be implemented to identify the shipments to be audited, must take these facts into account.43
43 Contract, Clause 3 (C-2). ↩
[Page 21]
65. The fee of 0.64% of the FOB, FOR or FOT value declared on the Inspection Certificates followed from Decree 477/97 and the Tender Terms and Conditions, which stipulated that the Auditor's fee would be 80% of the Inspection Companies' fees:
The price quoted by the bidder shall be a fixed percentage not exceeding EIGHTY PERCENT (80%) of the value of the inspection services established in section g) paragraph II) subparagraph 1) above.44
66. In turn, Annex I, Section (g)(II)(1) of Decree 477/97 and the Tender Terms and Conditions had stipulated that the Inspection Companies' fees were to be calculated as follows:
ZERO POINT EIGHT PER CENT (0.8%) of the FOB, FOR or FOT value declared on each inspection certificate of merchandise of the IMPORT PRE-SHIPMENT INSPECTION PROGRAMME.
The minimum fee to be charged for each transaction shall be TWO HUNDRED FIFTY UNITED STATES DOLLARS (U$S 250).
Fee amounts shall be paid on a monthly basis by [AFIP] pursuant to the procedure and requirements to be established by the Authority of Application.45
67. The Claimant's fees were to be paid by AFIP as follows:
Payments shall be made monthly in pesos, by the General Administration Bureau of the [AFIP], within THIRTY (30) days following the date the respective invoices are presented, duly approved in accordance with Point c), paragraph VII) of the Specification Sheet. The AUDITOR shall present the invoices pertaining to the duties performed throughout one calendar month, jointly with a summary of the audit reports that have been drawn up, within TEN (10) days of the following month in the form and conditions established by the EXECUTIVE COMMITTEE. Failure to pay at the due time and in the due form shall cause the STATE to be in default, without the need for any demand whatsoever.46
68. Finally, the Contract provided that the Claimant's entitlements were strictly limited to those set forth in the Contract:
The AUDITOR assumes exclusive responsibility for the services that comprise the object of this contract and it shall render them without any kind of employment relationship with the MINISTRY, and it shall not be entitled to receive any benefit, payment, subsidy, compensation or right which is not expressly stipulated or provided for in this contract.47
44 Decree 477/97, Annex III, Section (c)(XI) (C-6) (translation by the Tribunal). ↩
45 Decree 477/97, Annex I, Section (g)(II)(1) (C-6) (translation by the Tribunal on the basis of the Respondent's Closing, Slide 5). ↩
46 Contract, Clause 19 (C-2). ↩
47 Contract, Clause 21 (C-2). ↩
[Page 22]
69. On 9 September 1998, MECON approved Resolution No. 1106/98 (“Resolution 1106/98"), through which it again set the Claimant's fees at “EIGHTY PERCENT (80%) of the fees received by the Inspection companies for each audited Inspection certificate”, and modified the Inspection Companies' fees as follows:
In consideration for their services, inspection companies shall receive ZERO POINT NINE FIVE PER CENT (0.95%) of the FOB, FOR or FOT value declared on each inspection certificate of goods covered by the PRE-SHIPMENT INSPECTION OF IMPORTS PROGRAMME.
The minimum fee to be charged for each transaction shall be ONE HUNDRED TWENTY UNITED STATES DOLLARS (U$S 120).
The resulting amounts shall be paid on a monthly basis by the [AFIP] pursuant to the procedure and requirements to be established by the Authority of Application.48
70. As a result, the Claimant's fees were in effect increased to 0.76% of the FOB, FOR, or FOT value declared on each audited Inspection Certificate. In addition, Resolution 1106/98 established the process to be followed for amounts that could not be correlated with the Inspection Certificates, providing as follows:
When, owing to the nature of the tasks, the amount payable cannot be correlated to certificates of inspection, the audit firm shall draw up a report detailing the costs and fees following normal market practice, which shall be subject to the approval of the [Committee].49
71. Between March 2000 and September 2001, AFIP issued six resolutions through which a number of goods were excluded from the scope of the Programme (the “2000-2001 Resolutions").50
48 Resolution 1106/98, Articles 1(j), 2 (C-8) (translation by the Tribunal on the basis of the Respondent's Closing, Slide 6). ↩
49 Resolution 1106/98, Article 2 (C-8) (translation by the Respondent). ↩
50 AFIP Resolution No. 792/00 "Exclusion of goods from the Pre-Shipment Inspection Certificate Programme", 3 March 2000 (C-14); AFIP Resolution No. 822/00 “Exclusion of tariff items from the Pre-Shipment Inspection Certificate Programme", 31 March 2000 (C-15); AFIP Resolution No. 840/00 "Exclusion of tariff items from the Pre-Shipment Inspection Certificate Programme", 10 May 2000 (C-16); AFIP Resolution No. 910/00 “Exclusion of tariff items from the Pre-Shipment Inspection Certificate Programme", 19 October 2000 (C-17), AFIP Resolution No. 955/01 “Exclusion of tariff items from the Pre-Shipment Inspection Certificate Programme", 11 January 2001 (C-18); AFIP Resolution No. 1099/01 "Exclusion of tariff items from the Pre-Shipment Inspection Certificate Programme”, 24 September 2001 (C-19). ↩
[Page 23]
72. Throughout the duration of the Programme the Claimant audited the work performed by Inspection Companies by conducting physical inspections at the point of destination of certain shipments that were covered by the Programme and verifying the quantity, quality, tariff classification, and price of the relevant goods as per the applicable valuation rules.51
73. The selection of the shipments that were to be audited by the Claimant was determined by the Committee through the “Red Channel Audit system”.52 Under this system, the operations to be audited by the Claimant were selected by the Committee among the shipments processed by the DGA through the “red channel” in accordance with Resolution 396/97.53
74. As elaborated upon below, the Parties dispute whether an adequate system for selecting the shipments to be audited by the Claimant was put in place by the Respondent.54 The Claimant argues that the "Red Channel Audit system” failed to work in practice.55 The Claimant asserts that it notified these practical issues to the Respondent.56 For instance, the Claimant notes that in a number of communications, between July 1998 and May 1999, it pointed out that the customs authorities generally failed to notify the Claimant that an inspection was needed before the goods had been released from customs.57 The Claimant avers that, in the same communications, it noted that some customs offices indicated that their systems lacked any notifications regarding the
51 Statement of Claim, paras. 54-56; Statement of Defence, paras. 47-69; Hearing Tr., Day 1 (6 April 2021), 9:19-10:2; Committee Certification No. IPE 164/04, 22 July 2004 (C-98). The Contract was in force for an initial period of 2 years (i.e., until March 2000), and extended on 2 March 2001 for an additional year (i.e., from March 2000 to March 2001) (Decision of the Committee No. 002, 2 March 2001, Article 1 (C-20)). Following the conclusion of the extended term of the Contract, the Claimant continued to provide auditing services until the termination of the Programme in November 2001 (Statement of Claim, para. 52; Statement of Defence, para. 12). ↩
52 Statement of Claim, para. 64; Statement of Defence, para. 95. ↩
53 Statement of Claim, para. 64; Statement of Defence, para. 103. ↩
54 See e.g. Statement of Claim, paras. 63-65; Statement of Defence, para. 103. ↩
55 Statement of Claim, paras. 63-65. ↩
56 Statement of Claim, para. 64. ↩
57 Statement of Claim, para. 64; Fax from ICS to the Committee, 2 July 1998 (C-24); Letter from ICS to the Committee, 24 August 1998 (C-25); Letter from ICS to the Committee, 4 September 1998 (C-26); Letter from ICS to the Committee, 8 October 1998 (C-27); Report conducted at terminals 1 and 2, 4 February 1999 (C-28); Hearing Tr., Day 1 (6 April 2021), 55:10-56:10. ↩
[Page 24]
shipments that need to be audited by the Claimant.58 Moreover, the Claimant argues that the Respondent acknowledged these practical shortcomings when it instructed the Claimant to "install itself physically at the points of destination and to try to take as many dispatches as it can, [even if] this is not the ideal solution".59
75. On the other hand, the Respondent asserts that it appropriately established selection criteria that enabled the Claimant to carry out its duties, as the Claimant recognized in its monthly reports.60
76. Between June 1998 and July 2001, the Claimant submitted reports and letters to the Committee in relation to 21 tasks (“Special Services”).61 The reports and letters comprised:
a) “Banana Imports into Argentina”,62 June 1998: verifying whether the FOB price published in a statistical bulletin could be deemed valid in comparison to the average prices of that same product in Ecuador, Brazil, and Argentina;63
b) "Analysis of Deficiencies Detected in the Issue of the CIPI”, June – July 1998: verifying the compliance of a sample of Inspection Certificates with Resolution No. 1278 dated 7 November 1997 and the Committee's Provisions Nos. 4 and 8. The former resolution contained rules related to the determination of the country of origin of imported goods, and the latter provisions established the Inspection Companies' obligation to identify the imported merchandises that were not stored in a container or that were stored in an unsealed container;64
58 Statement of Claim, para. 64; Letter from ICS to the Committee, 16 April 1999 (C-29); Letter from ICS to the Committee, 6 May 1999 (C-30). ↩
59 Statement of Claim, para. 65; Letter from the Committee to AFIP, 6 August 1999 (C-32) (translation by the Claimant); Hearing Tr., Day 1 (6 April 2021), 56:11-57:1. ↩
61 Statement of Claim, paras. 72-74. ↩
62 For ease of reference, the titles of the alleged special services have been included as referred to by the Parties regardless of the actual title contained in the respective exhibit (See e.g. Statement of Claim, para. 73; Statement of Defence, para. 185). The title of each document as reflected in the respective exhibit is indicated in the footnotes. ↩
63 Report on Banana Imports into Argentina, Ref. No. ICS C/99/17141/ARG, 1 September 1999, p. 255 (C-122). ↩
64 Report on the Deficiencies Detected in the Issuance of Inspection Certificates, 6 July 1999, pp. 123-124 (C-123). ↩
[Page 25]
c) "Special Audit Report – Asia Imports”, June – August 1998: establishing the impact of the devaluation of currencies of countries in South East Asia upon the imports into Argentina and verifying in particular whether the Inspection Certificates of imports shipped from that region contained inconsistencies in prices and associated values;65
d) Special Report on “Committee Certificates”, June – October 1998: presenting statistics and comments regarding the number of Inspection Certificates submitted in April 1999 that were not included in the Committee's database;66
e) “Kodak Study”, July – August 1998: verifying the value of imports of electronic goods corresponding to the tariff code No. 370254190 (photographic film in rolls, sensitised, unexposed, of any material other than paper, paperboard, or textiles instant print film in rolls, sensitised, unexposed);67
f) “TDK Line Study”, August – October 1998: reviewing a sample of the Inspection Certificates with the purpose of verifying the prices of products of the brand TDK and Samsung;68
g) “Chicken Imports Report SADIA S.A.”, August 1998: presenting the outcome of an audit of the quality, quantity, tariff classification, and customs value of selected Inspection Certificates presented by SADIA ARG. S.A. (an importer) at the customs station of Bernardo de Yrigoyen;69
h) “Glass and Glassware Study”, 18 August 1998: analysing the operations of Soifer Hnos. S.A.I.C. (an importer) under the Programme;70
i) "Marble and Granite San Luis S.A.”, 29 October 1998: auditing an Inspection Certificate submitted by the importer Mármoles y Granitos San Luis S.A.;71
65 Special Audit Report concerning Importations from Asia, pp. 3-4 (C-124). ↩
66 Special Report on the Inspection Certificates not found in the Database of the Committee, 18 May 1999, p. 91 (C-125). ↩
67 Study Regarding Kodak Products, July – August 1998, p. 245 (C-126). ↩
68 Special Report on the tariff codes No. 8523.11.10; 8523.13.20 and 8523.90.00, 18 May 1999, p. 1 (C-127). ↩
69 Report on Chicken Imports SADIA S.A., 11 February 1999, p. 4 (C-128). ↩
70 Letter from the Claimant to the Committee on the Importations of Soifer Hnos. S.A.I.C (referred to by the Claimant as Glass and Glassware Study), 18 August 1998, p. 1 (С-129). ↩
71 Letter from the Claimant to the Committee on Mármoles y Granitos San Luis S.A., 29 October 1998, p. 1 (C-130). ↩
[Page 26]
j) "Temporary Imports Study”, November 1998 – February 1999: analysing the importations carried out under the Temporary Suspensive Import Destination Regime, between 1 February 1998 and 31 January 1999;72
k) "Report on Iquique (Chile), Colonia and Montevideo, Uruguay Free Zone”, November 1998 – February 1999: comprising two reports, one on the business processes applicable to importations from Iquique (Chile) and a second report on the business processes applicable to the importation of vehicles from the Colonia and Montevideo (Uruguay) free zones in 1999;73
l) “Brazil Imports, October - December 1998 and January 1999”, January – February 1999: analysing import trends from Brazil of goods covered by the Programme from December 1998 to January 1999;74
m) “Imports Chapter 30, October - December 1998 and January 1999”, January – February 1999: analysing the importation of goods from Brazil under Chapter 30 of the Mercosur Common Nomenclature (Pharmaceutical Products) between October – December 1998 and January 1999;75
n) “Kiwi Imports Study”, June 1999: analysing the market for the trade of kiwi in Chile and an approximation of such market in Argentina, Italy, and Australia;76
o) “Colonia Uruguay Free Zone Report”, July 1999: evaluating the administrative and operational headquarters of the Inspection Companies in Uruguay;77
p) "Report regarding Compliance with CEPIPI Article 2, provision No. 4”, September 1999 – February 2000: assessing the Inspection Companies' compliance with Article 2 of Committee Provision No. 4, which required the identification of imported goods that were not stored in a container or that were stored in an unsealed container;78
72 Temporary Imports Study, 17 February 1999, p. 2 (C-131). ↩
73 Report on Iquique, Colonia and Montevideo Free Trade Zones, pp. 2, 11 (R-137). ↩
74 Report on Imports from Brazil from December 1998 to January 1999, p. 7 (C-132). ↩
75 Report on Imports Chapter 30 from Brazil from December 1998 to February 1999, pp. 7-8 (C-133). ↩
76 Kiwi Imports Study, p. 4 (C-134). ↩
77 Colonia Uruguay Free Zone Report, 20 May 1999 (C-135) ↩
78 Report regarding Compliance with Article 2, Provision No. 4 of the Committee, p. 4 (R-101). ↩
[Page 27]
q) “Analysis of Imports among Related Companies”, November 1999 – January 2000: analysing operations involving related importers and exporters;79
r) "Item 8703 Imports Investigation”, November 1999 – February 2000: statistics on imports of tariff item 8703 (automobiles);80
s) "Iquique 2 Report”, January 2001 – April 2001: exhaustively auditing the certificates issued by the Inspection Companies for operations carried out during 2000-2001 from the Iquique (Chile) free trade zone in order to determine if there were tax losses and the amount thereof;81
t) “Satellite Antenna Report”, 24 January 2001: analysing the values of five certificates issued by Surveyseed for importations by Galaxy Entertainment de Argentina;82
u) "Rito Kosher Milk Report”, 20 July 2001: verifying the price of Kosher Milk declared by the importer Mutual Kashrut Com.83
77. As elaborated upon below, the Parties dispute the characterization and the fees that should be derived from the issuance of the above-listed reports.84 The Claimant considers that the reports constituted "special services” to be compensated at a market rate pursuant to Resolution 1106/98. For the Respondent, these services “were nothing more than tasks that ICS had to carry out as part of the provision of its auditing services and, as such, they were already duly paid for through the relevant payment of the monthly invoices".85 In addition, the Respondent questions the probative value of these reports given that none of them are signed by the Committee.86
79 Analysis of Imports among Related Companies, November 1999 – January 2000, p. 4 (C-136). ↩
80 Statistics on Imports of Tariff Item 8703 (automobiles) (C-137). ↩
81 Special Audit Report Concerning the Free Trade Zone of Iquique, 2001, p. 4 (C-138). ↩
82 Letter from the Claimant to the Committee_on the Values Certified by Surveyseed (Satellite Antenna Report), 24 January 2001, p. 1 (C-139). ↩
83 Letter from the Claimant to the Committee on the Price of Kosher Milk, 20 July 2001 (C-140). ↩
84 Statement of Claim, paras. 72-74; Statement of Defence, paras. 184-186. ↩
86 Hearing Tr., Day 7 (14 April 2021), 1122:17-20. ↩
[Page 28]
78. In accordance with Clause 3 of the Contract, the Claimant submitted invoices on a monthly basis for the services it performed under the Contract.87 Whereas during the original and extended term of the Contract—i.e., from March 1998 to March 2001—the Claimant issued invoices denominated in Pesos, as of the expiration of the contract the Claimant submitted invoices denominated in U.S. dollars.88
79. The Parties dispute whether the invoices submitted by the Claimant complied during the entire duration of the Programme with the 10% Fee Cap provided for in Clause 3 of the Contract. The Claimant indicates that, at the outset of the Programme, it submitted invoices that often exceeded the 10% Fee Cap provided for in Clause 3 of the Contract.89 According to the Claimant, it would only know whether it had exceeded the cap at the end of each quarter when the Respondent would request the Claimant to cancel the original invoices and re-issue new invoices for a lower amount that fell within the cap.90 The Claimant alleges that the reissuance of invoices resulted in excess tax liabilities due to the impossibility under Argentine law to reduce the monthly amount of Value Added Tax originally declared.91 In view of the delays and inconveniences caused by the described payment procedure, the Claimant says that it eventually decided to only issue invoices once the Respondent indicated the amount that should be billed.92
80. The Respondent argues that, while the Contract was in force, the Claimant's invoices complied with the 10% Fee Cap.93 However, following the termination of the Programme, the Claimant started issuing invoices that exceeded the 10% Fee Cap.94
81. According to the Respondent, the total amount paid by the Respondent for the auditing services rendered by the Claimant over the course of the Programme amounts to ARS 19,434,124.95 The Respondent asserts that after the Contract expired (i.e., from March 2001 until November 2001),
87 Statement of Claim, para. 57; Statement of Defence, paras.65-66. ↩
88 Reply, para. 41; Statement of Defence, paras. 66-69. ↩
89 Statement of Claim, para. 59. ↩
90 Statement of Claim, para. 59. ↩
91 Statement of Claim, para. 60; First Santamaria Statement, para. 25; Law 11.683, as amended by Decree 821/98, Article 13 (C-23). ↩
92 Statement of Claim, para. 61; First Santamaria Statement, paras. 25-26. ↩
93 Statement of Defence, para. 68; Invoices and Credit/Debit Notes (R-25). ↩
94 Statement of Defence, para. 68; Invoices and Credit/Debit Notes (R-25). ↩
95 Rejoinder, paras. 44-46; First Dapena Report, paras. 43-45; Second Dapena Report, Section II.A.1.c. ↩
[Page 29]
in the absence of a valid contract to justify the payments, AFIP decided to settle the payment of the Claimant's invoices as “equitable payments” on the basis of an unjust enrichment approach.96 The following table, produced by the Respondent, sets out the payments made to the Claimant:97
| ORIGINAL CONTRACT TERM | RENEWED TERM | EXCEPTIONAL PAYMENTS | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| By month of accrual | By month of payment | By month of accrual | By month of payment | By month of accrual | By month of payment | ||||||
| Month | Amount | Month | Amount | Month | Amount | Month | Amount | Month | Amount | Month | Amount |
| Apr-98 | 396 | Oct-98 | 397 | Apr-00 | 502 | Feb-01 | 384 | Apr-01 | 278 | Mar-06 | 839 |
| May-98 | 564 | Dec-98 | 1,072 | May-00 | 621 | Mar-01 | 454 | May-01 | 173 | Jul-06 | 391 |
| Jun-98 | 508 | Jan-99 | 398 | Jun-00 | 627 | Apr-01 | 284 | Jun-01 | 172 | ||
| Jul-98 | 398 | Feb-99 | 154 | Jul-00 | 557 | May-01 | 303 | Jul-01 | 119 | ||
| Aug-98 | 435 | Mar-99 | 281 | Aug-00 | 655 | Sep-01 | 377 | Aug-01 | 96 | ||
| Sep-98 | 389 | Jun-99 | 848 | Sep-00 | 341 | Oct-01 | 63 | Sep-01 | 88 | ||
| Oct-98 | 459 | Aug-99 | 325 | Oct-00 | 551 | Feb-02 | 341 | Oct-01 | 52 | ||
| Nov-98 | 885 | Sep-99 | 561 | Nov-00 | 551 | Oct-02 | 1,665 | Nov-01 | 53 | ||
| Dec-98 | 221 | Nov-99 | 221 | Dec-00 | 283 | Mar-03 | 1,644 | Dec-01 | 51 | ||
| Jan-99 | 653 | Feb-00 | 223 | Jan-01 | 420 | Aug-03 | 123 | Adjustment | 148 | ||
| Feb-99 | 223 | Aug-00 | 984 | Feb-01 | 408 | Jun-04 | 1 | ||||
| Mar-99 | 278 | Oct-00 | 361 | Mar-01 | 123 | ||||||
| Apr-99 | 352 | Nov-00 | 6,622 | ||||||||
| May-99 | 397 | Feb-01 | 118 | ||||||||
| Jun-99 | 505 | ||||||||||
| Jul-99 | 808 | ||||||||||
| Aug-99 | 949 | ||||||||||
| Sep-99 | 455 | ||||||||||
| Oct-99 | 874 | ||||||||||
| Nov-99 | 584 | ||||||||||
| Dec-99 | 717 | ||||||||||
| Jan-00 | 519 | ||||||||||
| Feb-00 | 560 | ||||||||||
| Mar-00 | 435 | ||||||||||
| TOTAL | 12,565 | 12,565 | TOTAL | 5,639 | 5,639 | TOTAL | 1,230 | 1,230 | |||
Summary:
| Accrued | Paid | Payment outstanding | |
|---|---|---|---|
| ORIGINAL CONTRACT TERM (Apr-98/Mar-00) | 12,565 | 12,565 | - |
| RENEWED TERM (Apr-00/Mar-01) | 5,639 | 5,639 | - |
| EXCEPTIONAL PAYMENTS (Apr-01/Dec-01) | 1,230 | 1,230 | - |
| TOTAL | 19,434 | 19,434 | - |
82. In 2001-2002, Argentina experienced an economic and political crisis that has been described as among the deepest recessions in its history.98 This crisis took place following three years of deep
96 Statement of Defence, para. 61; First Acosta Witness Statement, paras. 29-30. ↩
98 Carlos G. Fernández Valdovinos, "Growth, Poverty, and Social Equity in Argentina", World Bank Newsletter, November 2005, No. 82, p. 2 (R-55); BBC News – Max Seitz, "The day Argentina hit rock bottom," 19 December 2005 (R-45). ↩
[Page 30]
recession and an associated rise in the unemployment rate,99 and saw a 20% drop in the gross domestic product from 1999 to 2002.100
83. From December 1999 onwards, a number of measures were undertaken by the Argentine government to cope with the recession, including securing international financial support, enacting drastic cuts in public spending, and issuing sovereign debt.101 Such measures were implemented in the context of a convertibility regime pursuant to which the Argentine Peso was pegged to the U.S. dollar at a foreign exchange rate of one to one (1:1).102
84. On 24 August 2001, the President of Argentina issued Decree No. 1060/2001 (“Decree 1060/2001").103 Pursuant to Decree 1060/2001, public bodies and entities were ordered to request from suppliers a 13% reduction in the amounts payable for goods or services procured.104 In the event that the service provider's consent was not given within ten days from their notification, the respective administrative body could either: (i) terminate the contract, provided that the service in question was not essential for general public interest;105 or (ii) reduce
99 Saúl Keifman, “Auge y derrumbe de la convertibilidad Argentina: lecciones para Ecuador", Iconos, No. 19, Flacso-Ecuador, May 2004, p. 28 (R-58); INDEC, Evolution of activity, employment, unemployment and underemployment rates from 1974 onwards, available at https://www.indec.gob.ar/ftp/cuadros/menusuperior/archivo/shempleo1.xls (R-61); Clarín, “De la Rúa renunció, cercado por la crisis y sin respaldo político,” 21 December 2001, p. 5 (R-49). ↩
100 Carlos G. Fernández Valdovinos, "Growth, Poverty, and Social Equity in Argentina", World Bank Newsletter, November 2005, No. 82, p. 2 (R-55) ↩
101 Presidential Decree No. 648/01, 16 May 2001 (R-69); Paul Blustein, "And the Money Kept Rolling In (And Out): Wall Street, The IMF, and The Bankrupting of Argentina”, 2005, p. 9-19, 21 (R-54); Saúl Keifman, "Auge y derrumbe de la convertibilidad Argentina: lecciones para Ecuador", Iconos, No. 19, Flacso-Ecuador, May 2004, p. 28 (R-58); Clarín, “Alianza acelera dura reforma impositiva,” 5 November 1999 (R-64); Clarín, “De la Rúa anuncia hoy blindaje financiero," 18 December 2000 (R-65); Ámbito Financiero, “Blindaje, Megacanje y Corralito: las medidas me marcaron el fin de la Rúa,” 9 July 2019 (R-66); La Prensa, “Severo plan de ajuste de López Murphy," 17 March 2001 (R-67); La Nación, “El Megancanje es por 29.477 millones," 4 June 2001 (R-70); Fernando Krakowiak, “Trece cuasimonedas circulan por el territorio nacional,” 26 May 2002, p. 12 (R-134); Presidential Decree No 1004/01, 9 August 2001 (R-77); El País, “La Ley de Déficit Cero impone drásticos recortes en el gasto público en Argentina,” 31 July 2001 (R-79); Clarín, “Fijaron por decreto la poda para sueldos y jubilaciones," 24 July 2001 (R-80); Decree 1060/2001 (C-50). ↩
102 Saúl Keifman, “Auge y derrumbe de la convertibilidad Argentina: lecciones para Ecuador", Iconos, No. 19, Flacso-Ecuador, May 2004, pp. 27-28 (R-58). The Convertibility Law No. 23.928 passed by the Argentine Congress on 27 March 1991, set the foreign exchange rate between the Austral to the U.S. dollar at 10.000 Australes for 1 U.S. dollar (Convertibility Law No. 23.928, 27 March 1991, Article 1 (C-37)). Later on 17 October 1991 when the Peso was adopted as the national currency in Argentina and its value was set at 1 Peso for 10,000 Australes, the Peso was pegged to the U.S. dollar at a foreign exchange rate of one to one 1:1 (Presidential Decree 2128/91, 17 October 1991, Art. 1 (C-38)). ↩
103 Decree 1060/2001 (C-50). ↩
104 Decree 1060/2001, Articles 1, 4 (C-50). ↩
105 Decree 1060/2001, Article 1(2)(a) (C-50). ↩
[Page 31]
the level of services being provided in order to reduce the level of fees accordingly, if the service in question was essential for general public interest.106
85. On 1 December 2001, Decree 1570/01 imposed restrictions on the withdrawal of funds from the banking system (known as the “corralito”).107 This triggered widespread social discontent, including looting and riots during which it was reported that 39 persons died.108
86. In May 2002, the proportion of the population living below the poverty line had reached 53% and the unemployment rate had risen to 21.5%.109 Institutional instability ensued: following the resignation of the then President on 20 December 2001 and within a period of less than 15 days, Argentina had a succession of five Presidents, who resigned one after the other.110
87. On 6 January 2002, the Argentine Congress enacted Law No. 25.561 (the “Emergency Law"), declaring a temporary state of "emergency” for a period that was due to expire on 10 December 2003.111 Among other matters, the Emergency Law authorized the Executive branch of the government to institute a new currency exchange regime in Argentina.112 To this effect, the Emergency Law repealed the currency board established by the Convertibility Law which fixed the foreign exchange rate of one Peso to one U.S. dollar.113 The end of Peso-U.S. dollar parity led to a devaluation of the Peso against the dollar, with the value of Peso dropping to less than one third of its prior exchange rate.114
106 Decree 1060/2001, Article 1(2)(b) (C-50). ↩
107 Presidential Decree No. 1570/01, 1 December 2001 (R-81); Ámbito Financiero, “Blindaje, Megacanje y Corralito: las medidas me marcaron el fin de la Rúa," 9 July 2019 (R-66). ↩
108 Nodal Cultura, “39, las víctimas del 2001", 8 September 2018 (R-135). ↩
109 INDEC, Percentage of households and people living below the poverty and indigence lines in urban agglomerates (EPH - Permanent Household Survey) and statistical regions, from May 2001 onwards, available at: https://www.indec.gob.ar/ftp/cuadros/sociedad/sh-pobreza1.xls (R-83); INDEC, Evolution of activity, employment, unemployment and underemployment rates from 1974 onwards, available at: https://www.indec.gob.ar/ftp/cuadros/menusuperior/archivo/shempleo1.xls (R-61). ↩
110 BBCMundo.com, “Las semanas de los cinco presidentes," 31 December 2001 (R-50); Clarín, “De la Rúa renunció, cercado por la crisis y sin respaldo político,” 21 December 2001 (R-49). ↩
111 Emergency Law, Article 1 (C-36). ↩
112 Emergency Law, Article 2 (C-36). ↩
113 Emergency Law, Article 3 (C-36). ↩
114 Paul Blustein, "And the Money Kept Rolling In (And Out): Wall Street, The IMF, and The Bankrupting of Argentina", 2005, p. 19 (R-54). ↩
[Page 32]
88. Under the framework of the Emergency Law, on 4 February 2002, the President of Argentina issued Decree No. 214/02 (“Decree 214/02”).115 Decree 214/02 established that all the obligations denominated in a foreign currency existing as of the time of the enactment of the Emergency Law be converted into Pesos at a rate of one peso to one U.S. dollar.116 Decree 214/02 also established that the obligations converted into Pesos pursuant to its Article 1 were to be adjusted by a stabilization ratio (Coeficiente de Estabilización de Referencia).117
89. In accordance with MECON's resolution of 2 November 2001 and the Committee's notice of 21 November 2001, the Programme was terminated on 20 February 2002.118 By letter of that same date, the Claimant requested that the Committee approve its outstanding invoices.119
90. On 15 March 2002, the Claimant filed an administrative claim pursuant to Article 30 of the Argentine National Law of Administrative Procedures No. 19.549 (the “LPA”), reiterating its request for the approval and payment of the outstanding invoices identified in its letter of 20 February 2002.120 In addition, the Claimant argued that in view of the currency of the values that served as a basis for the calculation of its fees, the legal framework that was in force at the time the Programme was established, and the fact that a major part of its services under the Contract were rendered abroad, its outstanding invoices should be paid in U.S. dollars.121
91. On 22 August 2002, the Committee returned the Claimant's invoices for the services provided from April to December 2001 alleging that (i) the invoices were not issued in the currency indicated by Annex II of Decree 477/97 and the Contract; (ii) with the only exception of the invoice corresponding to a report concerning the free trade zone of Iquique, the invoices for “special services” did not comply with the requirements established by SIGEN on 4 June 2001;
116 Decree 214/02, Articles 1, 3 (C-39). ↩
117 Decree 214/02, Article 4 (C-39). ↩
118 Letter from the Committee to ICS, 21 November 2001, enclosing Resolution 650/01, 2 November 2001 (C-21). ↩
119 Letter from ICS to the Committee, 20 February 2002 (C-40). ↩
120 Administrative claim filed by the Claimant before the Committee, 15 March 2002, Case No. 252457/02, 15 March 2002, received on 6 June 2002 (C-41). ↩
121 Administrative Claim filed by the Claimant before the Committee, Case No. 252457/02, 15 March 2002, received on 6 June 2002 (C-41). ↩
[Page 33]
and (iii) the invoices concerning audited inspection certificates did not comply with the 10% Fee Cap and did not correspond to their issuance date.122
92. By letters dated 19 December 2002, the Claimant sent the Committee a new set of invoices for its outstanding fees, re-issued in accordance with the Committee’s observations of 22 August 2002.123 At the same time, the Claimant stated that it reserved its rights in respect of the interest accrued for untimely payment by the Respondent and the reduction in the amount of fees as a result of the conversion of the invoices from U.S. dollars to Pesos.124
93. By letter dated 8 October 2002, the Claimant provided certain clarifications regarding the invoices for the “special services”.125
94. On 22 April 2003, AFIP informed the Claimant that it made payments corresponding to some of the Claimant’s invoices.126
95. By letter dated 30 June 2003, AFIP requested that, pursuant to Decree 1060/2001, the Claimant issue credit notes to the effect of reducing 13% of each invoice issued between July and December 2001.127 AFIP further stated that the issuance of these credit notes constituted an indispensable requirement for the payment of further outstanding invoices.128
96. On 23 September 2004, the Claimant requested that the Committee inform it of the status of the approval and payment of the invoices related to the “special services”.129
97. On 28 September and 6 October 2004, the Committee reiterated its request for a 13% reduction of each invoice pursuant to Decree 1060/2001.130
122 Letter from the Committee to ICS, 22 August 2002 (C-42). ↩
123 Letters from ICS to the Committee, 19 December 2002 (C-45). ↩
124 Letters from ICS to the Committee, 19 December 2002, p. 2 (C-45). ↩
125 Letters from ICS to the Committee, 8 October 2003 (C-46). ↩
126 Letters from AFIP to ICS, 8 March 2003 and 22 April 2003 (C-48). ↩
127 Letter from AFIP to ICS, 30 June 2003 (C-49). ↩
128 Letter from AFIP to ICS, 30 June 2003 (C-49). ↩
129 Letter from ICS to the Committee, 23 September 2004 (C-47). ↩
130 Letter from the Committee to ICS, 28 September 2004 (C-51); Letter from the Committee to ICS, 6 October 2004 (C-52). ↩
[Page 34]
98. On 6 December 2004, the Claimant filed an amended and expanded administrative claim before the Minister of Economy and Production.131 The Claimant claimed payment of (i) the unpaid invoices for auditing services from April to December 2001 in the amounts and currency in which they were originally issued; (ii) invoices for auditing services prior to April 2001 which exceeded the 10% Fee Cap; (iii) the difference between the amounts paid by AFIP for auditing services carried out from July 2000 to March 2001 pursuant to the invoices reissued in Pesos and the amounts originally invoiced in U.S. dollars; and (iv) the payment of the invoices for “special services”.132
99. On 7 December 2004, the Claimant provided to the Committee the credit notes corresponding to the 13% reduction in the total amount of its outstanding invoices.133
100. On 10 January 2006, MECON issued Resolution No. 325 (“Resolution 325”) approving the payment of the Claimant’s fees corresponding to auditing services provided from April 2001 to December 2001 as per the invoices re-issued in Pesos and the credit notes reflecting a 13% reduction in such invoices.134
101. By letters of 24-25 January and 21 February 2006, the Committee observed that there was no proof of approval by the Committee of the “special services”.135 Accordingly, it requested the Claimant to submit, pursuant Article 2 of Resolution 1106/98, a report detailing the expenses and fees incurred in relation to each of the “special services” together with supporting documents.136 The Claimant provided the relevant documentation between 11 June and 1 August 2006.137
131 Amplified Administrative Claim filed by the Claimant before the Minister of Economy and Production of Argentina, Case No. 252457/02, 6 December 2004, Section V (C-54). ↩
132 Amplified Administrative Claim filed by the Claimant before the Minister of Economy and Production of Argentina, Case No. 252457/02, 6 December 2004, Section V (C-54). ↩
133 Letter from ICS to the Committee, 7 December 2004 (C-53). ↩
134 MECON, Decision No. 325, 10 January 2006 (C-60). ↩
135 Letters from the Committee to ICS, 24 and 25 January, and 21 February 2006 (C-57). ↩
136 Letters from the Committee to ICS, 24 and 25 January, and 21 February 2006 (C-57). ↩
137 Letters from ICS to the Committee, from 11 June to 1 August 2006 (C-59). ↩
[Page 35]
102. As noted above, on 15 March 2002,138 the Claimant filed an administrative claim, which was subsequently expanded on 6 December 2004.139 The Claimant points out that MECON never rendered a decision in respect of its administrative claim and that the respective administrative procedure was terminated when the Claimant submitted the dispute to the competent Argentine court on 17 February 2012.140
103. On 30 June 2009, the Claimant, ICS commenced arbitration proceedings against the Respondent pursuant to Article 8 of the Treaty and the UNCITRAL Rules (the “ICS I Arbitration”).141 In those proceedings, ICS contended the treatment accorded to it by Argentina in connection with the Contract had breached the Treaty.142
104. The tribunal in the ICS I Arbitration issued an award on jurisdiction on 10 February 2012, in which it declined jurisdiction over ICS’s claims due to the Claimant’s failure to comply with the mandatory 18-month litigation prerequisite set forth in Article 8 of the Treaty.143 The Tribunal determined that the former decision was “without prejudice to the Claimant’s rights to submit them to arbitration before a new tribunal after complying with Article 8 of the Treaty.”144
138 Administrative claim filed by the Claimant before the Committee, 15 March 2002, Case No. 252457/02 (C-41). ↩
139 Amplified Administrative Claim filed by the Claimant before the Minister of Economy and Production of Argentina, Case No. 252457/02, 6 December 2004 (C-54). ↩
140 Statement of Claim, fn. 91. ↩
141 ICS Inspection and Control Services Limited v. The Republic of Argentina, PCA Case No. 2010-9, Award on Jurisdiction, 10 February 2012, para. 3 (C-65). ↩
142 ICS Inspection and Control Services Limited v. The Republic of Argentina, PCA Case No. 2010-9, Award on Jurisdiction, 10 February 2012, paras. 1, 4 (C-65). ↩
143 ICS Inspection and Control Services Limited v. The Republic of Argentina, PCA Case No. 2010-9, Award on Jurisdiction, 10 February 2012, Section J (C-65). ↩
144 ICS Inspection and Control Services Limited v. The Republic of Argentina, PCA Case No. 2010-9, Award on Jurisdiction, 10 February 2012, Section J (C-65). ↩
[Page 36]
105. Following the award on jurisdiction in the ICS I Arbitration, the Claimant submitted the dispute to the Argentine administrative courts on 17 February 2012.145 To date, the proceedings in the Argentine courts remain pending.146
145 Argentine court filing by ICS, 17 February 2012 (C-66); Argentine court filing by ICS, 30 July 2012 (C-67). ↩
146 Statement of Claim, para. 95. ↩
[Page 37]
106. The Respondent raises four preliminary defences to the Claimant’s claims. In particular, the Respondent submits that the Claimant’s claims are precluded, alternatively, by (i) acquiescence and estoppel; (ii) good faith; and (iii) extinctive prescription.147
107. The Respondent submits that, under international law, the concepts of acquiescence and estoppel “prevent a claimant from bringing a claim if it may be inferred from its previous actions that it has consented to the acts on which its claim is based”, because “under the given circumstances, some sort of action was expected to be taken” if it had any objection.148 Estoppel, the Respondent adds, is a general principle of law rooted in the principle of good faith, “preventing a party from acting in a way that is contrary to its own previous actions where such change of mind would cause serious injustice to the other party.”149
108. With respect to the 10% Fee Cap, the Respondent submits that the Claimant complied with the 10% Fee Cap throughout the Programme, but then submitted for the first time in January 2002 invoices that exceeded the 10% Fee Cap along with belated objections.150 According to the Respondent, the Claimant provided its tacit consent to the application of the 10% Fee Cap by issuing invoices and accepting payments within that limit.151 The Respondent underscores that
147 Statement of Defence, Section IV; Rejoinder, Section IV. ↩
148 Statement of Defence, paras. 312-317; Rejoinder, paras. 195-196; I.V. MacGibbon, “Estoppel in International Law”, International and Comparative Law Quarterly, 1958, vol. 7, p. 501 (RLA-147); Christian J. Tams, “Waiver, Acquiescence, and Extinctive Prescription”, in The Law of International Responsibility, James Crawford J, Pellet A, and Olleson, S (eds.), 2010, pp. 1042-1044 (RLA-68); M.C.I. Power Group L.V. and New Turbine, Inv. v. Ecuador, ICSID Case No. ARB/03/6, Award, 31 July 2007, para. 302 (RLA-143); Ronald S. Lauder v. Czech Republic, 3 September 2002, paras. 270, 273 (RLA-144); Canfor Corporation v. United States of America; Tembec et al. v. United States of America; and Terminal Forest Products Ltd. v. United States of America, Order of the Consolidation Tribunal, 7 September 2005, para. 168 (RLA-145); Hearing Tr., Day 1 (6 April 2021), 105:1-8; Case concerning the Temple of Preah Vihear (Cambodia v. Thailand), Merits, Judgment, 15 June 1962: I.C. J. Reports 1962, p. 6 (CLA-194). ↩
149 Statement of Defence, para. 316; Rejoinder, para. 201; Canfor Corporation v. United States of America; Tembec et al. v. United States of America; and Terminal Forest Products Ltd. v. United States of America, Order of the Consolidation Tribunal, 7 September 2005, para. 168 (RLA-145); Hearing Tr., Day 1 (6 April 2021), 105:17-23. ↩
150 Statement of Defence, paras. 321, 324; Rejoinder, paras. 197, 203; Hearing Tr., Day 1 (6 April 2021), 105:9-16. ↩
151 Hearing Tr., Day 7 (14 April 2021), 1135:22-1136:10. ↩
[Page 38]
while the Programme was ongoing the Claimant never stated that any shortcomings in the red channel system prevented them from respecting the 10% Fee Cap, nor did it reserve its rights on this issue.152 For the Respondent, the Claimant’s assertion that it had no other option but to comply to with the 10% Fee Cap, as otherwise its position in the Programme would have been jeopardized, lacks any evidentiary basis.153
109. With respect to the payment of the Claimant’s invoices in Pesos, the Respondent maintains that the Claimant submitted invoices for fees in Pesos during the first three years of the Programme, only to begin to issue invoices in U.S. dollars in May 2001.154 For the Respondent, this constitutes tacit consent to the payment of those invoices in Pesos.155 The Respondent disputes the Claimant’s contention that the currency in which its invoices were issued was irrelevant prior to the enactment of the Emergency Law, as the Claimant began invoicing in U.S. dollars in May 2001, prior to the enactment of the Emergency Law in January 2002.156 In addition, the Respondent contends that the Claimant’s objections to the Peso-denominated invoices in 2002 were submitted belatedly given that, at that time, the Contract had expired and the respective payments had already been collected in Pesos.157
110. With respect to the application of Decree 1060/01, the Respondent asserts that the Claimant voluntarily decided to submit to the regime established in this decree “as it continued to provide services after the expiration of its Contract when such decree was already in force.”158 In addition, the Respondent contends that the Claimant submitted the credit notes relating to the invoices for the auditing services as from July 2001 for application of the reduction established by Decree 1060/01 “without raising any objection or expressing any reservation.”159
152 Hearing Tr., Day 7 (14 April 2021), 1139:4-1141:1. See also ibid., 1111:14-1112:15. ↩
154 Statement of Defence, paras. 321, 324; Hearing Tr., Day 1 (6 April 2021), 105:9-16. ↩
155 Hearing Tr., Day 7 (14 April 2021), 1135:22-1136:10. ↩
156 Rejoinder, paras. 198-199; Hearing Tr., Day 7 (14 April 2021), 1138:18-1139:3. ↩
157 Hearing Tr., Day 7 (14 April 2021),1137:10-20. ↩
[Page 39]
111. The Respondent submits that the principle of good faith, enshrined in both public international law and Argentine law, “bars Claimant from acting in an abusive fashion in this proceeding.”160 The Respondent reiterates that the Claimant has contradicted itself by issuing invoices in U.S. dollars and exceeding the 10% Fee Cap as from May 2001 and January 2002, respectively, given that until then it had consistently submitted invoices in Pesos and within the 10% Fee Cap.161 The Respondent adds that the Claimant attempted to obtain additional compensation for the alleged “special services”, when such services were part of the auditing services that the Respondent had already paid for.162 The Respondent argues that the Claimant decided to undertake such actions in early 2001, seeking to take advantage “of utter institutional, social and economic chaos”.163
112. The Respondent submits that the principle of extinctive prescription forbids the submission of untimely claims where a significant delay in the submission of a claim is attributable to the negligence of the claimant.164 According to the Respondent, the absence of a provision in the Treaty establishing a specific time limit to bring a claim does not preclude the application of the principle of extinctive prescription, as has been confirmed by various international tribunals.165
113. The Respondent alleges that, out of the four measures the Claimant complains of, the last to be implemented was the application of Decree 1060/01 by AFIP and the Committee in June 2003.166 Yet, the Respondent contends that it was not until late June 2009 that it initiated the ICS I
160 Statement of Defence, paras. 326-334; Rejoinder, para. 207; Hearing Tr., Day 1 (6 April 2021), 101:1-10; Phoenix Action Ltd. v. Czech Republic, ICSID Case No. ARB/06/5, Award, 5 April 2009, para. 107 (RLA-10). ↩
161 Statement of Defence, para. 336; Rejoinder, para. 211; Hearing Tr., Day 1 (6 April 2021), 78:14-79:21, 102:6-104:24. ↩
162 Statement of Defence, para. 337; Rejoinder, para. 212. ↩
163 Statement of Defence, paras. 338-339; Hearing Tr., Day 1 (6 April 2021), 78:14-79:21. ↩
164 Statement of Defence, paras. 344, 348; Bin Cheng, “General Principles of Law as Applied by Intentional Courts and Tribunals” (1987), p. 372 (RLA-125). ↩
165 Rejoinder, paras. 219-220; Nordzucker AG v. Republic of Poland, Partial Award, 10 December 2008, para. 221 (RLA-176); Caratube International Oil Company LLP and Devincci Salah Hourani v. Kazakhstan, ICSID Case No. ARB/13/13, Award, 27 September 2017, paras. 420, 421 (RLA-292). ↩
166 Rejoinder, para. 226; Hearing Tr., Day 1 (6 April 2021), 106:14-18. ↩
[Page 40]
arbitration.167 The Respondent denies that there were any amicable settlement negotiations from 2002 to 2006 that could justify the delay in the Claimant putting forward its claims.168
114. Contrary to the Claimant’s assertions, the Respondent submits that it is not required to demonstrate that the delay placed the responding party at a disadvantage.169 However, even if such a requirement were to apply, the Respondent argues that the Parties’ inability to produce documents requested during the document production phase as a result of the passage of time confirms that prejudice has arisen from the Claimant’s delay.170 The Respondent similarly points out that delay has rendered key witness testimony unavailable, such as that of any of the members of the Committee.171
115. Relying on Article 45(b) of the International Law Commission Articles on the Responsibility of States for Internationally Wrongful Acts (the “ILC Articles”), the Claimant contends that acquiescence “require[s] proof of the Claimant’s tacit consent to the relevant measures.”172 However, the Claimant insists that it never consented, whether tacitly or otherwise, to the conversion of dollar-denominated invoices into Pesos and the application of the 10% Fee Cap.173 In the Claimant’s view, this distinguishes the present case from the case of Lauder v. Czech Republic and M.C.I. Power v. Ecuador cited by the Respondent.174
167 Statement of Defence, para. 350; Rejoinder, para. 226; Hearing Tr., Day 1 (6 April 2021), 106:18-107:10. ↩
168 Rejoinder, paras. 228-229; Letter from ICS to the Argentine Treasury Attorney General, 27 November 2006 (RLA-179). ↩
169 Rejoinder, paras. 230-234; SGS Société Générale de Surveillance S.A. v. the Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, para. 162 (CLA-54); Wena Hotels Limited v. Arab Republic of Egypt, ICSID Case No. ARB/98/4, Award, 8 December 2000, para. 106 (CLA-49). ↩
170 Rejoinder, para. 235; Hearing Tr., Day 7 (14 April 2021), 1142:9-1145:20. ↩
171 Hearing Tr., Day 7 (14 April 2021), 1142:9-1145:20. ↩
172 Reply, paras. 122-124; ILC Articles on State Responsibility, Article 45 (CLA-85); N. S. Marques Antunes, Acquiescence in R. Wolfrum (ed.), The Max Planck Encyclopedia of Public International Law, OUP, Volume I, 2012, p. 53, para. 2 (CLA-132); Hearing Tr., Day 1 (6 April 2021), 31:1-4. ↩
173 Reply, paras. 125-130; Hearing Tr., Day 1 (6 April 2021), 31:20-32:6. ↩
174 Reply, paras. 131-132; Ronald S. Lauder v. The Czech Republic, UNCITRAL, Final Award, 3 September 2001, para. 271 (CLA-7); M.C.I. Power Group L.C. and New Turbine, Inc. v. Republic of Ecuador, ICSID Case No. ARB/03/6, Award, 31 July 2007, para. 301 (RLA-143). See also, Hearing Tr., Day 1 (6 April 2021), 34:7-35:15; Hearing Tr., Day 7 (14 April 2021), 1020:8-14. ↩
[Page 41]
116. The Claimant contends that, when the Peso was pegged to the U.S. Dollar, “it made no difference whether the Claimant issued its invoices in Pesos or US Dollars.”175 So, the Claimant avers that its issuance of invoices in pesos from March 1998 to May 2001 was immaterial.176 However, once the Emergency Law decoupled the dollar-peso exchange rate, the Claimant contends that the issuance of invoices in Pesos became inconsistent with the Claimant’s contractual right to set the value of its fees in U.S. dollars.177
117. The Claimant submits that it also did not consent to the 10% Fee Cap.178 It is the Claimant’s position that it repeatedly complained to Argentina about its failure to implement an adequate selection system, which underlies the Claimant’s claim for exemption from the 10% Fee Cap.179 The Claimant also submits that “ICS had no choice but to comply with Argentina’s demands and issue capped invoices”, as the Respondent would not otherwise make even partial payment of the Claimant’s fees.180 Furthermore, the Claimant contends that it formally challenged the application of the 10% Fee Cap on multiple occasion since December 2001, including in the context of the administrative claims filed in March 2002 and December 2004 and the ICS I arbitration.181
118. As for estoppel, the Claimant submits that the Respondent has failed to discharge its burden of establishing the essential elements of estoppel in the instant case, including (i) a statement of fact which is clear and unambiguous given voluntarily, unconditionally, and duly authorised; and (ii) reliance in good faith upon the statement either to the detriment of the party so relying on the statement or to the advantage of the party making the statement.182 The Claimant maintains that the Respondent has not shown that (i) “the Claimant made a clear and unambiguous statement of fact, given voluntarily, unconditionally, and duly authorised, that it would wholly abandon its rights with respect to amounts above the 10% Fee Cap and/or the full US Dollar value of its
176 Reply, paras. 126-128; Hearing Tr., Day 1 (6 April 2021), 32:7-21. ↩
179 Reply, para. 129; Hearing Tr., Day 1 (6 April 2021), 32:22-33:8. ↩
180 Reply, para. 129; First Santamaria Statement, paras. 26-27; Hearing Tr., Day 1 (6 April 2021), 33:9-16. ↩
181 Reply, para. 130; Hearing Tr., Day 1 (6 April 2021), 33:17-34:6. ↩
182 Reply, paras. 135-138; Land, Island and Maritime Frontier Dispute (El Salvador v. Honduras) [1990] ICJ Rep 92 at 118, para. 63 (CLA-189); Pope & Talbot Inc. v. The Government of Canada, Interim Award, 26 June 2000, para. 111 (CLA-191); Pan American Energy LLC and BP Argentina Exploration Company v. The Argentine Republic, ICSID Case No. ARB/03/13, Decision on Preliminary Objections, 27 July 2006, para. 159 (RLA-60); Canfor Corporation v. United States of America; Terminal Forest Products Ltd. v. United States of America, Order of the Consolidation Tribunal, 7 September 2005, para. 169 (RLA-145); Hearing Tr., Day 1 (6 April 2021), 31:6-11. ↩
[Page 42]
invoices”; nor that (ii) “Argentina relied upon such statement in good faith and detrimentally, so that reversal of the Claimant’s alleged position would cause serious injustice to Argentina”.183
119. The Claimant submits that the Respondent’s preliminary good faith defence is legally and factually misconceived.184 The Claimant contends that any inconsistency with the principle of good faith “would be engaged presumably through another international law rule because [...] good faith is [not] a principle in international law that creates a self-standing obligation.”185 However, the Claimant contends that such assertions by the Respondent “are entirely unfounded and fall short of the high standard required under international law”.186 The Claimant further disputes the Respondent’s assertion that the Claimant engaged in an abuse of rights by claiming “sums that it considers it is entitled to by application of the [Treaty] and the Contract.”187
120. The Claimant submits that arbitral practice confirms that extinctive prescription does not apply unless the applicable BIT contains a limitation period or similar time limit for bringing the claim, which the Treaty does not.188 However, the Claimant submits that, even if extinctive prescription were applicable, its requirements are not fulfilled in this case.189
121. First, the Claimant maintains that a particularly long delay is needed, noting that all of the cases cited have involved delays of 30 years or more.190 However, the Claimant contends that it “pursued its claim diligently from the outset and throughout the course of this dispute.”191 The
184 Hearing Tr., Day 7 (14 April 2021), 1019:1-24. ↩
185 Hearing Tr., Day 1 (6 April 2021), 35:22-36:3. ↩
187 Hearing Tr., Day 7 (14 April 2021), 1019:1-24. ↩
188 Reply, para. 143; SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, para. 166 (CLA-54); H&H Enterprises Investments, Inc. v. Arab Republic of Egypt, ICSID Case No. ARB 09/15, Decision on Jurisdiction, 5 June 2012, paras. 87-88 (CLA-70). ↩
190 Reply, para. 147(a); Irene Roberts case, RIAA, Vol. IX, p. 207 (CLA-136); Tagliaferro case, RIAA, Vol. Χ, 1903, p. 593 (CLA-137); Giacopini case RIAA, Vol. X, p. 594 (CLA-138); Gentini case, RIAA, Vol. Χ, p. 556 (CLA-139), see also pp. 551, 558; Spader case, RIAA, Vol. IX, p. 224 (CLA-140). ↩
[Page 43]
Claimant maintains that, upon the termination of the Programme in February 2002, it demanded payment of overdue and unpaid invoices and then filed an administrative claim in March 2002.192 The Claimant adds that it reserved its rights when it was “forced to give in to Argentina’s demands” to issue invoices denominated in Pesos and reduced its fees by 13% in December 2002 and December 2004, respectively.193 The Claimant thereafter notified Argentina of its claim under the BIT in November 2006.194 The Claimant adds that the Respondent was in contact with the Claimant and provided partial payments up to January 2006.195 The Claimant thus asserts that, even if there was a delay, “such delay was neither unreasonable, nor nearly long enough to lead to the extinctive prescription.”196
122. Second, the Claimant underscores that delay arising from attempts to settle a dispute “is not regarded as undue delay”.197 According to the Claimant, it spent years trying to reach an amicable settlement that resulted in Argentina making partial payments of unpaid invoices in 2003 and 2006.198 The Claimant alleges that it was only after such settlement negotiations “broke down” that it resorted to arbitration.199
123. Third, the Claimant contends that no prejudice to the Respondent has arisen from any delay.200 It is the Claimant’s position that the repeated demands for payments since the early stages of the dispute “would (or should) have put Argentina on notice regarding the need to collect and preserve evidence with respect to the Claimant’s claims”.201 In any event, the Claimant submits that the evidence submitted by both Parties in these proceedings confirm that any alleged delay did not ultimately lead to the disappearance or unavailability of relevant evidence.202
195 Hearing Tr., Day 7 (14 April 2021), 1021:16-1022:7. ↩
196 Reply, para. 150; Hearing Tr., Day 1 (6 April 2021), 12:6-10. ↩
197 Reply, paras. 147(b), 151; Ioannis Kardassopoulos v. The Republic of Georgia, ICSID Case No. ARB/05/18, Award, 3 March 2010, para. 261 (CLA-143). ↩
[Page 44]
124. The Tribunal recalls the preliminary decision in its Award on Jurisdiction on the Respondent’s objections of acquiescence, prescription, and good faith, wherein it deferred consideration of these issues to the merits phase of the arbitration. This decision was premised on the conclusion that these defences “address the substance of the dispute and not the power of the Tribunal to rule on them”.203 However, the Tribunal also supported this deferral on the basis that it would wish to “be sure that it has before it the complete factual and legal basis of the dispute” before definitively resolving these issues.
125. Having considered in full the Parties’ submissions and evidence, the Tribunal concludes that the Respondent’s defences must fail on several counts.
126. The Respondent’s objections—although formulated under the distinct headings of acquiescence, estoppel, good faith, and extinctive prescription—all have their root in the principle of good faith in international law. As already recorded in the Tribunal’s Award on Jurisdiction, the Parties are further agreed that all of these doctrines address a party’s implied consent by way of statements, actions, or omissions in response to certain actions or omissions by another party.204 The attempt to repudiate such consent at a later point in time runs counter to good faith.205
127. Taking the above as the basis for the analysis of the Respondent’s objections, the Tribunal finds that there is no positive statement nor any significant period of silence or inactivity—let alone acquiescence—which would support the objections. That is, the record shows no significant period during which the Claimant was idle and did not protest the measures underlying its claims in this arbitration. From the inception of those measures until the commencement of the prior arbitration between the Parties, and eventually this arbitration, the Claimant has objected to the measures in question whenever it would have been expected to do so. Indeed, since shortly after the termination of the concession, these issues have been the subject of pending administrative, arbitral, and court proceedings.206
128. In respect of the 10% Fee Cap, the Respondent argues that the Claimant first objected only in May 2001, when it should have been expected to do so throughout the Programme. However, this
203 Award on Jurisdiction, para. 379. ↩
204 Award on Jurisdiction, paras. 371-374. ↩
205 Award on Jurisdiction, paras. 373-374. ↩
206 See supra paras. 89-105. ↩
[Page 45]
ignores the complaints levelled by the Claimant against the administration of the “red notice” system, which is at the root of its claim that the application of the 10% Fee Cap was unreasonable.207 It also ignores the reservation of rights expressly made by the Claimant when issuing capped invoices.208
129. In respect of invoicing in Pesos versus U.S. dollars, the Respondent argues that the Claimant invoiced in Pesos during the pendency of the Contract. However, this ignores the fact that the peso-dollar peg rendered the currency immaterial. It also ignores the distinction between the value of the service rendered under the Contract, which was determined by reference to U.S. dollars, and the currency of invoices, which was stipulated to be Pesos.209
130. In respect of Decree 1060, the Respondent argues that the Claimant subjected itself to the application of this law by continuing to discharge its functions under the Contract. However, this ignores that national law doctrines by which a party may be taken to have submitted itself to a given legal regime or to certain legal consequences by conduct that is deemed to constitute consent in national law do not necessarily rise to the level of demonstrating acquiescence at an international level.
131. Accordingly, the Tribunal finds that the Respondent has not established a factual basis for its claims of acquiescence, estoppel, good faith, and prescription. The Tribunal thus dismisses these objections.
207 See supra paras. 74, 79-81. ↩
[Page 46]
132. The Claimant claims that the Respondent has violated Article 2(2) of the Treaty by:
133. The Claimant submits that the above measures breached the four different standards of protection set forth in Article 2(2), namely, the obligations concerning fair and equitable treatment (“FET”), unreasonable or discriminatory measures, full protection and security (“FPS”), and the umbrella clause.211 The Claimant has not put forward separate arguments in respect of each of these Treaty obligations, but rather focusses on the impugned measures, which it contends violate the Contract and Argentine law and thereby also the Treaty.212
134. The Respondent submits that the Claimant’s claims lack merit as the Respondent has “made all the relevant payments for the auditing services provided by Claimant” within the terms of the Contract and the applicable laws and regulations.213
135. The Claimant submits that, pursuant to Article 2(2) of the Treaty, the Respondent (i) is bound to afford the Claimant’s investment FET, FPS, and to observe any obligation it may have entered into with regard to it (also occasionally referred to as the “Umbrella Clause”); and (ii) is restricted from adopting any unreasonable or discriminatory measure by the Respondent that in any way impairs the management, maintenance, use, enjoyment or disposal of the Claimant’s investment.214
210 Statement of Claim, para. 122. ↩
211 Statement of Claim, Section D.2; Reply, para. 70. ↩
214 Statement of Claim, para. 123. ↩
[Page 47]
(a) The Claimant's Position
136. The Claimant maintains that the FET standard in Article 2(2) of the Treaty, interpreted in accordance with Article 31 of the VCLT, establishes an autonomous standard which is not limited to the minimum standard of treatment under customary international law.215 The Claimant states that the jurisprudence confirms that, “absent explicit wording to the contrary, the FET standard is not limited to the minimum standard of treatment under international law.”216 The Claimant underscores that the tribunal in National Grid v. Argentina reached this very conclusion in respect of Article 2(2) of the present Treaty.217 In any event, the Claimant submits that, even if the FET standard were to be equated to the customary international law minimum standard, the standard has evolved since its application in the Neer case, such that there is no meaningful difference to be made between the minimum standard of treatment under customary international law and an autonomous standard.218
137. The Claimant further submits that the FET standard “is very broad, and its meaning will depend on the specific circumstances of the case at issue”.219 Relying on the practice of arbitral tribunals, the Claimant contends that the FET standard may encompass the host state’s obligation to (i) protect the investor’s legitimate expectations based on the legal framework and on any
216 Reply, paras. 94-100; National Grid P.L.C v. The Argentine Republic, Award, 3 November 2008, paras. 167-169 (CLA-10); Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan, ICSID Case No. ARB/12/1, Decision on Liability, 10 November 2017, para. 6 (CLA-175); Deutsche Telekom A.G. v. India, PCA Case No. 2014-10, Interim Award, 13 December 2017, para. 330 (CLA-176); Indian Metals & Ferro Alloys Ltd v. Republic of Indonesia, PCA Case No. 2015-40, Award, 29 March 2019, para. 225 (CLA-177); Cervin Investissements S.A. and Rhone Investissements S.A. v. Republic of Costa Rica, ICSID Case No. ARB/13/2, Final Award, 7 March 2017, paras. 452-453 (CLA-178); Hearing Tr., Day 1 (6 April 2021), 21:7-22:23. ↩
217 Reply, para. 94; National Grid P.L.C v. The Argentine Republic, Award, 3 November 2008, paras. 167-169 (CLA-10). ↩
218 Reply, para. 101; Thomas Gosling and others v. Republic of Mauritius, ICSID Case No. ARB/16/32, Award, 18 February 2020, para. 243 (CLA-187); Saluka Investments B.V. v. The Czech Republic, PCA Case No. 2001-04, Partial Award, 17 March 2006, para. 291 (CLA-11); Biwater Gauff (Tanzania) Ltd. v. United Republic of Tanzania, ICSID Case No. ARB/05/22, Award, 24 July 2008, para. 592 (CLA-47); Rumeli Telekom A.S. and another v. Kazakhstan, ICSID Case No ARB/05/16, Award, 29 July 2008, para. 611 (CLA-91); Hearing Tr., Day 1 (6 April 2021), 23:22-24:6. ↩
219 Statement of Claim, paras. 125-127; Waste Management, Inc. v. United Mexican States, ICSID Case No. ARB(AF)/00/3, Final Award, 30 April 2004, para. 99 (CLA-6); Ronald S. Lauder v. The Czech Republic, Award, 3 September 2001, para. 292 (CLA-7); Noble Ventures, Inc. v. Romania, ICSID Case No. ARB/01/11, Award, 12 October 2005, para. 181 (CLA-8). ↩
[Page 48]
undertakings made by the host State;220 (ii) maintain a stable and predictable legal and business environment;221 (iii) act transparently and consistently;222 (iv) comply with its contractual obligations vis-à-vis the investor;223 (v) act in good faith;224 and (vi) not unjustly enrich itself.225
(b) The Respondent's Position
138. The Respondent submits that the FET standard provided for in Article 2(2) of the Treaty is equivalent to the minimum standard of treatment under customary international law.226 According to the Respondent, this minimum standard was defined in the Neer case as treatment that would “amount to an outrage, to bad faith, to wilful neglect of duty, or to an insufficiency of governmental action so far short of international standards that every reasonable and impartial
220 Statement of Claim, paras. 128, 130-134; Reply, para. 88; National Grid P.L.C v. The Argentine Republic, Award, 3 November 2008, para. 173 (CLA-10); Saluka Investments B.V. v. The Czech Republic, PCA Case No. 2001-04, Partial Award, 17 March 2006, paras. 301-302 (CLA-011); Frontier Petroleum Services Ltd. v. The Czech Republic, Final Award, 12 November 2010, para. 285 (CLA-015); Hearing Tr., Day 1 (6 April 2021), 26:15-27:4. ↩
221 Statement of Claim, paras. 128, 135-137; Reply, para. 88; CMS Gas Transmission Company v. The Republic of Argentina, ICSID Case No. ARB/01/8, Award, 12 May 2005, paras. 274-276 (CLA-016); Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, para. 300 (CLA-22); Gami Investments, Inc. v. The Government of the United Mexican States, Final Award, 15 November 2004, para. 91 (CLA-23). ↩
222 Statement of Claim, paras. 128, 138-140; Reply, para. 88; Metalclad Corporation v. The United Mexican States, ICSID Case No. ARB(AF)/97/1, Award, 30 August 2000, para. 76 (CLA-24); Técnicas Medioambientales Tecmed, S.A. v. The United Mexican States, ICSID Case No. ARB (AF)/00/2, Award, 29 May 2003, para. 167 (CLA-9); MTD Equity Sdn. Bhd. and MTD Chile S.A. v. Republic of Chile, ICSID Case No. ARB/01/7, Award, 25 May 2004, para. 163 (CLA-25). ↩
223 Statement of Claim, paras. 128, 141-145, Reply, para. 88; Mondev International Ltd. v. United States of America, ICSID Case No. ARB(AF)/99/2, Award, 11 October 2002, para. 134 (CLA-5); SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Decision on Jurisdiction, 2 February 2010, para. 146 (CLA-3); Noble Ventures, Inc. v. Romania, ICSID Case No. ARB/01/11, Award, 12 October 2005, para. 182 (CLA-8); Eureko B.V. v. Republic of Poland, Partial Award, 19 August 2005, para. 232 (CLA-26). ↩
224 Statement of Claim, paras. 128, 146-149; Reply, para. 88; Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, paras. 297-299 (CLA-22); Técnicas Medioambientales Tecmed, S.A. v. The United Mexican States, ICSID Case No. ARB (AF)/00/2, Award, 29 May 2003, para. 153 (CLA-9); Waste Management, Inc. v. United Mexican States, ICSID Case No. ARB(AF)/00/3, Final Award, 30 April 2004, para. 138 (CLA-6); Siemens A.G. v. The Argentine Republic, ICSID Case No. ARB/02/8, Award, 6 February 2007, para. 308 (CLA-29); Saluka Investments B.V. v. The Czech Republic, Partial Award, 17 March 2006, para. 307 (CLA-11); Frontier Petroleum Services Ltd. v. The Czech Republic, UNCITRAL, Final Award, 12 November 2010, para. 300 (CLA-15). ↩
225 Statement of Claim, paras. 128, 150-151; Reply, para. 88; A. Nussbaum, Arbitration Between the Lena Goldfields Ltd. and the Soviet Government, 36 Cornell L. Rev. 31 (1950) (CLA-38); Saluka Investments B.V. v. The Czech Republic, UNCITRAL, Partial Award, 17 March 2006, paras. 448-456 and 502 (CLA-11). ↩
226 Statement of Defence, paras. 354-363; Rejoinder, para. 239. ↩
[Page 49]
man would readily recognize its insufficiency.”227 The Respondent maintains that current case law reaffirms this standard.228 For instance, the Respondent refers to the award in Lauder v. Czech Republic, in which the tribunal determined that, absent a definition of FET in the applicable treaty, this standard “provides a ‘minimum international standard which forms part of customary international law’”.229 The Respondent argues that this is consistent with the interpretation of the Treaty under the VCLT.230
139. The Respondent further asserts that the FET standard does not encompass the protection of legitimate expectations of investors or a guarantee of legal and business stability.231 Relying on the annulment decision in MTD v. Chile, the Respondent avers that “[t]he obligations of the host State towards foreign investors derive from the terms of the applicable investment treaty and not from any set of expectations investors may have or claim to have”.232 The Respondent further cites Hochtief v. Argentina for the idea that, absent a specific promise by Argentina, the Claimant had no legitimate expectation that the legislation on Peso-U.S. dollar parity would be maintained indefinitely.233 Finally, the Respondent maintains that “mere breaches of contract do not amount to violations of the fair and equitable treatment standard.”234 For the Respondent, a violation of the FET standard requires the Claimant to establish that the Respondent committed a breach in exercise of its sovereign power.235
227 Statement of Defence, para. 355. ↩
228 Rejoinder, paras. 243-247; Hearing Tr., Day 1 (6 April 2021), 107:15-108:3; Glamis Gold, Ltd. v. United States of America, Award, 8 June 2009, paras. 614-615 (RLA-183); Alex Genin, Eastern Credit Limited, Inc. y A.S. Baltoil v. Republic of Estonia, ICSID Case No. ARB/99/2, Award, 25 June 2001 (RLA-186). ↩
229 Rejoinder, para. 244; Ronald S. Lauder v. Czech Republic, Award, 3 September 2002, para. 292 (RLA-144). ↩
231 Statement of Defence, paras. 369-378; Rejoinder, para. 239; Hearing Tr., Day 1 (6 April 2021), 108:4-18. ↩
232 Statement of Defence, para. 371; Rejoinder, para. 239; MTD Equity Sdn Bhd. & MTD Chile S.A. v. Republic of Chile, ICSID Case No. ARB/01/7, Decision on Annulment, 21 March 2007, paras. 66-67 (RLA-208). ↩
233 Statement of Defence, para. 374; Rejoinder, para. 249; Hochtief AG v. Argentine Republic, ICSID Case No. ARB/07/31, Decision on Liability, 29 December 2014, para. 239 (RLA-107). ↩
234 Statement of Defence, para. 375; Rejoinder, para. 241; Bayindir Insaat Turizm Ticaret Ve Sanayi A. Ş. v. Islamic Republic of Pakistan, ICSID Case No. ARB/03/29, Award, 27 August 2009, para. 180 (RLA-209). ↩
235 Statement of Defence, para. 375; Rejoinder, para. 241; Bayindir Insaat Turizm Ticaret Ve Sanayi A. Ş. v. Islamic Republic of Pakistan, ICSID Case No. ARB/03/29, Award, 27 August 2009, para. 180 (RLA-209). ↩
[Page 50]
(a) The Claimant's Position
140. The Claimant notes that, in addition to FET, Article 2(2) also provides that “[n]either Contracting Party shall in any way impair by unreasonable or discriminatory measures the management, maintenance, use, enjoyment or disposal of investments in its territory of investors of the other Contracting Party”.236 The Claimant submits that, under this obligation, the relevant question is “whether the measures complained about by the Claimant are either ‘unreasonable’ and/or ‘discriminatory’”.237
141. The Claimant asserts that the protection in respect of “unreasonable” measures substantially overlaps with the FET standard.238 The Claimant points out that a number of tribunals have equated “unreasonable” with “unfair”.239 However, the Claimant maintains that it would be inappropriate to equate “unreasonableness” with “arbitrariness”, given that the latter term does not appear in Article 2(2).240 The Claimant emphasizes that this is consistent with the findings of the tribunal in BG Group v. Argentina, which also applied Article 2(2) of the same Treaty.241
(b) The Respondent's Position
142. According to the Respondent, the standard of protection against unreasonable and discriminatory measures under Article 2(2) of the Treaty includes two types of measures.242 On the one hand, “unreasonable” measures for the Respondent “refer to measures adopted with no rationale behind them”.243 The Respondent contends that, as held in National Grid v. Argentina, the plain meaning of the terms “unreasonable” and “arbitrary” “is substantially the same in the sense of something
236 Statement of Claim, para. 152; Reply, para. 111. ↩
238 Statement of Claim, para. 153. ↩
239 Statement of Claim, para. 154; MTD Equity Sdn. Bhd. and MTD Chile S.A. v. Republic of Chile, ICSID Case No. ARB/01/7, Award, 25 May 2004, para. 196 (CLA-25); CME Czech Republic B.V. v. The Czech Republic, Partial Award, 13 September 2001, para. 612 (CLA-39). ↩
240 Statement of Claim, para. 155; Reply, paras. 111-114; Cambridge Dictionary, definition of the term “Unreasonable” (C-143); Cambridge Dictionary, definition of the term “Arbitrary” (C-144); Hearing Tr., Day 1 (6 April 2021), 30:11-19. ↩
241 Reply, para. 115; BG Group PLC. v. The Republic of Argentina, Final Award, 24 December 2007, paras. 340-342 (CLA-40). ↩
242 Statement of Defence, paras. 408-414; Rejoinder, paras. 274-279. ↩
[Page 51]
done capriciously, without reason”.244 On the other hand, the Respondent asserts that “discriminatory” measures “are measures that make an unjustified difference in treatment between two parties that are in similar situations.”245
143. The Respondent contends that the unreasonable and discriminatory measures standard and FET standard afford different types of protection.246 Otherwise, in the Respondent’s view, the Tribunal should decide that it is unnecessary to address these claims separately.247
(a) The Claimant's Position
144. The Claimant observes that Article 2(2) further establishes that “[i]nvestments of investors of each Contracting Party [...] shall enjoy protection and constant security in the territory of the other Contracting Party”.248 Given the provision’s unqualified text, the Claimant affirms, it requires the Respondent to protect both the physical and legal security of the Claimant’s investment.249 This is supported, in the Claimant’s view, by the fact that the definition of “investment” in the Treaty covers both physical assets and intangible assets. As noted in Siemens v. Argentina, the Claimant contends that “[i]t is difficult to understand how the physical security of an intangible asset would be achieved”.250
145. The Claimant avers that the broad nature of the full protection and security standard has been confirmed by several tribunals, including the one in National Grid v. Argentina which applied the Treaty at issue in these proceedings and whose conclusion on this issue was “reinforced by the inclusion of this commitment in the same article of the Treaty as the language on fair and equitable treatment.”251 The Claimant acknowledges that BG Group v. Argentina and AWG Group v.
244 Statement of Defence, para. 408; Rejoinder, para. 274; National Grid P.L.C. v. Argentine Republic, Award, 3 November 2008, para. 197 (CLA-10); Hearing Tr., Day 1 (6 April 2021), 108:19-109:9. ↩
245 Rejoinder, para. 277; Joseph C. Lemire v. Ukraine, ICSID Case No. ARB/06/18, Decision on Liability, 14 January 2010, para. 261 (RLA-294). ↩
246 Statement of Defence, paras. 405-407; Rejoinder, para. 272; Hearing Tr., Day 1 (6 April 2021), 119:10-21. ↩
247 Statement of Defence, paras. 405-407; Rejoinder, para. 273. ↩
248 Statement of Claim, para. 158; Reply, para. 103. ↩
249 Statement of Claim, para. 159; Reply, para. 104; Hearing Tr., Day 1 (6 April 2021), 30:4-10. ↩
250 Statement of Claim, para. 160; Siemens A.G. v. The Argentine Republic, ICSID Case No. ARB/02/8, Award, 6 February 2007, para. 303 (CLA-29). ↩
251 Statement of Claim, paras. 160-165; Reply, para. 108; National Grid P.L.C v. The Argentine Republic, Award, 3 November 2008, paras. 187, 189 (CLA-10); Siemens A.G. v. The Argentine Republic, ICSID Case No. ARB/02/8, Award, 6 February 2007, para. 303 (CLA-29); Biwater Gauff (Tanzania) Ltd. v. ↩
[Page 52]
Argentina reached a different conclusion, but contends that they were wrongly decided.252 On the one hand, the Claimant argues that BG Group v. Argentina ignored the specific terms and context of the obligation.253 Meanwhile, the Claimant considers that AWG Group v. Argentina improperly focussed on the absence of the word “full” in Article 2(2), rather than the unqualified nature of the provision.254
(b) The Respondent's Position
146. The Respondent asserts that the sole purpose of the standard of “protection and constant security” is to provide physical protection and security to investors and their investments, and does not extend to legal stability.255 The Respondent maintains that this is consistent with the decisions in BG Group v. Argentina and AWG Group v. Argentina under the same Treaty.256
(a) The Claimant's Position
147. The Claimant asserts that Article 2(2) also contains an umbrella clause, according to which “[e]ach Contracting Party shall observe any obligation it may have entered into with regard to investments of investors of the other Contracting Party”.257
252 United Republic of Tanzania, ICSID Case No. ARB/05/22, Award, 24 July 2008, para. 729 (CLA-47); CME Czech Republic B.V. v. The Czech Republic, Partial Award, 13 September 2001, para. 613 (CLA-39); Čskoslovenska Obchodní Banka, A.S. v. The Slovak Republic, ICSID Case No. ARB/97/4, Award, 29 December 2004, para. 170 (CLA-48). ↩
253 Reply, para. 109; BG Group PLC. v. The Republic of Argentina, Final Award, 24 December 2007, para. 326 (CLA-40); AWG Group Ltd. v. The Argentine Republic, Decision on Liability, 30 July 2010, para. 175 (CLA-12). ↩
254 Reply, para. 109; BG Group PLC. v. The Republic of Argentina, Final Award, 24 December 2007, para. 326 (CLA-40). ↩
255 Reply, para. 109; AWG Group Ltd. v. The Argentine Republic, Decision on Liability, 30 July 2010, para. 175 (CLA-12). ↩
256 Statement of Defence, paras. 391-397; Rejoinder, para. 259; Hearing Tr., Day 1 (6 April 2021), 111:18-112:1. ↩
257 Statement of Defence, paras. 394-395; Rejoinder, paras. 259-262; BG Group PLC. v. The Republic of Argentina, Final Award, 24 December 2007, paras. 324, 326 (CLA-40); Suez, Sociedad General de Aguas de Barcelona S.A., Vivendi Universal S.A. and AWG Group Limited v. Argentine Republic, ICSID Case No. ARB/03/19, Decision on Liability, 30 July 2010, para. 175 (CLA-12); Hearing Tr., Day 1 (6 April 2021), 112:1-9. ↩
Statement of Claim, para. 168; Reply, para. 73.
[Page 53]
148. The Claimant submits that contractual commitments a host State has entered into with an investor constitute “obligations” within the meaning of the Umbrella Clause.258 In this respect, the Claimant emphasizes that, in its Award on Jurisdiction, the Tribunal held that “[s]ince the Umbrella Clause elevates the rights and obligations provided for in the Contract to the level of international law, a breach of these obligations is a breach of the Umbrella Clause.”259 Likewise, referring among others to the decision on jurisdiction in SGS v. Paraguay, the Claimant asserts that “[a]s a matter of the ordinary meaning of the term, a contractual obligation is the prototypical legally binding ‘commitment.’”260 The Claimant affirms that the inclusion of contractual commitments within the scope of the Umbrella Clause is also confirmed by other provisions of the Treaty.261 In particular, the Claimant refers to the definition of “investment” (Article 1(a)), which covers “claims to money which are directly related to [...] any performance under contract having a financial value”, and a dispute resolution provision (Article 8) that provides that one of the sources of law to be applied shall be “the terms of any specific agreement concluded in relation to such an investment”.262
149. The Claimant disputes the Respondent’s contention that the scope of the Umbrella Clause is limited to obligations entered into by the Respondent acting as a sovereign entity, as opposed to a private party.263 The Claimant considers that the Respondent’s contention is inconsistent with the interpretation of the Umbrella Clause already made by the Tribunal in its Award on Jurisdiction.264 The Claimant underscores that the Tribunal held that:
One must begin with the plain meaning – the “ordinary meaning” – of the Umbrella Clause [...]. Considering the use of the mandatory term “shall”, the sentence is imperative. The expression “any obligation” is capacious, i.e. it is not limited to certain types of obligations but rather encompasses all obligations a host State may have entered into with regard to investments of investors of the other Contracting Party. [...] Interpreting the wording of the
258 Statement of Claim, paras. 169-170. ↩
259 Reply, para. 74; Award on Jurisdiction, para. 337; Hearing Tr., Day 1 (6 April 2021), 19:1-9. ↩
260 Reply, paras. 78-80; Statement of Claim, paras. 171-175; SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, paras. 90-91 (CLA-54); Noble Ventures, Inc. v. Romania, ICSID Case No. ARB/01/11, Award, 12 October 2005, para. 51 (CLA-8); SGS Société Générale de Surveillance S.A. v. Republic of the Philippines, ICSID Case No. ARB/02/6, Decision on Jurisdiction, 29 January 2004, para. 119 (CLA-2); Eureko B.V. v. Republic of Poland, Partial Award, 19 August 2005, para. 250 (CLA-26); SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Decision on Jurisdiction, 12 February 2010, paras. 91, 168 (CLA-3); Hearing Tr., Day 1 (6 April 2021), 15:14-16:15. ↩
261 Statement of Claim, para. 176. ↩
262 Statement of Claim, para. 176. ↩
263 Reply, paras. 77-78; Hearing Tr., Day 1 (6 April 2021), 14:22-15:11. ↩
264 Reply, paras. 77-78; Hearing Tr., Day 1 (6 April 2021), 14:22-15:6. ↩
[Page 54]
Umbrella Clause, it is clear that each Contracting Party shall observe any obligation it has assumed, or will in the future assume, with regard to investments covered by the Treaty.265
150. The Claimant points to a number of other decisions that have similarly eschewed such non-textual limitations when applying unqualified umbrella clauses.266
151. The Claimant further asserts that the application of the Umbrella Clause in respect of a particular obligation is not conditioned upon any domestic law procedural requirements, including domestic law time-bars, as such restrictions are not supported by the text of Article 2(2).267
(b) The Respondent's Position
152. The Respondent argues that the Umbrella Clause does not change the nature or content of, nor the law applicable to, the contractual obligations covered by such clause.268 Quoting the decision on annulment in CMS v. Argentina, the Respondent posits that “[t]he effect of the umbrella clause is not to transform the obligation which is relied on into something else; the content of the obligation is unaffected, as is its proper law.”269
153. In accordance with the foregoing, the Respondent submits that only actions taken by the State as a sovereign as opposed to a private capacity can breach the Umbrella Clause.270 The Respondent refers in this connection to various prior decisions, including Azurix v. Argentina, El Paso v. Argentina, and Supervisión y Control v. Costa Rica.271 Contrary to the Claimant’s assertion, the Respondent argues that this contention does not contradict the Tribunal’s interpretation of the
265 Reply, para. 75; Award on Jurisdiction, para. 343; Hearing Tr., Day 1 (6 April 2021), 12:14-14:18. ↩
266 Reply, paras. 79-84; SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, paras. 90-91, 95, 135, 162 (CLA-54); Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Jurisdiction, 2 June 2010, para. 179 (CLA-154); Duke Energy Electroquil Partners & Electroquil S.A. v. Republic of Ecuador, ICSID Case No. ARB/04/19, Award, 18 August 2008, para. 320 (CLA-51). ↩
267 Hearing Tr., Day 7 (14 April 2021), 1014:18-1016:19. ↩
268 Statement of Defence, paras. 418-421; Rejoinder, para. 284; CMS Gas Transmission Company v. Argentine Republic, ICSID Case No. ARB/01/8, Decision on Annulment, 25 September 2007, para. 95(c) (RLA-62); Toto Costruzioni Generali S.p.A. v. The Republic of Lebanon, ICSID Case No. ARB/07/12, Decision on Jurisdiction, 11 September 2009, para. 202 (RLA-33); Hearing Tr., Day 1 (6 April 2021), 112:10-113:7. ↩
269 Statement of Defence, para. 419; CMS Gas Transmission Company v. Argentine Republic, ICSID Case No. ARB/01/8, Decision on Annulment, 25 September 2007, para. 95(c) (RLA-62). ↩
270 Statement of Defence, para. 422; Rejoinder, paras. 287-290. ↩
271 Statement of Defence, para. 422; Rejoinder, paras. 287-290; Azurix Corp. v. Argentine Republic, ICSID Case No. ARB/01/12, Award, 14 July 2006, para. 315 (CLA-28); Supervisión y Control S.A. v. Republic of Costa Rica, ICSID Case No. ARB/12/4, Award, 18 January 2017, para. 282 (RLA-281); El Paso Energy International Company v. Argentine Republic, ICSID Case No. ARB/03/15, Decision on Jurisdiction, 27 April 2006, paras. 82, 84 (RLA-64). ↩
[Page 55]
Umbrella Clause.272 The Respondent notes that, in its Award on Jurisdiction, the Tribunal did “not refer to the types of measures that may violate the umbrella clause, but to the types of commitments that are protected by such standard.”273 In any event, the Respondent contends that the Tribunal’s observations regarding the effect of the Umbrella Clause in its Award on Jurisdiction constituted a “prima facie decision” that does not constrain the application of this provision to the merits of the dispute.274
154. Additionally, the Respondent maintains that the Umbrella Clause only applies to commitments “entered into” with the investor.275 It follows for the Respondent that, in the instant case, only the Contract during its pendency may be considered for the application of the Umbrella Clause, and not external laws or administrative regulations.276 The Respondent asserts that Decree 1060/2001 and Resolution 325 are thus irrelevant to the Claimant’s claim under the Umbrella Clause.277
(a) The Claimant's Position
155. The Claimant submits that the Respondent breached Article 2(2) of the Treaty by wrongfully applying the 10% Fee Cap under Clause 3 of the Contract.278 The Claimant explains that, over the course of the Programme, it issued invoices for USD 4,538,571.58 that were never paid because they exceeded the 10% Fee Cap under the Contract.279 It is the Claimant’s position that the
273 Rejoinder, para. 287; Award on Jurisdiction, para. 345. ↩
275 Statement of Defence, paras. 423-426; Rejoinder, paras. 285, 291; CMS Gas Transmission Company v. Argentine Republic, ICSID Case No. ARB/01/8, Decision on Annulment, 25 September 2007, para. 95(a) (RLA-62); Invesmart, B.V. v. Czech Republic, Award, 26 June 2009, para. 526 (RLA-219); Oxus Gold PLC v. The Republic of Uzbekistan, Award, 17 December 2015, paras. 364-371 (RLA-220); 9REN Holding S.à.r.l v. Kingdom of Spain, ICSID Case No. ARB/15/15, Award, 31 May 2019, para. 342 (RLA-223). ↩
276 Hearing Tr., Day 7 (14 April 2021), 1149:13-22. ↩
277 Hearing Tr., Day 7 (14 April 2021), 1149:23-1150:16. ↩
278 Statement of Claim, paras. 179-184; Reply, paras. 13-34. ↩
[Page 56]
application of the 10% Fee Cap by the Respondent breached both the Contract and Argentine law, and thereby also violated Article 2(2) of the Treaty.280
156. First, the Claimant maintains that, under Clause 3 of the Contract, the application of the 10% Fee Cap was conditioned upon the Respondent’s establishment of an adequate system to select the Inspection Certificates to be audited by the Claimant.281 According to the Claimant, Clauses 8 and 13 of the Contract, Article 6 of the Decree 477/97, and the fact that the Respondent attempted to put in place the “red channel” system further confirm that the Respondent was obliged to implement such a selection system.282 However, the Claimant alleges that the Respondent “never implemented a functioning selection system.”283 The Claimant argues that the system that the Respondent did put in place - the “red channel” system – failed to work in practice because the “Customs Officials charged with alerting ICS every time there [was] an item to audit [...] simply” did not do so.284 The Claimant contends that different government officials acknowledged these practical shortcomings and ultimately instructed the Claimant to “install itself physically at the points of destination and to try to take as many dispatches as it can, [even if] this is not the ideal solution.”285
157. The Claimant asserts that the lack of an adequate selection system prevented it from complying with the 10% Fee Cap because, in the absence of such a system, it was not possible to know how much the Inspection Companies’ total invoicing would be for each quarter, and thus, where its own 10% Fee Cap would fall.286 Accordingly, the Claimant argues that the Respondent cannot invoke the 10% Fee Cap to refuse payment of amounts in excess thereof “in circumstances where its own failures to perform prevented ICS from being able to operate as intended”.287 According to the Claimant, the only entity that had access to the information necessary to estimate the 10%
280 Reply, para. 8. See also Statement of Claim, para. 179. ↩
281 Statement of Claim, para. 180; Reply, paras. 19-22; Contract, Clause 3 (C-2); Hearing Tr., Day 7 (14 April 2021), 1065:4-1070:15. ↩
282 Reply, para. 22; Contract, Clauses 8, 13 (C-2); Hearing Tr., Day 7 (14 April 2021), 1060:4-1061:6, 1063:11-1064:7; Decree 477/97, Article 6 and Annex III, Section c(VIII) (C-6). ↩
283 Statement of Claim, para. 181; Reply, para. 14. ↩
284 Hearing Tr., Day 1 (6 April 2021), 55:10-56:10; Report conducted at terminals 1 and 2, 4 February 1999 (C-28). ↩
285 Statement of Claim, para. 65; Letter from the Committee to AFIP, 6 August 1999 (C-32) (translation by the Claimant); Report conducted at terminals 1 and 2, 4 February 1999 (C-28); Hearing Tr., Day 1 (6 April 2021), 56:11-57:1; Hearing Tr., Day 2 (7 April 2021), 273:1-11. ↩
286 Reply, paras. 21-24; Hearing Tr., Day 1 (6 April 2021), 54:11-55; Hearing Tr., Day 7 (14 April 2021), 1024:21-1026:6. ↩
287 Statement of Claim, para. 182; Reply, para. 16; Hearing Tr., Day 1 (6 April 2021), 58:12-16. ↩
[Page 57]
Fee Cap was the Committee.288 The Claimant alleges that it did not have access to the databases of the Committee or the Inspection Companies.289 Even if it did have access to the databases of the Inspection Companies, the Claimant asserts, it would only have been able to calculate the number of certificates below the 10% Fee Cap after the end of each month, by which time it may have already exceeded the 10% Fee Cap.290
158. Second, the Claimant submits that the 10% Fee Cap was also rendered inapplicable by Argentina’s unilateral amendment of key terms of the Programme when it adopted the 2000-2001 Resolutions.291 The Claimant points out that through the 2000-2001 Resolutions the AFIP excluded a number of goods from the scope of the Programme, effectively modifying the basis for calculating the Claimant’s fees under the Contract.292 According to the Claimant, the reduced scope of goods subject to the Programme caused a significant reduction to the level of fees earnable by and payable to the Inspection Companies, and consequently, the level of the 10% Fee Cap.293 As a result, the Claimant alleges that the application of the 10% Fee Cap was rendered unlawful.294
159. Third, the Claimant alleges that its claim for the amounts in excess of the 10% Fee Cap is not precluded by the fact that the Claimant failed to formally challenge the imposition of the 10% Fee Cap through administrative appeals, as the Respondent alleges.295 The Claimant submits that there is no such requirement under Argentine law.296 In this respect, the Claimant notes that the Petracca case, on which the Respondent relies, determined that this requirement applies with respect to “administrative acts” within the terms of the LPA.297 Relying on the opinion of its expert, Dr. Bianchi, the Claimant contends that Argentina’s purported imposition of the 10% Fee Cap “do[es] not meet the requirements set forth in Section 7 of the LPA”, and thus, does not
288 Hearing Tr., Day 7 (14 April 2021), 1025:23-1026:1. ↩
289 Hearing Tr., Day 7 (14 April 2021), 1024:21-1025:17, 1027:19-1028:1; Hearing Tr., Day 2 (7 April 2021), 285:23-286:24. ↩
290 Hearing Tr., Day 7 (14 April 2021), 1028:2-10; Hearing Tr., Day 3 (8 April 2021), 464:2-12. ↩
291 Statement of Claim, para. 182; Reply, paras. 32-34; First Bianchi Report, paras. 54, 58. ↩
292 Statement of Claim, para. 182; Reply, paras. 32-34; First Bianchi Report, paras. 54, 58. ↩
293 Statement of Claim, para. 69; Reply, para. 15. ↩
294 Statement of Claim, para. 182; Reply, paras. 32-34; First Bianchi Report, paras. 54, 58. ↩
295 Reply, paras. 25-28; Hearing Tr., Day 7 (14 April 2021), 1070:16-1072:7. ↩
297 Reply, para. 26; Second Bianchi Report, paras. 56-61; Petracca e Hijos, S. A. et al. v. National government -Ente Autárquico Mundial 78, Federal Court of Appeals in Administrative Matters sitting in full bench, Judgement, 24 April 1986, L.L., 1986-D-10 (RLA-113). ↩
[Page 58]
constitute an “administrative act” under the LPA.298 In addition, the Claimant alleges that the Petracca case “would not apply to the current questions of [...] ongoing contractual performance.”299 In any event, the Claimant contends that such requirement would be inconsistent with Article 2(2) of the Treaty.300
160. Fourth, the Claimant reiterates that the issuance of invoices below the 10% Fee Cap while the Programme was ongoing does not affect its right to claim the amounts in excess of that limit in this arbitration.301 The Claimant reiterates that it had no choice but to comply with Argentina’s demands and issue capped invoices, as the Respondent would not otherwise make even partial payment of the Claimant’s fees. Moreover, the Claimant underlines that, when issuing invoices for capped amounts, it reserved its right to claim the amount over the 10% Fee Cap.302
161. On the basis of the foregoing, the Claimant submits that the Respondent’s conduct pertaining to the 10% Fee Cap breached the four standards provided for in Article 2(2) of the Treaty.303
162. First, the Claimant claims that the Respondent breached the FET standard by frustrating the Claimant’s legitimate expectations that the Respondent would administer the Programme in accordance with the Contract and Argentine law, and honour its payment obligations thereunder.304 The Claimant also submits that the Respondent breached the FET standard by “acting inconsistently and unreasonably by failing to implement an adequate selection system, instead requiring the Claimant to perform Ordinary Services on a much larger scale than envisaged by the Contract and then refusing to compensate the Claimant for the services it performed”.305 According to the Claimant, the Respondent likewise unjustly enriched itself by
298 Reply, para. 26; Second Bianchi Report, paras. 56-57; Section 7 of the Administrative Procedure Act (ABB-56). ↩
299 Hearing Tr., Day 1 (6 April 2021), 59:10-19. ↩
300 Hearing Tr., Day 1 (6 April 2021), 36:20-37:12, 58:20-59:9; Link-Trading Joint Stock Company v. Department for Customs Control of the Republic of Moldova, UNCITRAL, Award, 18 April 2002 (CLA-144); Emilio Agustín Maffezini v. The Kingdom of Spain, ICSID Case No. ARB/97/7, Award, 13 November 2000 (CLA-164); Luigiterzo Bosca v. Lithuania, UNCITRAL, Award, 17 May 2013 (CLA-145). ↩
301 Hearing Tr., Day 7 (14 April 2021), 1028:23-1030:18. ↩
302 Hearing Tr., Day 7 (14 April 2021), 1028:23-1029:25; Hearing Tr., Day 2 (7 April 2021), 181:21-183:3. ↩
303 Statement of Claim, para. 184. ↩
304 Statement of Claim, para. 184(a)(i)-(ii); Hearing Tr., Day 1 (6 April 2021), 28:16-24. ↩
305 Statement of Claim, para. 184(a)(iii). ↩
[Page 59]
benefiting from the additional auditing services the Claimant provided while refusing to compensate such services.306
163. Second, the Claimant submits that the Respondent’s conduct pertaining to the 10% Fee Cap constitutes an unreasonable measure which impairs the Claimant’s management, maintenance, use, enjoyment and disposal of its investment.307
164. Third, the Claimant maintains that the Respondent failed to protect the Claimant’s legal rights under the Contract, and therefore, breached its obligation to afford the Claimant’s investment full protection and security.308
165. Fourth, the Claimant asserts that the Respondent breached the Umbrella Clause by failing to observe its obligations vis-à-vis the Claimant, arising under the Contract.309
(b) The Respondent's Position
166. The Respondent submits that the application of the 10% Fee Cap was in accordance with the terms of the Contract agreed by the Claimant, and in particular Clauses 3 and 6, which stated that the Claimant’s fees would “in no case” exceed the 10% Fee Cap and that the Claimant had to “make the necessary arrangements to comply with randomized checks, ‘always ensuring that the relevant values do not form a base which might exceed the maximum fees.’”310 For the Respondent, the Claimant’s claims thus run counter to pacta sunt servanda and good faith.311
167. The Respondent maintains that neither the alleged failure to implement a selection system nor the 2000-2001 Resolutions entitle the Claimant to an exemption from the 10% Fee Cap.312
306 Statement of Claim, para. 184(a)(iv). ↩
307 Statement of Claim, para. 184(b). ↩
308 Statement of Claim, para. 184(c). ↩
309 Statement of Claim, para. 184(d); Hearing Tr., Day 1 (6 April 2021), 20:19-23. ↩
310 Rejoinder, paras. 64, 252, 268, 281, 295; Contract, Clauses 3, 6 (C-2); Hearing Tr., Day 1 (6 April 2021), 81:3-83:22. ↩
311 Statement of Defence, paras. 77-94; Rejoinder, para. 63. ↩
312 Rejoinder, paras. 84-86, 92-97. ↩
[Page 60]
168. First, the Respondent contends that it did not have an obligation to implement a selection system under the Contract.313 Rather, the Respondent asserts that pursuant to Clauses 3, 6 and 8 of the Contract “the Auditor had the exclusive responsibility of providing the audit system.”314
169. The Respondent avers that, even though it was impossible to know at the beginning of each quarter which would be the upcoming import flows covered by the Programme,315 the Claimant was better positioned than the Committee to estimate the number of audits that would be below the 10% Fee Cap.316 In this respect, the Respondent contends that the Claimant represented on multiple occasions that it “had sufficient means and experience to meet the 10% fee cap”, including at the time of its proposal for Tender No. 13/97 and in the Audit Manual prepared by the Claimant.317 In particular, the Respondent points out that the Audit Manual provided that operations to be audited could be selected either pursuant to the instructions of MECON or by means of an algorithm or based on the value of the operations.318 The Respondent further asserts that the Claimant held its own statistics and had the right to access the databases of the Inspection Companies and the Committee.319
170. The Respondent asserts that under Clause 8 of the Contract its obligation with respect to the selection system was limited to establishing a selection criteria.320 Thus, in its view, the Claimant could not have had the legitimate expectation that the Respondent would provide a selection system that would guarantee observance of the 10% Fee Cap.321 The Respondent notes that Dr. Alberto B. Bianchi, the Claimant’s expert of Argentine law, confirmed that the Committee’s obligation under Clause 8 was to establish a “criterion for the selection” and that the selection system did not have to guarantee compliance with the 10% Fee Cap.322
313 Hearing Tr., Day 1 (6 April 2021), 82:6-8. ↩
314 Hearing Tr., Day 1 (6 April 2021), 82:6-84:23. ↩
315 Hearing Tr., Day 7 (14 April 2021), 1152:5-12. ↩
316 Hearing Tr., Day 7 (14 April 2021), 1109:10-1110:10. ↩
317 Statement of Defence, paras. 95-108; Rejoinder, paras. 66-71. ↩
318 Rejoinder, para. 68; Procedure Manual of the Programme for the Auditing of Pre-Shipment Inspection Certificates prepared by Claimant, 23 December 1997, Section I – General Procedures (R-148). ↩
319 Hearing Tr., Day 7 (14 April 2021), 1109:10-1110:10; Hearing Tr., Day 1 (6 April 2021), 149:16-22; Hearing Tr., Day 2 (7 April 2021), 164:22-166:1. ↩
320 Hearing Tr., Day 7 (14 April 2021), 1151:24-1152:12. ↩
321 Hearing Tr., Day 7 (14 April 2021), 1151:24-1152:12. ↩
322 Hearing Tr., Day 7 (14 April 2021), 1107:18-1108:6; Hearing Tr., Day 3 (8 April 2021), 412:16-414:5, 411:7-19. ↩
[Page 61]
171. Second, it is the Respondent’s position that it appropriately established a selection criteria that enabled the Claimant to perform the services provided for in the Contract.323 The Respondent asserts that the Claimant acknowledged as much in its monthly reports addressed to the Committee and on its website, where it explained that its auditing services were triggered when a shipment was processed by customs through the “red channel” category (as per the criteria set forth in Resolution 396/97) that contained goods within the tariff classifications covered by the Programme.324 The Respondent further avers that Mr. Juan Santamaría, operations coordinator of the Claimant’s subsidiary in Argentina since 1998, also confirmed during the Hearing on the Merits that a selection criterion was indeed established by the Committee.325
172. Third, even if it were determined that it breached its alleged obligation to implement a selection system, the Respondent argues that the Claimant was still not entitled to fees above the 10% Fee Cap.326 The Respondent contends that the implementation of a selection system was not a “condition precedent” for the application of the 10% Fee Cap.327 Rather, the Respondent contends that, when properly interpreted, Clauses 3 and 6 of the Contract establish that the 10% Fee Cap was to be applied “regardless of the systems to be implemented”.328 Moreover, the Respondent argues that the “contractual breach exception” under Article 1201 of the Argentine Civil Code is not applicable in the instant case.329 The Respondent asserts that this exception only applies to ongoing contracts, and in the case of administrative contracts – such as the Contract at issue in this dispute - is limited to situations in which the “government’s non-compliance is of ‘such a serious type that they make it impossible to perform the contract.’”330 In any event, the Respondent contends that the application of the “contractual breach exception” would only have
323 Rejoinder, paras. 72-91, 253; Statement of Defence, para. 20; DGA Resolution No. 396/97, published in the Official Journal No. 28783, Section 1, 27 November 1997 (R-18); Hearing Tr., Day 1 (6 April 2021), 86:25-87:88:1. ↩
324 Rejoinder, paras. 75-82; ICS, Monthly Reports, December 1998, March 1999 – May 1999, July 1999 – March 2000, September 2000, December 2000, March 2001 – December 2001, Section 1.3 (C-73 – C-97); ICS, Monthly Report, May 1998, Section e), p. 4 (R-151); ICS, Monthly Report, June 1998, p. 3 (R-152); Snapshot of ICS’s website of April 2001, available at https://web.archive.org/web/*/http://icsinspections.com/ (R-147). ↩
325 Hearing Tr., Day 7 (14 April 2021), 1110:11-14; Hearing Tr., Day 2 (7 April 2021), 173:17-23. ↩
326 Statement of Defence, paras. 89-90; Rejoinder, paras. 84-87. ↩
328 Rejoinder, paras. 65, 86; Second Comadira Report, paras. 15-16, 43-45; Hearing Tr., Day 7 (14 April 2021), 1105:17-1108:17. ↩
329 Statement of Defence, paras. 83-94; Rejoinder, para. 84; Second Comadira Report, paras. 34-35; Hearing Tr., Day 1 (6 April 2021), 85:2-86:14. ↩
330 Statement of Defence, paras. 85, 91-92; First Comadira Report, para. 85. ↩
[Page 62]
“entitled Claimant to refuse to provide the service until the obligations allegedly infringed were fulfilled, and to nothing else”.331
173. Fourth, the Respondent argues that the Claimant accepted the application of the 10% Fee Cap by failing to challenge the validity of this limitation since it started to be applied by the Committee in 1998 through the available administrative and judicial procedures.332 The Respondent alleges that the Claimant did not voice any reservations pertaining to the application of the 10% Fee Cap throughout the term of the Programme and until after the termination of the Programme in January 2002, including in respect of periods that had already been invoiced and paid for.333 For the Respondent, in accordance with the Petracca doctrine, the Claimant was required to have challenged the application of the 10% Fee Cap within the 90-day limit of the LPA (i.e., in 1998).334
174. Fifth, the Respondent asserts that the Claimant accepted Argentina’s authority to determine which goods would be covered under the Programme, and thus, the 2000-2001 Resolutions cannot affect the validity of the 10% Fee Cap.335 The Respondent argues that the terms and conditions of the Tender No. 13/97 implied knowledge and acceptance of all conditions involved in the contract.336 Part of those terms and conditions, the Respondent asserts, was MECON’s and subsequently AFIP’s authority as per Decree 477/97 and Resolution 118/2000, respectively, to determine the scope of the goods under the Programme.337 The Respondent stresses that this was never questioned by the Claimant, who noted the changes in the scope of the Programme in its monthly reports without expressing any disagreement.338
331 Statement of Defence, para. 89; Rejoinder, para. 84; Second Comadira Report, paras. 34-35. ↩
332 Statement of Defence, paras. 109-116; Rejoinder, para. 88. ↩
333 Statement of Defence, para. 114; Rejoinder, para. 51; Hearing Tr., Day 7 (14 April 2021), 1111:14-1112:3. ↩
334 Statement of Defence, para. 111; Rejoinder, para. 88; Petracca e Hijos, S. A. et al. v. Gobierno nacional - Ente Autárquico Mundial 78, Federal Court of Appeal in Administrative Matters sitting in full bench, Judgment, 24 April 1986, L.L., 1986-D-10 (RLA-113). ↩
335 Rejoinder, paras. 92-97; Hearing Tr., Day 1 (6 April 2021), 88:2-19. ↩
336 Rejoinder, para. 93; MECON, Call for Public Tender No. 13/97, 7 August 1997, attaching Terms and Conditions (C-9). ↩
337 Rejoinder, paras. 94-95; Decree 477/97 (R-15); MECON, Resolution No. 118/200, 23 February 2000 (R-165). ↩
338 Rejoinder, para. 96; ICS, Monthly Audit Report, September 2000, Section 1.3, preliminary explanations, p. 6 (C-86). ↩
[Page 63]
(a) The Claimant's Position
175. The Claimant submits that the Respondent breached Article 2(2) of the Treaty by failing to pay the Claimant’s U.S. dollar invoices in full and demanding that the Claimant re-issue the invoices in Pesos using the historic 1:1 exchange rate.339 According to the Claimant, the Respondent then only settled the re-issued invoices years later, when the Peso had devalued substantially so that the Claimant only received a small fraction of the value to which it was entitled pursuant to the Contract.340 It is the Claimant’s submission that the balance that remains outstanding on account of the forced re-issuance of invoices in Pesos is USD 3,375,289.01.341 The Claimant maintains that such conduct is contrary to Argentine law and the Contract, and thereby breaches the Treaty as well.342
176. The Claimant maintains that it had the right to accrue its fees and issue invoices for the services performed under the Contract in U.S. dollars.343 The Claimant observes that pursuant to Clause 3 of the Contract, as amended by Resolution 1106/98, the Claimant was entitled to be compensated for its auditing services with fees equivalent to 0.64% (and later 0.76%) of the FOB, FOR, or FOT value declared on each audited Inspection Certificate.344 According to the Claimant, since the value declared on Inspection Certificates was either expressed in U.S. dollars or accompanied by a U.S. Dollar exchange rate, it was entitled to fees invoiced in the same currency.345 The Claimant asserts that, after fixing the value of its fees in U.S. dollars, the Respondent had to provide the respective payment either in U.S. dollars or in the equivalent value in Pesos by applying the relevant U.S. Dollar-Peso exchange rate in effect at the time the invoice was paid.346
177. The Claimant refers to a number of additional documents that, in its view, further evidence its right to accrue its fees in U.S. dollars, in particular: (i) Decree 477/97 and the Tender Terms and
339 Statement of Claim, para. 193; Reply, para. 37. ↩
340 Statement of Claim, paras. 188-189, 192. ↩
341 Reply, para. 47; Second Dellepiane Report, p. 29. ↩
343 Reply, paras. 35, 40-43. ↩
344 Statement of Claim, para. 185; Reply, para. 35; Hearing Tr., Day 1 (6 April 2021), 46:22-48:1. ↩
345 Reply, para. 35; Second Bianchi Report, paras. 12(i)-(ii), 85, 89, 96; Contract, Clause 19 (C-2); Hearing Tr., Day 1 (6 April 2021), 46:22-47:12; Hearing Tr., Day 7 (14 April 2021), 1041:23-1043:5. ↩
[Page 64]
Conditions, both containing provisions on the Auditor’s fees similar to those in the Contract;347 (ii) Resolution 1106/98, which increased the Claimant’s fees without modifying the nature of their calculation;348 (iii) the Claimant’s monthly reports to the Committee, in which the value of the audited Inspection Certificates and its fees was recorded in U.S. Dollar;349 and (iv) a report issued by the Committee in November 1999, which recorded the value of the Inspection Certificates prepared under the Programme in U.S. dollars.350 The Claimant contends that while the Contract, the Tender Terms and Conditions and Decree 477/97 contain provisions that make reference to amounts in Pesos these do not concern the contractual amount, and thus, are irrelevant for determining the currency in which the Auditor was to invoice.351
178. For the Claimant, its right to issue invoices in U.S. dollars under the Contract remained unaffected by the fact that the Claimant had previously issued invoices denominated in Pesos.352 The Claimant argues that, until the enactment of the Emergency Law, “the currency in which invoices were issued and paid was of little significance”, since the U.S. dollar and the Peso were pegged at par.353 However, the Claimant submits that the rapid devaluation of the Peso vis-à-vis the U.S. dollar following the enactment of Emergency Law meant that the issuance of invoices in Pesos “could easily result in the Claimant receiving a different amount (and potentially a very different amount) than the amount to which it was contractually entitled”.354 The Claimant argues that under the Contract “any exchange rate risk was borne by Argentina, not the Claimant”.355 In this respect, the Claimant indicates that, by contrast to the contract Argentina concluded with the Inspection Companies, it did not include a provision in the Contract requiring the Claimant to issue its invoices in Pesos.356
347 Hearing Tr., Day 7 (14 April 2021), 1043:6-1044:16; Decree 477/97, Annex III(c)(9), Annex I(g)(II)(1)(C-6); MECON, Call for Public Tender No. 13/97, 7 August 1997, attaching Terms and Conditions, para. c.XI (C-9). ↩
348 Hearing Tr., Day 7 (14 April 2021), 1054:10-1057:6. ↩
349 Hearing Tr., Day 7 (14 April 2021), 1030:19-1034:2; December 1998 Monthly Audit Report (C-73); March 2001 Monthly Audit Report (C-88). ↩
350 Hearing Tr., Day 7 (14 April 2021), 1034:3-1035:9; Report of the Committee of November 1999 (R-20). ↩
351 Hearing Tr., Day 7 (14 April 2021), 1045:2-1046:21. ↩
352 Statement of Claim, paras. 186-187; Reply, para. 41; Hearing Tr., Day 1 (6 April 2021), 48:18-24. ↩
353 Statement of Claim, paras. 186-187; Reply, para. 41. ↩
[Page 65]
179. The Claimant further maintains that its right to invoice in U.S. dollars was not affected by the Emergency Law or Decree 214/02.357 According to the Claimant, the Emergency Law and Decree 214/02 only applied to “monetary obligations”.358 Given that the Claimant’s fees were established as the percentage of the value stated in the relevant Inspection Certificates or on the basis of market value, these obligations comprised “value obligations” under Argentine law, and therefore, fell outside of the scope of the Emergency Law and Decree 214/02.359 The Claimant emphasizes that this conclusion is consistent with a number of legal opinions issued by Argentina’s Directorate General of Legal Affairs (“DGAJ”).360 Additionally, the Claimant contends that the vast majority of its invoices were issued and became due and payable before the Emergency Law came into force.361
180. The Claimant concludes that the Respondent’s conduct in respect of the alleged forced re-issuance of the Claimant’s invoices in Pesos breached the four obligations provided for in Article 2(2) of the Treaty.362
181. First, the Claimant claims that the Respondent breached the FET standard by failing to maintain a stable and predictable legal and business environment.363 The Claimant further asserts that the Respondent frustrated the Claimant’s legitimate expectations by (i) wrongfully applying the Emergency Law to value obligations beyond its scope of application;364 (ii) retroactively applying the Emergency Law in respect of rights and obligations which had accrued and crystallised before it came into force;365 and (iii) breaching its contractual obligations to pay the Claimant’s fees due under the Contract.366 The Claimant submits that the Respondent also breached the FET standard by “discriminating against the Claimant by pesifying the Claimant’s invoices on a 1:1 basis and not applying a Stabilisation Ratio (CER) as was Argentina’s usual practice in relation to its US
357 Statement of Claim, para. 190; Reply, paras. 44-47; Hearing Tr., Day 1 (6 April 2021), 53:1-54:6. ↩
358 Statement of Claim, para. 190; First Bianchi Report, Section VI and paras. 22, 80; Reply, para. 46; Hearing Tr., Day 1 (6 April 2021), 53:20-21. ↩
359 Statement of Claim, para. 190; First Bianchi Report, Section VI; Reply, para. 46; Second Bianchi Report, paras. 92-94; Hearing Tr., Day 1 (6 April 2021), 53:22-54:6. ↩
360 Statement of Claim, para. 190; DGAJ Opinions Nos. 9800, 10338, 13865 and 13957 (C-70). See also Hearing Tr., Day 1 (6 April 2021), 48:8-17. ↩
361 Statement of Claim, para. 189. ↩
362 Statement of Claim, para. 193; Reply, para. 102. ↩
363 Statement of Claim, para. 193(a)(i). ↩
364 Statement of Claim, para. 193(a)(i). ↩
365 Statement of Claim, para. 193(a)(ii). ↩
366 Statement of Claim, para. 193(a)(iv); Hearing Tr., Day 1 (6 April 2021), 28:10-15. ↩
[Page 66]
Dollar payment obligations”.367 In addition, the Claimant asserts that the Respondent acted “in an arbitrary and inconsistent manner as regards the treatment of the Claimant’s Ordinary Services invoices, as evidenced by the conflicting positions taken by MECON and the DGAJ”.368 According to the Claimant, the Respondent further unjustly enriched itself by benefitting from the auditing services performed by the Claimant while refusing to duly compensate the Claimant for these services.369
182. Second, the Claimant submits that the Respondent’s conduct pertaining to the conversion of dollar-denominated invoices into Pesos constitutes an unreasonable or discriminatory measure which impairs the Claimant’s management, maintenance, use, enjoyment and disposal of its investment.370
183. Third, the Claimant maintains that the Respondent breached its obligation to afford the Claimant’s investment FPS. The Claimant asserts that the Respondent failed to afford the Claimant’s investment a stable and secure commercial and legal environment, including by unlawfully applying the Emergency Law.371
184. Fourthly, the Claimant asserts that the Respondent breached the Umbrella Clause by failing to observe its obligation under the Contract to pay the Claimant’s remaining balance in respect of the forced re-issuance of its invoices in Pesos.372
(b) The Respondent's Position
185. The Respondent submits that the conversion of U.S. dollar denominated invoices into Pesos was consistent with (i) the applicable legal framework;373 (ii) the Claimant’s conduct throughout the Programme;374 and (iii) the place in which the Claimant performed its services and incurred its costs.375
367 Statement of Claim, para. 193(a)(iii). ↩
368 Statement of Claim, para. 193(a)(v). ↩
369 Statement of Claim, para. 193(a)(vi). ↩
370 Statement of Claim, para. 193(b). ↩
371 Statement of Claim, para. 193(c). ↩
372 Statement of Claim, para. 193(d); Hearing Tr., Day 1 (6 April 2021), 20:9-18. ↩
373 Rejoinder, paras. 98, 100-108, 254, 268, 281, 294. ↩
374 Statement of Defence, paras. 133-141; Rejoinder, para. 99. ↩
375 Statement of Defence, paras. 142-147; Rejoinder, paras. 121-125. ↩
[Page 67]
186. First, the Respondent maintains that, pursuant to the legal framework applicable to the auditing services, the fees for the services provided under the Contract were accrued in Pesos and “ICS had to issue peso-denominated invoices”.376 The Respondent asserts that, in accordance with Resolution 1106/98 and Clause 3 of the Contract, the Claimant’s fees “were calculated by reference to the fees invoiced by the inspection companies, which were under an obligation to issue peso-denominated invoices.”377 The Respondent recalls that Resolution 1106/98 established that the Claimant’s fees amounted to “EIGHTY PERCENT (80%) of the fees received by the Inspection companies for each audited Inspection certificate”.378 The Respondent also points out that Clause 3 of the Contract provided that the Claimant’s fees could not exceed 10% of the “amount invoiced by the inspection companies”.379 With respect to the fees of the Inspection Companies, the Respondent avers that, pursuant to the Committee’s Operative Notices Nos. 2 and 3 of 19 March 1998 and 28 June 2001, monthly invoices for import pre-shipment inspection services had to be submitted to AFIP in Pesos.380 The Respondent underlines that the Operative Notice No. 2 was issued six months prior to Resolution 1106/98, such that when the resolution refers to the fees charged by the inspection companies, “there was no doubt that it made reference to fees—those of the inspection company—accrued, invoiced and received in pesos.”381
187. According to the Respondent, all of the foregoing is confirmed by the testimony of Ángela Cupello and Amelia Acosta, former officers of AFIP involved in processing the payments in connection with the Programme, who also note that interest accrued in Pesos.382 The Respondent adds that (i) the Tender Terms and Conditions and Contract both stipulated that payments would be made in Pesos; (ii) the bid bond had to be denominated in Pesos; and (iii) the performance bond was denominated in Pesos.383
376 Statement of Defence, para. 130; Rejoinder, paras. 96, 101, 254; Hearing Tr., Day 7 (14 April 2021), 1095:18-1103:10. ↩
377 Rejoinder, paras. 101, 254; Resolution 1106/98 (C-8); Contract, Clause 3 (C-2); Hearing Tr., Day 1 (6 April 2021), 89:3-22. ↩
378 Rejoinder, para. 100; Resolution 1106/98 (C-8). ↩
379 Rejoinder, para. 100; Contract, Clause 3 (C-2). ↩
380 Statement of Defence, paras. 128-129; Rejoinder, paras. 102-103; Executive Committee Operative Notice No. 2/1998, 19 March 1998 (R-32); Executive Committee’s Order No. 3/2001, 28 June 2001 (R-33). ↩
382 Statement of Defence, para. 136; Rejoinder, para. 104; Acosta First Witness Statement, paras. 23-24; Acosta Second Witness Statement; para. 5; Cupello Second Witness Statement, paras. 4-7. See also Hearing Tr., Day 3 (8 April 2021), 371:9-372-1. ↩
383 Statement of Defence, paras. 125-127, 130; Decree 477/97, Annex III, Sections (c)(V), (e)(VI), (f)(10)(1) (R-15); Contract, Clause 19 (C-2). ↩
[Page 68]
188. Second, the Respondent submits that the Claimant’s claims concerning the alleged forced conversion of dollar denominated invoices into Pesos is at odds with the Claimant’s own issuance of invoices denominated in Pesos while the Contract was in force.384 Consequently, the Respondent notes that it had consistently settled the Claimant’s invoices in Pesos.385 It was only upon the expiration of the Contract, the Respondent contends, that the Claimant decided to change course and submit a large number of dollar-denominated invoices.386
189. Third, the Respondent avers that invoicing in Pesos was in line with the place in which the Claimant performed its services and incurred its costs.387 As indicated by the Tender Terms and Conditions, the on-site inspections carried out by the Claimant had to be performed at the point of destination of the relevant goods (i.e., Argentine territory).388 Moreover, the Respondent affirms that Claimant’s costs were substantially denominated in Pesos, as evidenced by its financial statements.389 In light of these circumstances, the Respondent contends, the issuance by the Claimant of invoices denominated in U.S. dollars “makes no sense from an economic standpoint”.390
190. Finally, according to the Respondent, the enactment of the Emergency Law and Decree 214/02 was irrelevant as the payment obligations under the Contract were already set in Pesos.391 In any event, the Respondent submits that the payments owed by the Respondent’s under the Contract were obligations to pay sums of money—as opposed to value obligations—given that they concerned amounts that were exactly determined at the end of each month in which the services were rendered.392 In this regard, the Respondent contends that the opinions of the Directorate General of Legal Affairs relied upon by the Claimant should be disregarded.393 The Respondent
384 Statement of Defence, paras. 133-134; Rejoinder, paras. 99, 254; Hearing Tr., Day 1 (6 April 2021), 91:1-10. ↩
385 Statement of Defence, paras. 136-141; Cupello First Statement, paras. 14-15; Acosta First Statement, paras. 25-27. ↩
387 Statement of Defence, para. 134; Rejoinder, para. 99; Hearing Tr., Day 1 (6 April 2021), 90:3-20. ↩
388 Statement of Defence, paras. 143-144; Rejoinder, para. 122; Decree 477/97, Annex III, Section (c)(VIII) (R-16). ↩
389 Rejoinder, para. 122; First Dapena Report, paras. 33-35. ↩
391 Statement of Defence, paras. 148-155; Comadira First Report, paras. 104, 110-111, 115; Rejoinder, paras. 109, 254; Comadira Second Report, para. 114. ↩
392 Rejoinder, para. 111; Comadira Second Report, paras. 118-120. ↩
393 Rejoinder, para. 112. See also Statement of Claim, para. 190; Directorate General of Legal Affairs, Opinions: No. 9800 (File No. 0286419/02), 13 February 2003; No. 10338 (File No. 0176433/02), 11 ↩
[Page 69]
argues that these were in fact opinions of Yolanda M. Eggink, a former MECON official, which “were never documented by way of an administrative act recognizing them as binding upon the State and were disregarded by the Legal Department of the Ministry of Economy”.394 The Respondent stresses that Mrs. Eggink was sentenced to three years of imprisonment “for having favoured business owners to the detriment of the Argentine State by unlawfully recognizing peso/dollar-denominated claims in their favour.”395
(a) The Claimant's Position
191. The Claimant submits that the Respondent breached Article 2(2) of the Treaty by unlawfully applying Decree 1060/01 pursuant to which the Respondent demanded a 13% reduction of the Claimant’s fees.396
192. The Claimant points out that Decree 1060/01 of 24 August 2001 expressly required the Respondent “to request a service provider’s consent to the 13% reduction at the time when the services in question were actively being provided”.397 If the service provider’s consent was not given, the Claimant asserts that the Respondent could either: (i) terminate the relevant contract; or (ii) reduce the level of services being provided thereunder so as to reduce the level of fees accordingly.398 According to the Claimant, this process was not followed: the Respondent never sought or obtained the Claimant’s consent to reduce its fees or reduced the level of the Claimant’s services at any time.399 Rather, the Claimant argues that it was only in June 2003 and September and October 2004, “years after the Claimant had provided the relevant services”, that the Respondent sought a retroactive reduction of the Claimant’s fees in purported application of Decree 1060/01.400
394 February 2003; No. 13865 (File No. 0286419/02), and 13957 (File No. 0176433/02), 1 September 2003 (C-70). ↩
Rejoinder, para. 112.
395 Rejoinder, para. 113; Federal Court of Cassation in Criminal Matters, Panel IV, “MELLER, Sergio E. y otros s/recurso de casación” (Case No. 9618/2001/TO1/CFC6), Judgment, 24 October 2018 (R-291). ↩
396 Statement of Claim, para. 197; Reply, para. 8. ↩
397 Reply, para. 54; Second Bianchi Report, paras. 103-107. ↩
398 Reply, para. 54; Second Bianchi Report, para. 107. ↩
399 Reply, para. 54; Hearing Tr., Day 1 (6 April 2021), 61:4-6. ↩
400 Reply, para. 54; Hearing Tr., Day 1 (6 April 2021), 59:20-60:1; Hearing Tr., Day 7 (14 April 2021), 1036:5-18. ↩
[Page 70]
193. The Claimant underscores that while it eventually complied with the Respondent’s demand and reissued reduced invoices, it only did so given that otherwise “no payment whatsoever would be forthcoming by Argentina in respect of the relevant invoices.”401 In any event, the Claimant argues that it reserved all its rights in this respect when it filed its expanded administrative claim.402
194. In addition, the Claimant argues that the fact that it continued providing the services after the expiry of the Contract in March 2001 did not entail a tacit acceptance of the 13% reduction established in Decree 1060/01.403 Relying on the opinion of Prof. Bianchi, the Claimant submits that the “behavior of both parties suggests that they continued their existing contractual relationship by mutual agreement, with the same rights and obligations that existed before that date under the Contract” until the termination of the Programme in February 2002.404 Throughout this additional period the Claimant says that the Respondent continued to request, and the Claimant continued to provide, services under the terms agreed in the Contract.405 The Claimant contends that it had previously done the same thing following the expiry of the original period of the Contract in March 2000 and until its retroactive one-year extension until March 2001.406 According to the Claimant, the Respondent has acknowledged that the only reason why the Contract was not formally extended again was because there was not enough time to complete a new bidding process before the termination of the Programme.407
195. The Claimant disputes the Respondent’s assertion that the payments for the services provided after the Contract expired (i.e., from April to December 2001) were made on the basis of the principle of unjust enrichment.408 If that would have been the case, the Claimant contends, the Claimant “would only have been entitled to receive expenses and no profits.”409 According to the
404 Reply, para. 53; Second Bianchi Report, para. 122. ↩
405 Reply, para. 52; Second Santamaria Statement, para. 14; Hearing Tr., Day 1 (6 April 2021), 60:12-16. ↩
406 Reply, para. 52; Second Santamaria Statement, para. 14; Decision of the Committee No. 002, 2 March 2001, Article 1 (C-20). ↩
407 Reply, para. 52; Resolution No. 325/2006 (C-60); Hearing Tr., Day 1 (6 April 2021), 60:17-61:6. ↩
408 Hearing Tr., Day 7 (14 April 2021), 1072:8-1075:5. ↩
409 Hearing Tr., Day 7 (14 April 2021), 1072:22-1073:12. ↩
[Page 71]
Claimant, this was not the case as the Claimant continued “to be paid in accordance with its entitlement under Decree 477/97 and the Contract.”410
196. In light of the foregoing, the Claimant concludes that the 13% reduction of its invoices breached the four obligations provided for in Article 2(2) of the Treaty.411
197. First, the Claimant claims that the Respondent breached the FET standard by frustrating the Claimant’s legitimate expectations that the Respondent would (i) comply with its national laws, and not wrongfully apply Decree 1060/01;412 (ii) comply with its obligations vis-à-vis the Claimant under the Contract;413 and (iii) not unjustly enrich itself by benefitting from the auditing services performed by the Claimant while refusing to duly compensate the Claimant for these services.414
198. Second, the Claimant submits that the Respondent’s conduct pertaining to the 13% reduction of the Claimant’s invoices constitutes an unreasonable measure which impairs the Claimant’s management, maintenance, use, enjoyment and disposal of its investment.415
199. Third, the Claimant maintains that the Respondent breached its obligation to afford the Claimant’s investment full protection and security, by failing to protect the Claimant’s legal rights.416
200. Fourth, the Claimant asserts that the Respondent breached the Umbrella Clause by failing to observe its obligation to pay the Claimant’s fees due under the Contract.417
(b) The Respondent's Position
201. The Respondent submits that the 13% reduction provided for in Decree 1060/01 was properly applied to the Claimant, and thus, did not breach Article 2(2) of the Treaty.418
410 Hearing Tr., Day 7 (14 April 2021), 1073:13-19. ↩
411 Statement of Claim, para. 197. ↩
412 Statement of Claim, para. 197(a)(i); Hearing Tr., Day 1 (6 April 2021), 29:1-9. ↩
413 Statement of Claim, para. 197(a)(ii). ↩
414 Statement of Claim, para. 197(a)(iii). ↩
415 Statement of Claim, para. 197(b). ↩
416 Statement of Claim, para. 197(c). ↩
417 Statement of Claim, para. 197(d); Hearing Tr., Day 1 (6 April 2021), 21:1-3. ↩
418 Statement of Defence, paras. 162-171; Rejoinder, paras. 126-145, 255, 268, 281, 294. ↩
[Page 72]
202. The Respondent asserts that Decree 1060/01 (in force as from 1 July 2001 and adopted in accordance with Article 34 of Law No. 24,156, as amended by Law No. 25,453) established that the Government had the authority to reduce public expenses in view of available budgetary resources.419 Relying on the expert evidence of Prof. Julio Pablo Comadira, its expert on Argentine law, the Respondent notes that although Decree 1060/01 required to request a service provider’s consent when there was an ongoing contractual relation, it did not do so in the absence of a contract.420 According to the Respondent, Law No. 24,156 formed part of the legal framework governing government procurement which was applicable to the participants of the Tender 13/97, as duly noted in the Tender Terms and Conditions.421
203. The Respondent also submits that the Claimant consented to the application of Decree 1060/01 in respect of the services provided from July to December 2001.422 Relying on the opinions of Profs. Comadira and Dapena, the Respondent argues that the Claimant’s decision to continue providing its auditing services after the Contract was no longer in force “meant consenting to the applicable regulations, especially Presidential Decree No. 1060/2001.”423 Otherwise, the Respondent contends, the Claimant would have had to cease provision of its services.424 Moreover, the Respondent argues that, when the Claimant submitted the respective credit notes applying the 13% reduction, the Claimant failed to make any observations or reservations.425 In this connection, the Respondent notes that the Argentine Supreme Court has held that “the interested parties’ voluntary submission to a given legal framework, without making any express reservation, renders their subsequent challenge inadmissible.”426 The Respondent further avers that the applicability of Decree 1060/01 was confirmed by Opinion No. 20484 of the General
419 Statement of Defence, paras. 162-163; Rejoinder, paras. 127, 255; Decree 1060/01, 22 August 2001, Articles 1 and 4 (C-50); Law No. 25,453, 30 July 2001, Article 10 (replacing Article 34 of Law No. 24,156) (R-40). ↩
420 Hearing Tr., Day 7 (14 April 2021), 1115:22-1116:9; Hearing Tr., Day 4 (9 April 2021), 631:14-25. ↩
421 Rejoinder, para. 128; Decree 477/97, 22 May 1997, Annex III, Section (d)(I) (R-15). ↩
422 Statement of Defence, paras. 166-168; First Comadira Report, para. 143; Rejoinder, paras. 133, 255, 268. ↩
423 Statement of Defence, para. 167; Comadira First Report, para. 143; First Dapena Report, para. 57. ↩
424 Statement of Defence, para. 166; Rejoinder, para. 133. ↩
425 Rejoinder, para. 130; Letter from the Committee No. 279/04 to the Claimant, 6 October 2004, and Letter from ICS to the Committee No. ICS/C/18826/04, 7 December 2004 (R-145). ↩
426 Rejoinder, para. 132; Argentine Supreme Court of Justice, “Cabrera, Gerónimo Rafael y otro c/ P.E.N. - ley 25.561 - dtos. 1570/01 y 214/02 s/ amparo sobre ley 25.561”, Judgment, 13 July 2004, Judgments: 327:2905, recital no. 5 (RLA-287). ↩
[Page 73]
Directorate for Legal Affairs of the Ministry of Economy and the testimony of Ms. Acosta, a former AFIP official responsible for approving the payments related to the Programme.427
204. The Respondent argues that the rules governing government procurement in Argentina are of public order, such that an administrative contract that has expired cannot be implicitly extended, especially in a manner contrary to the terms of Decree 1060/01.428 Thus, according to the Respondent, the de facto situation that emerged after the expiry of the Contract cannot be considered an ongoing contractual relationship subject to the procedures and consent requirements of Decree 1060/01.429 The Respondent alleges that it was precisely because of this lack of a contractual basis that AFIP had to settle the payments for the services provided from July to December 2001 as “equitable payments” on the basis of Resolution 325.430
205. Moreover, considering that there was no contract in force from July to December 2001, the Respondent argues that the Claimant could not have been put in a better situation than those providers that did have a contract with the Argentine government.431
206. The Claimant submits that the Respondent breached the obligations provided for in Article 2(2) of the Treaty by failing to compensate the Claimant for the work it performed in connection with the “special services” in breach of the Contract and Argentine law.432
207. The Claimant alleges that, between June 1998 and July 2001, the Respondent requested and the Claimant prepared and issued the 21 special reports of issues of specific interest to Argentina (see paragraphs 76-77 above).433 The Claimant contends that these special services were distinct from the ordinary services relating to the review of inspection certificates.434 In this respect, the
427 Statement of Defence, para. 165; Rejoinder, para. 129; Second Acosta Statement, paras. 9-10. ↩
428 Rejoinder, paras. 136-137; Second Comadira Report, paras. 134-140. ↩
429 Statement of Defence, para. 170; First Comadira Report, paras. 151-153; Rejoinder, paras. 135-136; Second Comadira Report, paras. 132-133. ↩
430 Rejoinder, para. 137; Second Comadira Report, paras. 143-145. See also Hearing Tr., Day 2 (7 April 2021), 320:4-19. ↩
431 Hearing Tr., Day 1 (6 April 2021), 93:4-10. ↩
432 Statement of Claim, para. 202; Reply, para. 8. ↩
433 Statement of Claim, para. 73; Reply, para. 57; Hearing Tr., Day 1 (6 April 2021), 61:7-15. ↩
[Page 74]
Claimant asserts that Clauses 6, 8 and 9 of the Contract stipulated that the Claimant "was obliged to comply with the Respondent's instructions which could and did include instructions to carry out Special Services.”435
208. The Claimant asserts that the special services required performing different types of tasks than those undertaken for the ordinary services.436 In support of this contention, the Claimant refers to the evidence provided by Mr. Juan Santamaría,437 operations coordinator of the Claimant's subsidiary in Argentina since 1998, and Dr. Julio Pablo Comadira, the Respondent's expert on Argentine law.438 The Claimant explains that ordinary services entailed reviewing a specific import by conducting a physical inspection of the shipment upon arrival in Argentina and subsequently checking that the Inspection Certificate was consistent with that inspection.439 By contrast, the special services pertained to more extensive tasks such as conducting market analysis, assessing the implementation of other trade programmes and examining the prices of goods imported to the country after they had been cleared from customs.440
209. According to the Claimant, these special services were to be paid on the basis of the second sentence of Article 2 of Resolution 1106/98, which established that, for any fees that could not "be correlated to certificates of inspection, the audit firm shall draw up a report detailing the costs and fees following normal market practice”.441 In view of the lack of a payment mechanism for special services prior to the issuance of Resolution 1106/98, the Claimant asserts that Article 2 "intended to cover invoices submitted after its entry into force, even if certain works were carried out beforehand."442
435 Reply, para. 63; Contract, Clauses 6, 8, 9, 13 (C-2); Second Bianchi Report, paras. 18(v), 172; Hearing Tr., Day 1 (6 April 2021), 50:15-23; Hearing Tr., Day 7 (14 April 2021), 1075:11-19. ↩
436 Hearing Tr., Day 2 (7 April 2021), 253:1-263:10; Hearing Tr., Day 7 (14 April 2021), 1038:16-24, 1039:14-1040:1. ↩
437 Hearing Tr., Day 2 (7 April 2021), 253:1-263:10. ↩
438 Hearing Tr., Day 4 (9 April 2021), 569:13-16. ↩
439 Hearing Tr., Day 2 (7 April 2021), 253:1-254:13. ↩
440 Hearing Tr., Day 2 (7 April 2021), 254:17-263:10; Banana Imports into Argentina Special Services Report (C-122); Temporary Imports Special Services Report (C-131); Kiwi Imports Special Services Report and Related Work Product (C-134); Asia Imports Special Services Report and Related Work Product (C-124); Annex to Claimant's Closing Statement, 14 April 2021. ↩
441 Reply, para. 58; Resolution 1106/98, Article 2 (C-8) (translation by the Claimant); Hearing Tr., Day 1 (6 April 2021), 51:1-13; Hearing Tr., Day 7 (14 April 2021), 1037:6-9. ↩
442 Hearing Tr., Day 7 (14 April 2021), 1077:15-1078:6. ↩
[Page 75]
210. The Claimant maintains that, despite the fact that it duly performed the special services and invoiced the Respondent in accordance with Resolution 1106/98, the Respondent has refused to compensate the Claimant for such services.443 The Claimant alleges that the special services were provided at the request of the Committee, some of these requests were made in writing and specifically based on Clause 8 of the Contract.444 The Claimant notes that in 2006, many years after the special services had been performed, the Respondent requested extensive supporting materials in respect of each invoice for these services.445 According to the Claimant, such documentation was provided to the Committee and has also been submitted in this arbitration.446
211. Moreover, the Claimant alleges that the Respondent recognized on a number of occasions that the special services were duly performed and that the Claimant was entitled to receive fees accordingly.447 The Claimant points out that upon the termination of the Programme the Respondent expressly acknowledged that, in addition to the Claimant's audit tasks, the Claimant had also "prepared Special Reports on request from the Executive Committee to arbitrate corrective actions.”448 The Claimant also underscores that the Respondent previously approved one of the Claimant's special services invoices.449 In addition, the Claimant cites a legal opinion provided by DGAJ to MECON in June 2001 that recognized that the Claimant could be asked to perform “tasks that [were] especially required by the Executive Committee” which may not be related to the review of Inspection Certificates, and that this was precisely why the Resolution 1106/98 established a specific basis to calculate the fees for such services.450
212. In the light of the above, the Claimant concludes that the Respondent's failure to pay for the special services breached the four obligations arising under Article 2(2) of the Treaty.451
443 Statement of Claim, paras. 200-201; Reply, para. 59. ↩
444 Hearing Tr., Day 7 (14 April 2021), 1037:1-5; Asia Imports Special Services Report and Related Work Product, p. 22 (C-124); Amplified Administrative Claim, 6 December 2004, p. 35 (C-54). ↩
445 Statement of Claim, para. 200; Letters from ICS to the Committee, 12 June 2006 to 1 August 2006 (C-59). ↩
446 Reply, para. 67; Supporting Files for the Special Services Reports (C-101 – C-121); Hearing Tr., Day 1 (6 April 2021), 62:1-63:19, 64:16-65:3. ↩
448 Reply, para. 63; Committee Certification No. IPE 164/04, 22 July 2004 (C-98) (translation by the Claimant). ↩
449 Statement of Claim, para. 199; Letter from the Committee to ICS, 22 August 2002 (C-42); Hearing Tr., Day 1 (6 April 2021), 61:19-62:1. ↩
450 Reply, para. 65; DGAJ Opinion 1747, June 2001 (C-99) (translation by the Claimant); Hearing Tr., Day 1 (6 April 2021), 51:14-18; Hearing Tr., Day 7 (14 April 2021), 1075:20-1076:11. ↩
451 Statement of Claim, para. 202. ↩
[Page 76]
213. First, the Claimant claims that the Respondent breached the FET standard by:
a) frustrating the Claimant's legitimate expectations that the Respondent would comply with its obligation to compensate the Claimant for services provided under the Contract;452
b) acting inconsistently, unreasonably and arbitrarily, “with certain branches of the Argentine administration expressly requesting and authorising the Special Services, and others subsequently objecting to the Special Services and refusing to pay for them";453
c) acting in a non-transparent, unreasonable, arbitrary and inconsistent manner, “motivated by improper purposes, in relation to the Claimant's attempts to seek payment for the Special Services";454 and
d) unjustly enriching itself by benefitting from the special services performed by the Claimant while refusing to compensate the Claimant for these services.455
214. Second, the Claimant submits that the Respondent's failure to pay for the special services constitutes an unreasonable measure which impairs the Claimant's management, maintenance, use, enjoyment and disposal of its investment.456
215. Third, the Claimant maintains that the Respondent, through the Committee, MECON, and AFIP, breached its obligation to afford the Claimant's investment FPS by failing to protect the Claimant's legal rights under the Contract.457
216. Fourth, the Claimant asserts that the Respondent breached the Umbrella Clause by failing to observe its obligation under the Contract to compensate the Claimant for the special services.458
217. The Respondent submits that the alleged special services “were nothing but tasks that ICS was required to carry out as part of the provision of the [ordinary] auditing services set forth in the
452 Statement of Claim, para. 202(a)(i); Hearing Tr., Day 1 (6 April 2021), 29:10-18. ↩
453 Statement of Claim, para. 202(a)(ii). ↩
454 Statement of Claim, para. 202(a)(iii). ↩
455 Statement of Claim, para. 202(a)(iv). ↩
456 Statement of Claim, para. 202(b). ↩
457 Statement of Claim, para. 202(c). ↩
458 Statement of Claim, para. 202(d); Hearing Tr., Day 1 (6 April 2021), 21:4-6. ↩
[Page 77]
Contract".459 In addition, the Respondent maintains that (i) paying for “special services” would be contrary to Argentine government procurement regulations;460 (ii) the fees payable for the alleged special services would have been accrued in Pesos;461 and (iii) the fees claimed have not been justified.462
218. First, the Respondent asserts that the purported special services were “covered by the payment of the auditing services' fees”.463 The Respondent argues that under Clauses 8, 9 and 13 of the Contract the Claimant agreed to perform various jobs, including submitting reports pertaining to the oversight of certain operations or to deficiencies noted in the course of providing its services.464 The Respondent argues that such services are covered by the fees set forth in Clause 3 and that Clause 21 expressly stated that the Claimant would “not be entitled to receive any benefit, payment, subsidy, compensation or right which is not expressly stipulated or provided for in this contract.”465 Relying on the opinion of its expert on Argentine law, the Respondent asserts that the cited clause is a provision with “restrictive criteria”.466
219. The Respondent further alleges that each of the purported “special services” consisted in tasks that formed part of the regular auditing services under the Contract, notably the analysis of data from Inspection Certificates; physical inspections; and the verification of prices, customs valuation or the tariff classification of determined sets of goods.467 The Respondent argues that the Claimant's own descriptions belie the “special” nature of the services:468
a) "Analysis of Deficiencies Detected in the Issue of the CIPI”: the Claimant states that it "selected some Import Pre-Shipment Inspection Certificates and found that they failed
459 Rejoinder, paras. 147, 256, 268, 281, 295. ↩
460 Statement of Defence, paras. 248-262; Rejoinder, paras. 164-180. ↩
461 Rejoinder, paras. 181-186. ↩
462 Rejoinder, paras. 187-192. ↩
463 Statement of Defence, paras. 182-247; Rejoinder, paras. 150-163, 256, 268; Hearing Tr., Day 1 (6 April 2021), 93:22-96:10. ↩
464 Statement of Defence, para. 178; Rejoinder, para. 153; Contract, Clauses 8-9, 13 (C-2); Hearing Tr., Day 7 (14 April 2021), 1119:21-1120:20. ↩
465 Statement of Defence, paras. 179-180; Rejoinder, paras. 153, 155; Contract, Clauses 3, 21 (C-2); Hearing Tr., Day 7 (14 April 2021), 1120:20-1121:14. ↩
466 Hearing Tr., Day 7 (14 April 2021), 1120:20-1121:10; Hearing Tr., Day 4 (9 April 2021), 570:10-18. ↩
467 Statement of Defence, para. 185; Rejoinder, para. 157; Hearing Tr., Day 1 (6 April 2021), 97:5-20. ↩
[Page 78]
to comply with MEyOySP Resolution No. 1278 of 7 November 1997, and that others had inspection service deficiencies”;469
b) "Special Audit Report – Asia Imports”: the Claimant audited 32 Inspection Certificates in order to verify whether there were serious under-invoicing cases in imports from Asia;470
c) Special Report on “Committee Certificates": which comprised four “letters, of one page each," the Claimant provided summaries and statistics of its auditing services;471
d) “TDK Line Study”: the Claimant covered "a sample of Inspection Certificates of TDK and SAMSUNG products”;472
e) “Chicken Imports Report SADIA S.A.": the Claimant "audited four inspection certificates issued by the inspection company Bureau Veritas” corresponding to imports processed by SADIA ARG S.A.;473
469 Statement of Defence, paras. 189-191; Report on Deficiencies Detected in the Issue of Certificates, 8 June 1999, p. 01311, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-85). ↩
470 Statement of Defence, paras. 192-194; Report on Asia Imports, 5 August 1998, p. 01540, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-86). ↩
471 Statement of Defence, paras. 195-200; ICS's letter C/98/13801/ARG, without the signature of the sender from ICS, sent to Rezk, in his capacity as head of the Committee's Programme, 19 June 1998, p. 620, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-87); ICS's letter C/98/13806/ARG, signed by Eirc Rojo from ICS, sent to Rezk, in his capacity as head of the Committee's Programme, 22 June 1998, p. 621, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-88); ICS's letter C/98/14581/ARG, without the name of the sender from ICS, sent to Rezk, in his capacity as head of the Committee's Programme, 8 October 1998, p. 629, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-89); ICS letter C/98/14699/ARG, sent by General Manager Carlos Cheble to Rezk, in his capacity as head of the Committee's Programme, 30 October 1998, p. 630, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional - Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-90). ↩
472 Statement of Defence, paras. 204-206; SWIPCO's letter signed and sent by General Manager Cheble to Rezk, in his capacity as head of the Committee's Programme, dated 19 May 1999, p. 01228, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-91). ↩
473 Statement of Defence, paras. 207-209; SADIA Chicken Report, 11 February 1999, p. 01263, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-92). ↩
[Page 79]
f) “Glass and Glassware Study”: the Claimant verified the tariff classification related to the importer Soifer Hnos. S.A.I.C. “us[ing] previously audited inspection certificates";474
g) “Marble and Granite San Luis S.A.”: which comprised a two-page letter, the Claimant provided "additional information on No. 1-98-013925-0 issued by Supervillance S.A. in regard to importer Mármoles y Granitos de San Luis S.A., with the sole purpose of analyzing the tariff classification”;475
h) "Brazil Imports, October - December 1998 and January 1999”: the Claimant "analyzed inspection certificates during a given period and different graphs were drawn up" assessing the impact that the devaluation of the Brazilian currency against the U.S. dollar had on imports to Argentina;476
i) “Imports Chapter 30, October - December 1998 and January 1999”: the Claimant "analyz[ed] inspection certificates" related to tariff positions in Chapter 30 of the Mercosur Common Nomenclature (Pharmaceutical Products);477
j) “Colonia Uruguay Free Zone Report”: the Claimant's analysis focused "on inspection certificates issued by Intertec, Inspectorate, Socotec and Surveyseed," all of them Inspection Companies in the free trade zone of Colonia (Uruguay);478
k) "Report regarding Compliance with CEPIPI Article 2, provision No. 4": the Claimant corroborated the Inspection Companies' compliance with regulations on the
474 Statement of Defence, paras. 210-212; SWIPCO's letter C/98/14188/ARG, 18 August 1998, p. 633, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-93). ↩
475 Statement of Defence, paras. 213-214; ICS's letter C/98/14688/ARG, signed and sent by Legal Representative Daniel Blondeau and Engineer Carlos Cheble, in his capacity as General Manager, to Rezk, head of the Committee's Programme, 29 October 1998, pp. 01528, 01529, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional - Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-94). ↩
476 Statement of Defence, paras. 221-223; Brazil Imports Report, 17 February 1999, p. 01515, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-95). ↩
477 Statement of Defence, paras. 224-225; Chapter 30 Imports in File No. EXP-S01:0438572/2005, commenced on 26 December 2005, pp. 6-7 (R-139). ↩
478 Statement of Defence, paras. 228-229; SWIPCO's letter C/99/15496/ARG, 20 April 1999, submitted by ICS as Appendix XXVII to its statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional - Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-97). ↩
[Page 80]
identification of goods by reviewing a sample of Inspection Certificates. The Respondent emphasizes that the Claimant acknowledged in this report that it was "responsible for expressing an opinion on the said certificates on the basis of [its] audit job";479
l) "Analysis of Imports among Related Companies”: the Claimant “analyse[d] inspection certificates which revealed a link between importer and exporter". In this case, the Respondent stresses that the Claimant also recognized that it was “responsible for expressing an opinion on the said certificates on the basis of [its] audit job";480
m) “Iquique 2 Report”: the Claimant stated that it "exhaustively audit the certificates issued by the inspection companies for operations carried out during 2000/2001 from the Iquique (Chile) free zone in order to determine if there were tax losses and the amount thereof";481 and
n) “Satellite Antenna Report”: the Claimant, in response to a request made by the Committee pursuant to Clause 8 of the Contract, “analyzed the value of five certificates issued by inspection company Surveyseed".482
220. Further, the Respondent asserts that, in five of the alleged special reports, the Claimant refers to the verification of prices of goods that were or could potentially be covered by the Programme,
479 Statement of Defence, paras. 230-232; Report regarding Compliance with Article 2, provision 4 of the Executive Committee, p. 01370, submitted by ICS as Appendix XXVII to its statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-101). ↩
480 Statement of Defence, paras. 233-235; Analysis of Imports among Related Companies, p. 01727, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-102). ↩
481 Statement of Defence, para. 238; Executive Committee's letter No. 0485, 2 March 2001, p. 01860, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-104). ↩
482 Statement of Defence, paras. 241-243; Executive Committee's letter No. 0060/01, signed by Bizzotto in his capacity as head of the Committee's Programme, 10 January 2001 (R-106); ICS's letter, signed and sent by Legal Representative Juan Alemann to Bizzotto, in his capacity as head of the Committee's Programme, dated 24 January 2001, pp. 02143-02146, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-107). ↩
[Page 81]
namely, the: "Banana Imports into Argentina”,483 “Kodak Study”,484 "Report on Iquique (Chile), Colonia and Montevideo, Uruguay Free Zone”,485 "Kiwi Imports Study",486 and "Rito Kosher Milk Report".487 The Respondent adds that in some of the invoices for the purported special services the Claimant itself stated that the amount charged corresponded to auditing fees.488
221. In the following table, the Respondent specifies which type of tasks were performed in respect of each "special service":
| Audit | Data | Physical | Prices | Customs Value | Tariff Classification |
|---|---|---|---|---|---|
| 1. Banana Imports into Argentina | X | ||||
| 2. Analysis of Deficiencies Detected in the Issue of Certificates | X | X | |||
| 3. Asia Imports | X | X | X | X | X |
| 4. Committee Certificates | X | X | |||
| 5. Kodak Study | X | X | |||
| 6. TDK Line Study | X | X | |||
| 7. SADIA Chicken Imports Report | X | X | X | ||
| 8. Glass and Glassware Study | X | X | |||
| 9. Mármoles y Granitos de San Luis S.A. | X | X | |||
| 10. Temporary Imports Study | X | ||||
| 11. Report on Iquique, Colonia and Montevideo Free Zone | X | ||||
| 12. Brazil Imports | X | ||||
| 13. Chapter 30 Imports | X | ||||
| 14. Kiwi Imports Study | X | ||||
| 15. Colonia Free Zone Report | X | X | X | X | X |
| 16. Report regarding Compliance with CEPIPI, Article 2, provision 4 | X | X | |||
| 17. Analysis of Imports among Related Companies | X | ||||
| 18. Item 8703 Imports Investigation | X | X | X | ||
| 19. Iquique 2 Report | X | X | X | X | X |
| 20. Satellite Antenna Report | X | X | X | ||
| 21. Rito Kosher Milk Report | X |
483 Statement of Defence, paras. 187-188; Report on Banana Imports into the Argentine Republic, dated 1 September 1999, pp. 01215-01221, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-84). ↩
484 Statement of Defence, paras. 201-203; Kodak Report in File EXP-S01:0001938/2006, commenced on 2 January 2006, pp. 04-07 (R-119). ↩
485 Statement of Defence, paras. 218-220; Free Zone Report in File EXP-S01:0001462/2006, commenced on 2 January 2006, p. 2 (R-137). ↩
486 Statement of Defence, paras. 226-227; Kiwi Imports Report, p. 02014, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings "Inspection and Control Services c/ Estado Nacional - Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-96). ↩
487 Statement of Defence, paras. 244-246; Executive Committee's letter No. 1123/01, 27 June 2001, p. 02306, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-108). ↩
488 Rejoinder, paras. 175-176; ICS, Invoices and collection documents (CLEX-16). ↩
[Page 82]
222. Second, the Respondent contends that the second sentence of Article 2 of Resolution 1106/98, invoked by the Claimant, cannot serve as a basis to compensate the alleged “special services.489 The Respondent argues that the first eight reports claimed were rendered between June 1998 and August 1998, before Resolution 1106/98 was approved on 9 September 1998.490 The Respondent further contends that Resolution 1106/98 did not expand the scope of services covered by the Contract, and that MECON, the entity that issued Resolution 1106/98, lacked the powers to do so.491 Moreover, the Respondent argues that this provision only applies to tasks that cannot be correlated to Inspection Certificates, such that it could not have covered tasks that formed part of the Claimant's auditing services under the Contract.492 In any event, the Respondent contends that a review of the documentation provided by the Claimant and Mr. Santamaría's testimony evidences that the alleged special services did not comply with the requirements under Resolution 1106/98.493
223. Third, the Respondent maintains that any payment for the alleged special services would be contrary to Argentine government procurement regulations.494 The Respondent asserts that, pursuant to the Tender Terms and Conditions, the Claimant was subject to the rules governing public procurement in Argentina.495 According to the Respondent, such rules require that payments for services provided to the administration be supported by service orders and an acknowledgement that the service was provided.496 The Respondent indicates that the Committee thus requested the Claimant to provide in respect of each report (i) the technical and economic justification for its request; (ii) the service orders signed by the parties; and (iii) the reasonableness of the agreed-upon conditions regarding the time of delivery, payment method, receipt and conformity by the Committee.497 According to the Respondent, given that the Claimant “never
489 Statement of Defence, paras. 175-179; Rejoinder, paras. 150-151, 157. ↩
490 Rejoinder, paras. 150-151; Resolution 1106/98 (C-8); Hearing Tr., Day 1 (6 April 2021), 96:15-97:5. ↩
491 Rejoinder, para. 156; Second Comadira Report, para. 177; Hearing Tr., Day 7 (14 April 2021), 1121:15-1122:11; Hearing Tr., Day 4 (9 April 2021), 561:11-20. ↩
492 Rejoinder, para. 157; Hearing Tr., Day 4 (9 April 2021), 562:17-21. ↩
493 Hearing Tr., Day 7 (14 April 2021), 1127:12-1133:14; Hearing Tr., Day 2 (7 April 2021), 236:6-15. See also Statement of Defence, paras. 176-179. ↩
494 Statement of Defence, paras. 248-262; Rejoinder, paras. 164-180. ↩
496 Rejoinder, paras. 170-172; Second Dapena Report, paras. 31-32; Presidential Decree No. 5720/1972, 28 August 1971, Government Procurement Rules, Chapter VI, Article 61(53)(a) (R-43). ↩
497 Statement of Defence, paras. 250-251; Rejoinder, paras. 167, 256; Letter from the Committee No. 958/2001 to ICS, 4 June 2001, enclosing Letter from SIGEN to the Committee, 30 May 2001 (C-44). ↩
[Page 83]
responded satisfactorily" to this request for supporting documentation, the invoices were never approved by the Committee.498
224. Fourth, the Respondent submits that the Claimant failed to provide sufficient support for the expenses it allegedly incurred in connection with the special services.499 The Respondent contends that the direct and indirect costs reported by the Claimant “were related to Claimant's ordinary course of business”.500 Therefore, the Respondent concludes such costs have already been paid for by Argentina under the Contract.501
225. Fifth, and in the alternative, the Respondent objects to the Claimant's attempt to seek payment for the special services in U.S. dollars.502 The Respondent notes that half of the invoices for the special services were issued in Pesos and that almost all of the costs allegedly incurred by the Claimant were incurred in Pesos.503
226. The Claimant asserts violations of Argentina's obligations set forth in Article 2(2) of the Treaty, which reads:
Investments of investors of each Contracting Party shall at all times be accorded fair and equitable treatment and shall enjoy protection and constant security in the territory of the other Contracting Party. Neither Contracting Party shall in any way impair by unreasonable or discriminatory measures the management, maintenance, use, enjoyment or disposal of investments in its territory of investors of the other Contracting Party. Each Contracting Party shall observe any obligation it may have entered into with regard to investments of investors of the other Contracting Party.
227. The Claimant identifies four distinct obligations contained in this provision, namely FET (fair and equitable treatment), FPS (full protection and security), the prohibition of unreasonable and discriminatory conduct, and the Umbrella Clause. The Claimant has focused on FET and the Umbrella Clause, but does not appear to have restricted its case, which is thus that each one of
498 Rejoinder, paras. 169-171, 256; Hearing Tr., Day 1 (6 April 2021), 97:21-99:16; Hearing Tr., Day 7 (14 April 2021), 1124:10-1126:24. ↩
499 Statement of Defence, para. 264; Rejoinder, paras. 187-192. ↩
500 Rejoinder, paras. 190-191; Second Dapena Report, Section II.A.4.d, Annex 2. ↩
501 Rejoinder, paras. 190-191. ↩
502 Rejoinder, paras. 181-186. ↩
503 Rejoinder, para. 185; Second Dapena Report, paras. 84-85. ↩
[Page 84]
the four standards in Article 2(2) was breached by each one of the following four acts of the Respondent:
- non-payment of the Claimant's fees exceeding 10% of the inspection companies' fees according to the fee cap in Article 3 of the Contract;
- "pesification” of the Claimant's remuneration, by paying in pesos after Argentina abandoned parity between the Argentine peso and U.S. dollar;
- imposing, in 2003, a reduction of the Claimant's remuneration by 13% as from July to December 2001; and
- non-payment of the Claimant's remuneration for the "Special Services".
228. The Respondent's primary position is that its actions were consistent with the Contract, duly interpreted under the applicable Argentine law:
- the 10% Fee Cap was applied as agreed in Article 3 of the Contract;
- the Contract already provided for fees in Pesos;
- the 13% reduction in the Claimant's remuneration was accepted by performance when the Claimant continued to provide services after the expiration of the Contract; and
- the Special Services are covered by the remuneration paid to Claimant for its auditing services.
229. In addition, to the extent that the Respondent's acts violate the Contract, these acts are said to be consistent with the Treaty. In the Respondent's view, the requirements of Article 2(2) of the Treaty apply only to sovereign measures, and the measures it enacted complied with these requirements.
230. The latter argument is brought in particular against the Claimant's Umbrella Clause claims, and in support of the assertion that acts breaching the Contract cannot, by themselves, also constitute breaches of the Umbrella Clause. The proper interpretation of the Umbrella Clause is therefore the starting point for the Tribunal's analysis.
[Page 85]
231. The Tribunal recalls its Award on Jurisdiction, in which it rejected the Respondent's preliminary objection relating to the scope of the Umbrella Clause to the effect that the provision only covered certain kinds of agreements entered into by the State:
One must begin with the plain meaning – the “ordinary meaning" – of the Umbrella Clause: "[e]ach Contracting Party shall observe any obligation it may have entered into with regard to investments of investors of the other Contracting Party." Considering the use of the mandatory term “shall", the sentence is imperative. The expression "any obligation" is capacious, i.e. it is not limited to certain types of obligations but rather encompasses all obligations a host State may have entered into with regard to investments of investors of the other Contracting Party. In particular, this expression is capable of applying to obligations arising under national law, e.g. those arising from a contract. Indeed, as noted in SGS v. Philippines, "it would normally be under its own law that a host State would assume obligations 'with regard to specific investments in its territory by investors of the other Contracting Party”. Interpreting the wording of the Umbrella Clause, it is clear that each Contracting Party shall observe any obligation it has assumed, or will in the future assume, with regard to investments covered by the Treaty.
The object and purpose of the Treaty also support such an interpretation. The aim of the Treaty is to promote and reciprocally protect investments. According to its preamble, the Contracting Party expressed the desire to “create favourable conditions for greater investment by investors of one State in the territory of the other State". When it comes to its interpretation, account must be taken of the purpose of the Treaty, which is to favour the protection of covered investments. In this way, the principle of effectiveness will be applied. The Tribunal agrees with the assessment made in SGS v. Philippines and considers it entirely consistent with the object and purpose of the Treaty to hold that the commitments made by the State towards investments are incorporated and brought within the framework of the Treaty by Article 2(2).
The scope of the Treaty is limited to investments as defined by the Treaty. The Tribunal refers to its previous developments in which it found that the Claimant held a protected investment (see above, para. 297). The wording of Article 2(2) of the Treaty does not support, even implicitly, imposing an additional requirement to limit the effect of the Umbrella Clause to a particular definition of investment agreements. The requirement of the international element allegedly applicable to agreements concluded in relation to investments is not provided for in the Treaty. The Tribunal does not see on what basis such a requirement would be established. (citations omitted)504
232. For the same reasons, the Tribunal cannot accept the Respondent's argument at this stage of the proceedings that the Umbrella Clause covers only certain specific kinds of breaches of the agreements covered by that clause. To accept this argument would require the Tribunal to find that the Umbrella Clause covers only certain kinds of obligations within covered agreements, or that it only prohibits certain kinds of acts by the State in relation to those agreements. As already held by the Tribunal, the coverage of the Umbrella Clause extends to “any obligation” and “is not limited to certain types of obligations but rather encompasses all obligations a host State may have entered into with regard to investments of investors of the other Contracting Party.” The
504 Award on Jurisdiction, paras. 343-345. ↩
[Page 86]
phrase "shall observe" in the Umbrella Clause “is imperative" and unqualified. The Tribunal thus concludes in similar fashion here that the limitation asserted by the Respondent "is not provided for in the Treaty. The Tribunal does not see on what basis such a requirement would be established."
233. In this sense, the Tribunal adopts the conclusion of the tribunal in SGS v. Paraguay, as equally applied to the Umbrella Clause in Article 2(2) of the present Treaty:
Given the unqualified text of [the Umbrella Clause], and its ordinary meaning, we see no basis to import into [the Umbrella Clause] the non-textual limitations that Respondent proposed in its Reply. [The Umbrella Clause] does not exclude commercial contracts of the State from its scope. Likewise, [the Umbrella Clause] does not state that its constant guarantee of observance of such commitments may be breached only through actions that a commercial counterparty cannot take, through abuses of state power, or through exertions of undue government influence. Respondent's appeal to the putative “true meaning” of umbrella clauses cannot take precedence over the plain language of the umbrella clause that is before us. In effect, we see no basis on the face of the clause to believe that it should mean anything other than what it says that the State is obliged to guarantee the observance of its commitments with respect to the investments of the other State party's investors. (citations omitted)505
234. Notwithstanding the foregoing, the Umbrella Clause is not a conflict rule in the sense of stipulating that the Contract is governed by public international law. The Contract remains between the State and the investor, who have agreed a choice of Argentine law to govern it. The Tribunal thus agrees with the holding, cited by the Respondent, from the annulment decision in CMS v. Argentina, to the effect that “[t]he effect of the umbrella clause is not to transform the obligation which is relied on into something else; the content of the obligation is unaffected, as is its proper law."506
235. Nor is the Umbrella Clause a stabilization clause, which would freeze norms of Argentine law and act akin to a negative choice of the law of the State for all norms that would affect performance of the Contract after it is made. Rather, the Umbrella Clause is worded as a substantive undertaking by reference to other substantive undertakings (“any obligation it may have entered into"), and is better analogized to an undertaking in the nature of a suretyship, guarantee, or joint obligation made by Argentina in its capacity as a party to the Treaty for the obligations Argentina would later assume in the Contract in its capacity as a party to the Contract.
505 SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Decision on Jurisdiction, 12 February 2010, para. 168 (CLA-3). ↩
506 CMS Gas Transmission Company v. Argentine Republic, ICSID Case No. ARB/01/8, Decision on Annulment, 25 September 2007, para. 95(c) (RLA-62). ↩
[Page 87]
This undertaking does not prevent mandatory norms issued by Argentina in its capacity as lawmaker from applying to the Contract.
236. The above interpretation of the Umbrella Clause, and the framework of undertakings contained in Article 2(2) of the Treaty, helps shape the issues and the sequence in which they must be decided in the present case. For two of the Claimant's claims—the 10% Fee Cap and the Special Services-the Respondent's defences are limited to the Contract's terms; they do not engage subsequent measures. For the other two claims the pesification and the 13% reduction—the Respondent's defences also involve subsequent justificatory measures that may need to be assessed under the FET, FPS, and non-discrimination standards.507 In all four instances, if all the non-payments, reduced payments, and delayed payments were contractually justified, there is no breach of the Contract and no breach of the Umbrella Clause. The contractual obligations that are guaranteed have been performed, such that no liability arises under the Umbrella Clause.
237. For the Claimant's part, it is in theory possible to argue that the FET, FPS, and non-discrimination standards could be breached by conduct that is strictly in keeping with the Claimant's rights and obligations under the Contract. Such a claim has not, however, been advanced by the Claimant, whose case is premised on the Respondent's alleged breaches of the Contract. Hence, it is necessary to determine first the rights under the Contract.
238. Accordingly, the Tribunal first needs to decide whether the Respondent's actions are consistent with the Contract, as interpreted and applied in accordance with its applicable law. At the same time, the Tribunal recalls its holding in its Award on Jurisdiction that "given the different legal bases of the contractual claims before the Argentinian courts and the claims in the present arbitral proceedings, the Tribunal is not called upon to decide the Claimant's claims arising from contract as such."508 The Tribunal held that, while the Tribunal does not have jurisdiction to decide with res judicata effect the issues arising under the Contract and Argentinian law (in view of Clause 23 of the Contract), it may have to decide them as incidental issues in order to decide the issues arising under the Treaty, which it is empowered to decide with res judicata effect.509
239. In the light of the foregoing, the Tribunal must adopt the following sequence to decide the substantive issues. The Tribunal must first decide whether any of Argentina's non-payments, reduced payments, or delayed payments for the Claimant's services breached any of Argentina's
507 See infra sections VII.C.5 and VIII.C. ↩
508 Award on Jurisdiction, para. 367. ↩
509 Award on Jurisdiction, para. 340. ↩
[Page 88]
obligations under the Contract as interpreted and applied in accordance with Argentine law. If that question is answered in the affirmative, then the Tribunal must analyse two follow-on questions:
(a) whether any alleged breach of contract was justified by mandatory norms issued by Argentina and applicable to the Contract under Argentine law; and
(b) whether any such justifications were inconsistent with Argentina's undertakings under the FET, FPS, and non-discrimination standards in Article 2(2) of the Treaty.
240. The Tribunal must thus take each of the Claimant's contractual claims and determine in each case whether the Claimant correctly invokes a breach of the Contract by the Respondent. This is to what the Tribunal now turns.
241. Clause 3 of the Contract provided as follows:
“THE AUDITOR” undertakes to perform this contract fully in accordance with its quotation included in its Bid in Envelope No. 2 and the clarification concerning the latter, that is, for the sum consisting of ZERO POINT SIXTY FOUR PERCENT (0.64%) of the FOB, FOR or FOT value declared on each inspection certification of audited merchandise. In no case shall the fee to be received by the AUDITOR surpass, during the respective quarter, TEN PERCENT (10%) of the amount invoiced by the inspection companies nor may it be under FOUR PERCENT (4%) thereof, for which purpose, the selection systems to be implemented to identify the shipments to be audited, must take these facts into account.510
242. This clause of the Contract provided that the Claimant's fees for each quarter could not exceed the 10% Fee Cap, i.e., 10% of the amount invoiced by the Inspection Companies. Nominally, this would preclude the Claimant from earning or invoicing fees beyond this cap, which is stated in strict terms: "[i]n no case shall the fee to be received by the Auditor surpass, during the respective quarter, TEN PERCENT (10%)”.
243. At the same time, the very sentence setting out the cap links it to the implementation by the Respondent of an adequate system to select the Inspection Certificates to be audited by the Claimant, as also foreseen in Clauses 6, 8, and 13 of the Contract.511 In particular, Clause 6 of the Contract reads as follows:
510 Contract, Clause 3 (C-2). ↩
511 Contract, Clauses 3, 8, 13 (C-2). ↩
[Page 89]
The AUDITOR shall carry out the inspections at the pertinent Customs, taking care to maintain a suitable ratio according to the operations implemented at each, and in all cases must resolve upon the means required to undertake random controls, as well as to comply with the instruction imparted to it by the EXECUTIVE COMMITTEE of the PRE-SHIPMENT INSPECTION OF IMPORTS PROGRAMME, always ensuring that the values in question do not represent a base that may exceed the maximum fee referred to in clause three.
244. In essence, these provisions foresee a system by which the shipments selected to be audited will not yield a fee surpassing ten percent of the total fees that will be invoiced by all the Inspection Companies for the same period. For this purpose, it is necessary to know, at the time of selecting the shipments to be audited by the Claimant, the value of all the shipments, including those not selected to be audited. Only the Respondent had access to this information at the time when Inspection Certificates were being audited by the Claimant. The latter did not have access to the amount of fees that would be invoiced by the Inspection Companies for all the Inspection Certificates, including those that were not audited.
245. The selection system foreseen to serve this purpose was to be the “red channel” system.512 However, the “red channel” system failed to work in practice, and the Respondent's officials ultimately instructed the Claimant to “install itself physically at the points of destination and to try to take as many dispatches as it can, [even if] this is not the ideal solution."513 As a result, the Inspection Certificates that the Respondent required the Claimant to audit carried auditing fees that repeatedly exceeded the 10% Fee Cap. Furthermore, the Inspection Companies invoiced their fees quarterly, whereas the Claimant had to invoice its fees monthly under the Contract.514
246. The Claimant asserts that the failure to implement an adequate selection system meant that it was not in a position to determine how much the Inspection Companies' total invoicing would be for each quarter, and thus could not comply with the 10% Fee Cap. The Claimant nevertheless contends that it was entitled to a remuneration commensurate with the auditing services it provided, and that it was incumbent on the Respondent, if it wanted to avail itself of the 10% Fee Cap, to devise the method necessary to ensure that it would not require the Claimant to audit certificates that would carry fees exceeding the cap. The Claimant characterizes the devising of such a selection system as a quid pro quo for the imposition of the cap (triggering an exceptio non adimpleti contractus if it was not implemented) and, alternatively, as a condition precedent to the
513 Letter from the Committee to AFIP, 6 August 1999 (C-32) (translation by the Claimant); Report conducted at terminals 1 and 2, 4 February 1999 (C-28); Hearing Tr., Day 2 (7 April 2021), 273:1-11. ↩
514 Contract, Clause 19 (C-2). ↩
[Page 90]
operation of the cap.515 Accordingly, the Claimant argues that the Respondent's own failure to comply with Clause 3 rendered the 10% Fee Cap inapplicable.
247. In the circumstances, the Respondent relied on the 10% Fee Cap to reject all monthly invoices and required the Claimant instead to invoice quarterly, and when the Respondent received these quarterly invoices, it refused to pay any amount exceeding 10% of the fees invoiced by the Inspection Companies over the same quarter. The Respondent asserts that the Contract does not condition the application of the 10% Fee Cap on the implementation of an adequate selection system and that the Claimant also failed to make a sufficient effort to bring its fees within the 10% Fee Cap.
248. The issue is therefore whether the Respondent was entitled to insist on the 10% Fee Cap, or whether it had an obligation to pay for the Claimant's auditing services it required without being entitled to rely on the cap. In the latter case, non-payment of the auditing fees exceeding the 10% Fee Cap would be a breach of the Contract. This issue must be resolved as a matter of contract interpretation under Argentine law.
249. The Claimant's arguments assume that its auditing fees had to be consistent and co-extensive with its work, i.e., that the 10% Fee Cap meant that it would not have to audit certificates in an amount such that its fee would exceed 10% of all the Inspection Companies' fees. In other words, the agreed method to respect the cap was to tailor the value of the shipments to be audited so as to respect the cap.
250. It is correct that the 10% Fee Cap was not the kind of cap where the service provider has full control over its work, assesses the amount of work, and agrees to a cap based on its evaluation of the work envisaged. Instead, the auditing work was in practice performed on demand, its scope was set by the Inspection Certificates that the Respondent required the Claimant to audit. The Claimant had limited control over the amount of services provided, i.e., the certificates it was required to audit. It was obliged to follow whatever instructions were provided by the Respondent. Moreover, it was impossible for the Claimant to determine whether the certificates it was required to audit would reach or surpass the cap. The Respondent, however, was in a position to do so. To calculate the 10% Fee Cap, the Claimant would have had to have access, in real time, to the value of all the certificates that the Respondent did not ask the Claimant to audit.
515 First Bianchi Report, paras. 36-45; Second Bianchi Report, paras. 22-43. ↩
[Page 91]
251. In sum, the 10% Fee Cap was not equivalent to an agreed lump sum remuneration regardless of the services provided. The services required of the Claimant by the Respondent had to be tailored to the cap. Even to the extent that the Contract is taken as an administrative law contract whose scope of work may be unilaterally changed by the State, the agreed link between the fee and the value of audited certificates had to be respected as essential to the economic equilibrium of the Contract. The price of the work was established at 0.64% (and later 0.76%) of the value of the Inspection Certificates. It was not agreed that there could be a disconnect between the quantity of services provided and the amount of remuneration.
252. The scope of work was thus defined by reference to the 10% ratio of the Claimant's fees to the fees of all the Inspection Companies in the Programme. Each Party says that it was incumbent on the other to work out a system to determine the certificates to be audited such that the Claimant's monthly fee would not exceed the 10% Fee Cap. The Claimant says it was impossible for it to do so—both in theory, considering that it had no way of knowing the Inspection Companies' fees, which covered many more certificates than those audited by the Claimant, and also in practice, given the Respondent's instruction “to try to take as many dispatches as it can" rather than implementing any particular selection criteria.
253. The Respondent does not explain how it would have been possible for the Claimant to determine the total fees invoiced by the Inspection Companies, on a monthly basis, let alone in real time. The Respondent simply asserts that the Claimant could have made certain statistical projections and estimates with a view to staying within the 10% Fee Cap. The Respondent does not explain, however, how this would have been expected to work in practice, how such an expectation aligned with the Contract and its performance, or how this would have been consistent with the instruction actually given (i.e., “to try to take as many dispatches as it can").
254. The Respondent insists that the Contract in any event does not establish the implementation of an adequate selection system as a condition precedent to the application of the 10% Fee Cap. It is correct that it does not do so expressly. However, an express textual link is nevertheless made between the “purposes” of the two, the selection system being obliged to "take [the cap] into account" in its design. Moreover, it bears noting that Clause 3 of the Contract establishes not only a 10% Fee Cap, but also a 4% floor. Express language of conditionality would not easily fit.
255. Given the foregoing analysis of the text of the Contract and the circumstances of its performance, the Tribunal thus finds that the Claimant could reasonably claim exemption from the 10% Fee Cap. The Respondent established a selection system in theory, but it was not workable or at least never properly implemented. That circumstance was outside the Claimant's control and
[Page 92]
exclusively within the purview of the Respondent's obligations under the Contract. The 10% Fee Cap could not thus be unreasonably imposed on the Claimant in the absolute terms envisaged by the Respondent's construction of the Contract.
256. In particular, the Tribunal takes into account that the Respondent's actions went beyond a mere breach of the obligation to institute a proper selection system: the Respondent's instruction to the Claimant to abandon the “red channel" system and “install itself physically at the points of destination and to try to take as many dispatches as it can” constituted a wholesale repudiation of this obligation. Such conduct rendered it reasonably impossible for the Claimant to keep its fees under the 10% Fee Cap. It thus precluded the Respondent's right to invoke the correlative (synallagmatic) obligation to reduce the fees to the 10% Fee Cap as a matter of good faith contractual interpretation and exceptio non adimpleti contractus,516 even under the more restrictive application of that doctrine advocated by the Respondent's expert.517
257. Finally, the Respondent's invocation of the so-called Petracca doctrine—purporting to require the Claimant to institute administrative claims, or at least expressly reserve its rights, within 90 days of every single assertion of the 10% Fee Cap—is also unavailing in the circumstances. To the extent that this doctrine is not substantively equivalent in operation to the objections based on acquiescence, estoppel, good faith, and prescription already dismissed above,518 the Tribunal accepts the evidence of the Claimant's expert, Dr. Bianchi, that it would not apply to questions of invoicing or ongoing contractual performance with the formalism that is suggested by the Respondent and its expert, Dr. Comadira.519
258. The Tribunal therefore concludes that the Claimant was contractually entitled in accordance with Argentine law to the amounts claimed in excess of the 10% Fee Cap.
259. Under the Contract, the remuneration was set as a percentage of the value of the shipments recorded in the Inspection Certificates audited by the Claimant. Originally, this percentage was
516 Argentine Civil Code, in force until 31 July 2015, Article 1201 (ABB-19); Argentine Civil and Commercial Code, 1 August 2015, Article 1032 (ABB-20). ↩
517 First Comadira Report, para. 100. ↩
519 Second Bianchi Report, paras. 56-61; Administrative Procedure Act, Section 7 (ABB-56). ↩
[Page 93]
0.64% of the FOB, FOR, or FOT value of each audited Inspection Certificate, as set forth in Clause 3 of the Contract, reproduced once again below:
“THE AUDITOR" undertakes to perform this contract fully in accordance with its quotation included in its Bid in Envelope No. 2 and the clarification concerning the latter, that is, for the sum consisting of ZERO POINT SIXTY FOUR PERCENT (0.64%) of the FOB, FOR or FOT value declared on each inspection certification of audited merchandise. In no case shall the fee to be received by the AUDITOR surpass, during the respective quarter, TEN PERCENT (10%) of the amount invoiced by the inspection companies nor may it be under FOUR PERCENT (4%) thereof, for which purpose, the selection systems to be implemented to identify the shipments to be audited, must take these facts into account.520
260. This fee of 0.64% of the FOB, FOR or FOT value declared on the Inspection Certificates followed from Decree 477/97 and the Tender Terms and Conditions, which stipulated that the Auditor's fee would be 80% of the Inspection Companies' fees:
The price quoted by the bidder shall be a fixed percentage not exceeding EIGHTY PERCENT (80%) of the value of the inspection services established in section g) paragraph II) subparagraph 1) above.521
261. In turn, the Inspection Companies' fees were set at 0.8% of the FOB, FOR or FOT value declared on the Inspection Certificates, as set forth in Annex I, Section (g)(II)(1) of Decree 477/97 and the Tender Terms and Conditions:
ZERO POINT EIGHT PER CENT (0.8%) of the FOB, FOR or FOT value declared on each inspection certificate of merchandise of the IMPORT PRE-SHIPMENT INSPECTION PROGRAMME.
The minimum fee to be charged for each transaction shall be TWO HUNDRED FIFTY UNITED STATES DOLLARS (U$S 250).
Fee amounts shall be paid on a monthly basis by [AFIP] pursuant to the procedure and requirements to be established by the Authority of Application.522
262. Subsequently, Resolution 1106/98 increased the Claimant's remuneration to 0.76% of the FOB, FOR, or FOT value declared on each audited Inspection Certificate. Resolution 1106/98 maintained the Claimant's fees at “EIGHTY PERCENT (80%) of the fees received by the Inspection companies for each audited Inspection certificate", but increased the Inspection Companies' fees to 0.95% of the FOB, FOR, or FOT value declared on each Inspection Certificate as follows:
In consideration for their services, inspection companies shall receive ZERO POINT NINE FIVE PER CENT (0.95%) of the FOB, FOR or FOT value declared on each inspection
520 Contract, Clause 3 (C-2). ↩
521 Decree 477/97, Annex III, Section (c)(XI) (C-6) (translation by the Tribunal). ↩
522 Decree 477/97, Annex I, Section (g)(II)(1) (C-6) (translation by the Tribunal on the basis of the Respondent's Closing, Slide 5). ↩
[Page 94]
certificate of goods covered by the PRE-SHIPMENT INSPECTION OF IMPORTS PROGRAMME.
The minimum fee to be charged for each transaction shall be ONE HUNDRED TWENTY UNITED STATES DOLLARS (U$S 120).
The resulting amounts shall be paid on a monthly basis by the [AFIP] pursuant to the procedure and requirements to be established by the Authority of Application.523
263. The Claimant's fees were to be paid by AFIP as follows:
Payments shall be made monthly in pesos, by the General Administration Bureau of the [AFIP], within THIRTY (30) days following the date the respective invoices are presented, duly approved in accordance with Point c), paragraph VII) of the Specification Sheet. The AUDITOR shall present the invoices pertaining to the duties performed throughout one calendar month, jointly with a summary of the audit reports that have been drawn up, within TEN (10) days of the following month in the form and conditions established by the EXECUTIVE COMMITTEE. Failure to pay at the due time and in the due form shall cause the STATE to be in default, without the need for any demand whatsoever.524
264. In sum, the Claimant's remuneration was set as a proportion of the U.S. dollar value of the shipments, but payments were to be made in Pesos. Until the financial crisis of the end of 2001, the exchange rate between Argentinian pesos and U.S. dollars was pegged at 1:1. Therefore, the fact that the currency of account and the currency of payment were different made no difference. When the fixed parity between the two currencies was repealed at the end of 2001, the interaction between the currency of account and the currency of payment became material. The delay between invoicing and payment also became material to the extent that the exchange rate between the two currencies changed in the interval.
265. The Respondent disputes that remuneration was fixed by reference to the value declared on Inspection Certificates. It does so on the basis that (i) the Inspection Companies' invoicing was in Pesos, (ii) the 10% Fee Cap is expressed by reference to amounts invoiced by the Inspection Companies; (iii) Resolution 1106/98 effectively modified the Claimant's remuneration from “EIGHTY PERCENT (80%) of the value of the inspection services” to “EIGHTY PERCENT (80%) of the fees received by the Inspection companies" (emphasis added). Accordingly, in the Respondent's view, remuneration was to be calculated by reference to amounts invoiced by the Inspection Companies in Pesos, rather than by reference to amounts reported on Inspection Certificates in U.S. dollars.
266. The Tribunal finds that the terms of the Contract and its underlying documentation are clear, and that the accessory elements referred to by the Respondent do not alter their meaning. In particular,
523 Resolution 1106/98, Articles 1(j), 2 (C-8) (translation by the Tribunal on the basis of the Respondent's Closing, Slide 6). ↩
524 Contract, Clause 19 (C-2). ↩
[Page 95]
the Contract and underlying documents consistently define the Claimant's remuneration directly or indirectly by reference to Inspection Certificate values. The mention of “amount invoiced by the [I]nspection [C]ompanies" in the 10% Fee Cap is thus insufficient to suggest an intention to interpose the legal act of invoicing by the Inspection Companies as the ultimate determinant of the Claimant's remuneration. This is especially so when neither of the Parties would have expected that act to have any impact in the light of peso-dollar parity. The same is true for the suggestion that Resolution 1106/98 intended to modify, without any evident reason, the prior terms of the Contract. The Tribunal thus concludes that, under the Contract, the Claimant's remuneration is to be calculated in dollars.
267. As for the variations in the exchange rate between the time of the invoice and the time of payment at the due date, the question arises whether the conversion of the amount due into Pesos at the time of invoicing has fixed Argentina's debt and ICS's entitlement to the amount in Pesos as invoiced. The answer may again depend on the nature and effect of the legal act of invoicing.
268. Pursuant to the last sentence of Clause 19 of the Contract, "[f]ailure to pay at the due time and in the due form shall cause the STATE to be in default, without the need for any demand whatsoever." As a result of being in automatic default, the Respondent would be liable for any damage caused by the delay in payment beyond the due date, including any currency exchange loss.
269. The foregoing does not end the analysis. In 2002, Argentina enacted the Emergency Law and Decree 214/02, which could justify the pesification of the Claimant's remuneration under Argentine law, notwithstanding the Contract's terms.
270. It is common ground between the Parties that Decree 214/02 applied only to "monetary obligations" and not "value obligations", and that the distinction between the two is to be made according to the definition of money obligations in Article 765 of the Argentine Civil and Commercial Code:
An obligation is a money debt where the debtor owes a certain sum of money, determined or determinable, at the time when the obligation is incurred.525
The Parties differ, however, as to whether the Claimant's remuneration under the Contract was at least determinable as a certain sum of money at the time when the obligation is incurred.
525 Argentine Civil and Commercial Code, 1 August 2015, Article 765 (ABB-26). ↩
[Page 96]
271. The Tribunal finds that it was not, and thus did not constitute a money obligation under Article 765 of the Argentine Civil and Commercial Code. As already set forth above, the Claimant's remuneration was measured by reference to the value of the Inspection Certificates audited, and yet payment was to be made in Pesos. Given that the value obligation expressed in US dollars is to be satisfied by payment in Pesos, it cannot be determined in the payment currency until the date of the invoice. This is precisely because, following the repeal of peso-dollar parity by the Emergency Law, the exchange rate between these two amounts may vary in time. The Claimant's remuneration under the Contract was therefore not determinable at the time the obligation was incurred, i.e., at the time of the auditing of Inspection Certificates.526 Accordingly, the fees under the Contract were a value obligation beyond the scope of application of Decree 214/02.
272. The Tribunal concludes that the Claimant was entitled under the Contract to invoice for the full U.S. dollar value of its services.
273. Pursuant to Decree 1060/01, public bodies and entities were ordered to request from suppliers a 13% reduction in the amounts payable for goods or services procured, and to take certain actions if suppliers did not consent to such a reduction in remuneration:527
1) [The responsible officers] will require the suppliers of goods and services the [13%] reduction provided for in article 4 of this decree, in the consideration payable by the National Public Sector.
2) If the supplier does not consent to that reduction, within the period of TEN (10) days of notice of the requirement indicated in paragraph 1), the following procedure must be followed:
a) If the provision of goods or the execution of services is expendable for the general interest, the contract will be revoked.
b) If the provision of goods or the execution of the services is essential, the service, the frequency of deliveries or the requested quantities of goods will be reduced accordingly to adapt the expense to the existing credit, taking into account the decrease ordered. In these cases, the payment of lost profits, of unproductive, indirect expenses, and any concept similar to them, will not be recognized; the contractor's consent will be required for this purpose.
Prior to the negotiation provided for in subsection 2), paragraph b) of this section, the responsible officers for the entities and jurisdictions will require the opinion of the respective Internal Audit Unit.
526 The Tribunal further notes that the 10% Fee Cap, were it to apply, would also preclude the determination of the amount of the Claimant's remuneration at the time of auditing Inspection Certificates, and until the total quarterly amount of fees invoiced by the Inspection Companies was known. This, in the Tribunal's view, further confirms the nature of the obligation as a value obligation. ↩
527 Decree 1060/2001, Articles 1, 4 (C-50). ↩
[Page 97]
Regarding utilities, the conditions in force will be maintained until they are adjusted according to the complementary regulations issued by the SECRETARY FOR THE MODERNIZATION OF THE STATE from the OFFICE OF THE CHIEF OF THE CABINET OF MINISTRIES.528
274. Thus, where the supplier did not consent to the 13% reduction, the respective administrative body was instructed either (i) to terminate the contract, provided that it did not concern an essential public service, or (ii) to reduce the level of services being provided in order to achieve the 13% fee reduction.
275. It is common ground that, until after the termination of the Programme, no such request was made to the Claimant, no consent was given by the Claimant, and no termination or reduction in services ensued. As such, Decree 1060/01 does not apply as such on its own terms.
276. Rather, the Respondent argues that the Claimant should be taken as having tacitly consented to the reduction foreseen in Decree 1060/01 for the period from July to December 2001 in which it continued to provide services after the expiry of the Contract:
The last point that I would like to refer is about Decree 1060, and here the main discussion is about consent. It was very clear from Comadira's explanation that Decree 1060 did not require consent from ICS because consent was only required when a contract was in force. [...T]he Contract expired in March 2001. So, as of July 2001, there was no contract in force. And this is extremely important because today we've heard counsel for Claimant saying that Decree 1060 applied to the Contract. That's not Argentina's position. Argentina's position is that Decree 1060 applies to services provided from July until December which are not based on a contract.529
277. The Respondent also cites Circular No. 05/2001 of the National Procurement Office, issued as a clarification and complement to Decree 1060/01:
3) Contracts that are entered into from the entry into force of the Decree:
From the entry into force of the regulation and since each agency already has its budget reduced by 13%, contracts for the provision of goods and services will [be] entered into taking into account the budget available.530
278. According to the Respondent, by deciding to continue providing services without a contract in force, the Claimant can be taken as having assented to the applicable laws and regulations as they stood at that moment.
528 Decree 1060/2001, Article 1 (C-50). ↩
529 Hearing Tr., Day 7 (14 April 2021), 1115:22-1116:15. ↩
530 Circular No. 05/2001, 29 September 2001 (R-39) (translation by the Tribunal). ↩
[Page 98]
279. The Tribunal has difficulty squaring this argument with the terms of Decree 1060 and Circular No. 05/2001. Neither prejudges the means by which the 13% reduction is to be achieved, as between an agreed reduction, contract termination, or a negotiated reduction in the services provided. And neither even purports to amend Decree 477/97, which provided a legal basis for the Claimant's remuneration for services provided even after the expiry of the Contract.531
280. The Tribunal thus concludes that the Claimant was not subject to a 13% reduction in its remuneration for the services provided in the period from July to December 2001 after the expiry of the Contract.
281. As with the claims regarding the 10% Fee Cap, the Claimant's claims and the Respondent's defences in respect of payment for the Special Services are entirely contractual in nature. Thus, it is necessary first to identify the issues and the rules applicable to the alleged Special Services under the Contract, before applying these rules to decide on each alleged Special Service.
282. In respect of audit services, the Committee could issue instructions that the Claimant had to honour pursuant to Clauses 6, 8, 9 and 13 of the Contract. None of these provisions can supply the contractual basis for a remuneration exceeding the flat-percentage fee payable for each individual Inspection Certificate audited, as Clause 21 provides:
The AUDITOR assumes exclusive responsibility for the services that comprise the object of this contract and it shall render them without any kind of employment relationship with the MINISTRY, and it shall not be entitled to receive any benefit, payment, subsidy, compensation or right which is not expressly stipulated or provided for in this contract.532
283. However, Article 2 of Resolution 1106/98 later established the basis for a distinct remuneration as follows:
When, owing to the nature of the tasks, the amount payable cannot be correlated to certificates of inspection, the audit firm shall draw up a report detailing the costs and fees
531 Hearing Tr., Day 7 (14 April 2021), 1075:6-10. ↩
532 Contract, Clause 21 (C-2). ↩
[Page 99]
following normal market practice, which shall be subject to the approval of the [Committee].533
284. The limitation on the Claimant's remuneration provided in Clause 21 of the Contract may be exceeded only if the conditions set out in Resolution 1106/98 are met. Thus, when an instruction issued by the Committee falls into the category of auditing services provided for in the Contract, the Claimant may not refuse to comply with it and may not require an additional remuneration. If the requested service falls into the category dealt with in Resolution 1106/98, however, the procedure outlined therein applies to remunerate such a service (which has become known and is referred to here as a Special Service).
285. Resolution 1106/98 applies to requests for services for which “the amount payable cannot be correlated to certificates of inspection" because of "the nature of the tasks" requested. Resolution 1106/98 thus defines its own subject matter scope of application by reference to the possibility, or not, of correlating the “amount payable [...] to certificates of inspection". The costs and fees to perform this category of services shall be chargeable by "following normal market practice". The legal opinion provided by DGAJ to MECON in June 2001 recognized the distinction between auditing Inspection Certificates and “tasks that [were] especially required by the Executive Committee", for the remuneration of which Resolution 1106/98 provides a legal basis.534
286. Resolution 1106/98 was approved on 9 September 1998. It does not provide for retroactive effect.535 Article 3 of Resolution 1106/98 states that it “[would] become effective (NINETY) 90 days after its publication in the Official Gazette [11 September 1998], but might become effective earlier upon the express consent of all the currently qualified inspection companies.”536 There is no evidence in the record of any such agreement.
533 Resolution 1106/98, Article 2 (C-8) (translation by the Respondent). ↩
534 DGAJ Opinion 1747, June 2001 (C-99) (translation by the Claimant); Hearing Tr., Day 1 (6 April 2021), 51:14-18; Hearing Tr., Day 7 (14 April 2021), 1075:20-1076:11. ↩
535 Resolution 1106/98, Article 3 (C-8). ↩
536 Rejoinder, para. 151 (translation by the Respondent). ↩
[Page 100]
287. The Respondent contends that Resolution 1106/98 could not expand the scope of services covered by the Contract, and that MECON lacked the authority to issue Resolution 1106/98.537 However, within its scope of application, Resolution 1106/98 is the public law authorization to the Committee to procure services for which the amount payable cannot be correlated with the audit of Inspection Certificates. The Respondent cannot be heard to challenge, in its relationship with the Claimant, a formal resolution by invoking a lack of capacity or authority of MECON, at least where such a resolution has not been impugned and set aside by a competent court.
288. Article 2 provides for a framework under which it is for the Committee to request a Special Service, for the Claimant to provide the Committee with information “detailing the costs and fees following normal market practice", which the Committee may accept or not. In doing so, it is for the Committee to determine whether to go on or not with its request. Given this procedure, the decision as to whether the requested service qualifies as a Special Service under Resolution 1106/98, or is merely an instruction about how to carry out the audit services, stands to be made in the first place by the Committee, which requests the service.
289. If the Claimant disagrees with the Committee's view based on the nature of the task requested, such a disagreement about the characterization of the requested task as a Special Service should normally arise at the time of the request.
290. Resolution 1106/98 does not require that the Committee's request for a Special Service be in writing or any other specific form. It is, therefore, sufficient to prove by any means that a particular request was made. A request may be made orally and proven by testimony. In any event, good faith can substitute a form requirement if the party relying on non-compliance with a requirement of form is the one who has disregarded it.
537 Rejoinder, para. 156; Second Comadira Report, para. 177; Hearing Tr., Day 7 (14 April 2021), 1121:15-1122:11; Hearing Tr., Day 4 (9 April 2021), 561:11-20. ↩
[Page 101]
291. If the requested service qualifies under Resolution 1106/98, the next step is for the Committee to approve detailed information on the costs and fees quoted by the Claimant. This information must follow the "normal market practice". If such practice is to invoice “costs and fees”, it may be possible to give only an estimate in advance of completing the work, unless a lump sum is to be agreed for the costs and fees, which Resolution 1106/98 does not appear to require.
292. The question then arises as to the legal consequence of the Committee requesting and obtaining a Special Service without following the procedure outlined in Resolution 1106/98. Should the Claimant have refused to perform the service? If it performed the requested service, should it be denied any specific remuneration, or is the Claimant entitled to be remunerated at the normal market price to be determined? The Claimant will still be bound to carry out the requested service (per Clause 9 and 13 of the Contract in particular), but the remuneration for such service will have to be determined.
293. Looking at the Parties' respective responsibilities, it was not the Claimant's responsibility to follow the procedure outlined in Resolution 1106/98 to obtain the service. Rather, that was the Committee's responsibility. The Claimant was bound to comply with, and could rely on, the Committee's requests to prepare and deliver the requested Special Services, whether the Respondent previously requested and approved details as to how the “costs and fees" would be determined following the “normal market practice" referred to in Resolution 1106/98.
294. Furthermore, according to the principle of good faith in dealings between the Administration and private persons, the former could not choose not to observe a procurement requirement and later rely on its non-observance to refuse to pay for the service it has requested and obtained. It is for the Claimant to prove that it could in good faith understand that the Committee requested a Special Service. If the Claimant did not insist on having a costing approved by the Committee before undertaking the work requested by the Committee, the Claimant ran the risk that if the Committee later disagreed about the characterization of the requested service or about the price invoiced, the Claimant may bear the burden of proving (as it demands payment, ultimately in arbitration) that the requested work fell under Resolution 1106/98 and that the price invoiced was “following normal market practice".
295. Most reports include a cover letter which mentions that the report is issued “acorde al Artículo 2º de la Resolución (ex M.E. y O. y S.P.) 1106/98, segundo párrafo, presentado
[Page 102]
oportunamente".538 If such a mention was incorrect, it would appear to be incumbent on the Respondent to dispute it promptly lest it be deemed to have tacitly agreed. As no timely objection is proven in the record, the next question is whether such a mention can override the definition in Resolution 1106/98 of the kind of task which may be invoiced at the market price. The answer is that such a mention does not prevail over public mandatory regulation of Argentina for two reasons. First, an agreement cannot change the scope of application of a public law act. Second, even if it could, the mention refering to the Resolution 1106/98, it accepts that the latter governs the issue of remuneration for Special Services, including all its requirements.
296. The Claimant claims remuneration for 21 reports, which the Respondent considers to be merely the performance of instructions regarding the audit of Inspection Certificates, not Special Services falling under Resolution 1106/98.
297. Resolution 1106/98 supersedes Clause 21 of the Contract only after it came into force. Resolution 1106/98 was approved on 9 September 1998.539 Before that date, any additional remuneration is ruled out by both Clause 21 of the Contract and public procurement regulations.
298. As a result, even if the Claimant performed a service pursuant to Clauses 9 or 13 of the Contract before 9 September 1998 that would, after that date, fall into the category of Special Services, the remuneration foreseen by Resolution 1106/98 would still not apply. In this scenario, the remuneration for auditing Inspection Certificates is not apposite to the different work done for the Special Service, but there is no basis under the Contract for a remuneration exceeding the flat-percentage fee applying to the audit of individual Inspection Certificates. Thus, the Respondent may have obtained a distinct service having value without having to pay a distinct remuneration to the Claimant. Nonetheless, recovery of the Claimant's costs (without a profit) under the theory of unjust enrichment is ruled out by Clause 21 of the Contract or, in any event, by regulations governing public procurement of services.
538 See for example Report on Imports from Brazil from December 1998 to January 1999, p. 1 (C-132). ↩
539 Rejoinder, paras. 150-151; Resolution 1106/98 (C-8); Hearing Tr., Day 1 (6 April 2021), 96:15-97:5. ↩
[Page 103]
299. The Respondent asserts that the first eight Special Services were undertaken before Resolution 1106/98.540 The dates for the Special Services are said to be based on Mr. Santamaría's testimony,541 but it is not clear where he himself obtained these dates. Mr. Santamaría says that they are "an estimate of when the relevant service was performed”.542 Some of these dates are, however, roughly a year earlier than the dates of those eight reports in the record.543 The Claimant's letter to the Committee of 8 October 2003 states dates for some of the Special Services which are earlier than 9 September 1998 (reports regarding Kodak, Asia Imports, Glasses and glassware, Desarrollo y Mantenimiento del Software Capacitación de Usuarios, the latter not being part of the Special Services claimed in the present arbitration), and the letter states two dates (one before and one after 9 September 1998) for the TDK and the Bananas reports; the dates stated for the other reports are after 9 September 1998.544
300. The question is whether the information and documentation provided to the Committee as the alleged Special Services, together with the research and the preparation of these reports and the supporting documentation, were already subsumed or implied in the audit of the selected Inspection Certificates performed by the Claimant, so that the Committee's requests for these alleged Special Services were merely requiring communication of supporting information that should in any event have been elicited by the Claimant to perform its audit of selected Inspection Certificates. If, however, the “amount payable” for these services cannot "be correlated to certificates of inspection” (“relacionarse [...] con certificados de inspección”), the services qualify as Special Services under Resolution 1106/98. This assessment needs to be carried out seriatim in respect of each alleged Special Service.545
301. It appears from the Committee's conduct that the alleged Special Services were not volunteered by the Claimant, but that they have been requested orally or in writing by the Committee, as
540 Rejoinder, para. 150-151; Statement of Claim, para. 73. ↩
541 First Santamaria Statement, paras. 38-40, fn. 68. ↩
542 First Santamaria Statement, para. 40. ↩
544 Letter from ICS to the Committee, 8 October 2003, p. 2 (CLEX-15). ↩
545 See infra paras. 321-388. ↩
[Page 104]
testified by Mr. Santamaría.546 The Respondent does not appear to dispute that the Committee requested the services alleged to be Special Services, but only that they were part of the Claimant's obligations under the Contract, and that anyway eight of them fell outside the temporal scope of Resolution 1106/98.
302. The Respondent states that such a prior approval (which the Committee dispensed with) has never taken place.547 It appears from the record that the Committee neither required nor approved prior information as to the costs and fees to be incurred for any of the requested Special Services. The request was made by the Committee ex post facto, once the Committee referred the invoices to SIGEN, which requested proof of strict compliance with the preliminary requirements of Resolution 1106/98.548
303. While the Respondent disputes the characterization of the Special Services and the existence of any prior approval of their pricing, it does not dispute that the Claimant delivered the 21 reports. Both the Claimant and the Respondent have exhibited in the present arbitration copies of the reports alleged to be Special Services.549 Furthermore, the Respondent also acknowledged that, in addition to the Claimant's audit tasks, the latter had “prepared Special Reports on request from the Executive Committee to arbitrate corrective actions."550
304. Furthermore, the Directorate General of Legal Affairs also provided a legal opinion to MECON in June 2001 stating, inter alia, that “there are also tasks that are required by the Executive Committee and may not be related to those [‘the review of inspection documents (Inspection
546 First Santamaría Statement, para. 39; Hearing Tr., Day 2 (7 April 2021), 211:21-213:1. ↩
547 Rejoinder, para. 177: “the Executive Committee never approved the expenses and fees for the alleged special services, nor did it approve the invoices for such alleged services. 271 [footnote 271 refers to Acosta Second Witness Statement, 8; Cupello Second Witness Statement, § IV.]". ↩
548 Letter from the Committee No. 958/2001 to ICS, 4 June 2001, enclosing Letter from SIGEN to the Committee, 30 May 2001 (C-44). ↩
549 Claimant exhibits complete copies of 19 of the 21 reports and related work product provided to Argentina in connection with the Claimant's provision of Special Services (C-122 – C-140). The Claimant accepts the Report on Iquique (Chile), Colonia and Montevideo, Uruguay Free Zone (R-137) and the Report regarding Compliance with CEPIPI Article 2, provision No. 4 (R-101) submitted by Argentina as accurate and therefore does not dispute them nor submit another version of these documents. ↩
550 Reply, para. 63; Committee Certification No. IPE 164/04, 22 July 2004 (C-98) (translation by the Claimant). ↩
[Page 105]
Certificates)'] [...] It is precisely for these tasks that later by [MECON Resolution] No. 1106 dated 9 September 1998, in section 2 it was established [quoting the wording of Resolution 1106/98]".551 In 2006, the Committee requested, in order to comply with Resolution 1106/98, supporting evidence of the amounts invoiced by the Claimant for all the reports.552 Such requests may be seen as an implied recognition that the reports have been supplied and even that the Claimant has a potential entitlement to be paid under Resolution 1106/98, provided the supporting evidence is satisfactory.
305. When the Committee received the invoices from the Claimant, it referred them to SIGEN,553 which blocked their payment for non-compliance with public regulations, so that the invoices did not reach AFIP for payment.554 The Respondent previously approved one of the Claimant's invoices for a Special Service (provided it was restated in Pesos).555
306. The Claimant seeks reimbursement of its costs to produce the Special Services and a fee, which is calculated as a profit margin of 20 percent. Given that the Respondent has not approved any of the 21 invoices for Special Services except one,556 it is incumbent on the Claimant to allege and prove the quantum of these two components of its claim based on the Special Services. Specifically, the Claimant needs to establish a sufficient link between each cost claimed and the work required for the Special Service. It is not for the Tribunal to seek to make that link.
307. The justification for each cost would usually be evidenced in an expense report filed with the company by the person seeking reimbursement of the expense by the company, as well as time-sheets of the persons who worked on a project including a summary description of the work they did. This or equivalent evidence is necessary to prove the justification of the cost allegedly incurred in connection with the Special Service claimed. Lastly, the evidence needs to be
551 DGAJ Opinion 1747, June 2001 (C-99) (translation by the Claimant); Reply, para. 65. ↩
552 Letters from the Committee to ICS, 24 and 25 January and 21 February 2006 (C-57). ↩
555 Statement of Claim, para. 199; Letter from the Committee to ICS, 22 August 2002 (C-42); Hearing Tr., Day 1 (6 April 2021), 61:19-62:1. ↩
556 Statement of Claim, paras. 87-89; First Santamaría Statement, para. 42. ↩
[Page 106]
commensurate to the amounts claimed, which are high for the Special Services (USD 3,035,071.68 for 21 reports, or an average of USD 144,527.22 for each report).
308. On the other hand, the fact that the Respondent kept requesting more Special Services shows that the Respondent considered them to be of value, and there is no evidence that the Committee stated or even understood at the time that these services would not be remunerated.
309. The Claimant relies in the present arbitration on the supporting documentation that it had communicated to the Respondent in 2006 at the latter's request.557 There is no doubt that effort and expense must have gone into producing each Special Service. However, the relationship between each cost claimed and the Special Service is often not sufficiently shown to make a finding that it is more likely than not that the cost claimed was incurred specifically for the Special Service. The supporting documentation does not include timesheets filled in by each person claimed to have worked on the Special Service with a summary description allowing the Tribunal to make the link between such work and the Special Service. Instead, the time charges are based on assigning a portion of each person's wages to a Special Service, without it being clear how that portion was arrived at.
310. The supporting documentation proves that costs were recorded in the ordinary course of business, and the testimony of Mr. Santamaría provides a foundation for this, such that this evidence is deemed admissible and convincing, in the absence of rebuttal evidence, as to the fact that these costs were actually incurred by the Claimant. However, the allegation that these costs and fees were required to produce the report in question is challenged by the Respondent, and its expert, Mr. Dapena, has shown that the link between the report and the costs and fees claimed is sometimes not proven or is questionable. For instance, Mr. Dapena has identified serious inconsistencies between the costs invoiced and the subject of, or persons involved in, the Special Services.558
311. The supporting documentation consists also of invoices from suppliers and subcontractors, travel expenses, and other miscellaneous expenses. However, there is often a lack of the usual cover sheets or expense reports indicating the person having incurred the expense and the purpose or justification for the expense, which would allow one to make the link with the Special Service
557 Supporting Files for the Special Services Reports (C-101 – C-121). ↩
558 See e.g., Second Dapena Report, para. 242. ↩
[Page 107]
claimed. Many expenses appear to fall into the category of general overheads. The distinction between direct and indirect costs does not assist in finding what costs were incurred specifically for a Special Service. They show that the Claimant incurred the costs, but they do not establish that link.
312. Furthermore, as mentioned, the Respondent has been able to discredit some of the indirect costs claimed, “such as travel expenses and accommodation for company officers who are not included in the personnel payroll presented by ICS as assigned to the alleged Special Services, the fees of certified accountants for the financial statements audits, and even the computation of certain amortizable fixed assets, among other items”.559 The Claimant has not been able to rebut these criticisms by the Respondent's expert or to rehabilitate the credibility of its evidence by supplementing it and producing an expert report reviewing and certifying the evidence, which the Tribunal cannot do for the Claimant, who bears the burden of proof.
313. Overall, the evidence is therefore partially insufficient for the purpose of ascertaining the Claimant's costs qualifying under Resolution 1106/98. Without performing itself an expert review of each piece of evidence (almost 5,000 pages in total) contained in the 2006 documentation, the Tribunal will have to apply a discounting factor to the costs claimed. The Tribunal considers that on average the Claimant has proven 90 percent of the costs claimed. A discount of ten percent will consequently be applied to all the invoices that otherwise qualify for remuneration under Resolution 1106/98. This is not an ex aequo et bono determination. It is the application of the law on evidence (burden of proof) as well as the substantive law on damages, which provides that when a debt of damages is owed with certainty, but it is not possible or practicable after the fact to determine its exact amount, the Tribunal must make the closest possible approximation of the quantum, taking into account all relevant considerations based on the evidence available.
314. The Claimant contends that a profit margin of 15-20% is the normal market practice for its industry, calculated as a percentage of the revenue or sale price (excluding VAT). The Respondent's expert argues that this percentage should be calculated as a percentage of the costs,
559 Second Dapena Report, paras. 110, 202 (Table 4), 240-241 (Appendix II) (lease and cleaning services for ICS headquarters, electricity, gas, running water, mobile phone, photocopier rental, monthly rent for parking places, subscriptions to newspapers and magazines, English courses, public relations, ordinary expenses for office supplies, etc). Mr. Dapena further points out serious inconsistencies, and expenses that can hardly be connected with the claimed Special Service, or any other of the Special Services. Second Dapena Report, paras. 242-245. See also Second Dapena Report, para. 108, Picture 8. ↩
[Page 108]
not of revenue. The Tribunal accepts Mr. Santamaría's evidence, based on his professional experience, of a normal market practice of a profit of approximately 20 percent of the costs and fees incurred for the services, as opposed to Mr. Dapena's calculation. However, the profit margin should be calculated on the amount ex VAT, because VAT is a recoverable expense which has been charged to the Respondent.
315. The 20-percent margin of profit is to be applied to each Special Service to the extent that the Claimant has not claimed a lower profit as, if the profit calculated by the Claimant for a given Special Report is a lower percentage, the Tribunal may not grant more than such a lower claimed profit, as it might otherwise run the risk of making an award ultra petita.
316. The Claimant charged VAT on all its invoices for the 21 Special Services, and VAT is included in its claim. The Respondent disputes that such VAT may be passed on to it. Since all these invoices were issued by ICS Inspection and Control Services Limited, a company registered in the UK, and not by the Claimant's Argentinian branch, it appears from the expert evidence in the record that VAT should not be charged on the overall amount of each invoice. This is confirmed by the Claimant's own practice of not having charged VAT on its other invoices for audit services issued by the UK company.560 Thus, according to the Respondent, if the Claimant has paid such VAT in Argentina on the Special Services, the damage was self-inflicted, and there is no basis to recover this VAT from the Respondent in the present arbitration.
317. However, as explained by the Claimant:
Mr. Dapena says that the Special Services invoices are incorrectly including VAT. First of all, the Special Services invoices, if we look at them, they don't include any VAT as a separate line item. What they include is VAT on the portion of the costs incurred in Argentina. If you look at the bottom left part of the screen--I don't know if you can see my cursor here--but I'm pointing at the red connector between 14,375 and 3,018. 3,018.93 is the amount of VAT on the Argentina portion of the invoice and only on the Argentina portion of the invoice. And this is a cost to ICS Argentina. And is therefore, being passed on to as a cost as the rest of the costs are in these Special Services invoices, so there is nothing really surprising, and I don't think there is anything incorrect, but I can see at least in the application of VAT on the Special Services invoices, as long as it corresponds only to the Argentina costs. (citations omitted)561
318. The breakdown of each invoice appearing at page 5 in the supporting documentation for each Special Service, shows that VAT is added only on the portion of the costs and fees performed in
560 ICS, Invoices and collection documents (CLEX-16); Hearing Tr., Day 6 (13 April 2021), 991:10-997:1. ↩
561 Hearing Tr., Day 5 (12 April 2021), 676:11-677:3. ↩
[Page 109]
Argentina and not on the portion performed abroad, when a portion is performed abroad. This is borne out in respect of a number of Special Services.562
319. The invoices are due in USD as the value currency for the same reasons explained in respect of the other invoices, even though nearly half of the invoices for the Special Services were issued in Pesos and the majority of the costs allegedly incurred by the Claimant were incurred in Pesos.
320. Lastly, the fact that the Claimant's auditors questioned the recoverability of the invoices for the Special Services does not mean that they are not legally owed, which is a determination to be made by the Tribunal.
321. Based on the above findings, there remains to be assessed whether the date of each report falls within the temporal scope of application of Resolution 1106/98 (i.e., after 9 September 1998), whether the nature of the task qualifies under Resolution 1106/98 (the amount payable cannot be correlated to Inspection Certificates because of the nature of the task), and whether the amount invoiced is justified under Resolution 1106/98 (proven costs and 20 percent profit margin).
322. The topics of each one of the 21 reports claimed as Special Services are briefly described at paragraph 76 above. To assess and adjudicate each alleged Special Service, three documents are particularly relevant: the reports,563 the invoices,564 and the supporting documentation;565 the latter includes a breakdown of costs and profit for each invoice under “ANEXO I”.
562 For instance, this can be seen with the reports on the kiwi imports (invoice at CLEX-16, p. 389, invoice breakdown at C-114, p. 5: no VAT charged on costs and fees abroad), on the Colonia Uruguay Free Zone Report (invoice breakdown at C-115, p. 5), on the Compliance with Article 2, Provision No. 4 of the Committee (invoice at CLEX-16, p. 391, invoice breakdown at C-116, p. 5), on the satellite receivers (invoice at CLEX-16, p. 415, invoice breakdown at C-120, p. 5), and on the Price of Kosher Milk (invoice at CLEX-16, p. 417, invoice breakdown at C-121, p. 5). ↩
563 Special Services Reports (C-122 – C-140, R-137, R-101). ↩
564 ICS, Invoices and collection documents, pp. 382-417 (CLEX-16). ↩
565 Supporting Files for the Special Services Reports (C-101 – C-121). ↩
[Page 110]
323. Date of the report: 1 September 1999. Therefore, Resolution 1106/98 applies to this report.
324. Nature of the task: The assignment was to verify whether the FOB price published in a statistical bulletin could be deemed valid in comparison to the average prices for that same product in Ecuador, Brazil, and Argentina.567 The nature of this task, which is to investigate other markets for apparently policy considerations, is distinct from auditing any Inspection Certificate, so that its remuneration cannot be correlated with the audit of any Inspection Certificate. Therefore, this report qualifies as a Special Service, and the amount payable must follow normal market practice.
325. Based on the findings made above,568 however, the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced (USD)569 | Amount owed (USD) | ||
| Fees and costs | 22,276.75 | 22,276.75 | Alleged fees and costs |
| -2,227.68 | Average discount for defective proof | ||
| 20,049.08 | Fees and costs proven | ||
| Profit (roughly 20% of the 35,959.00 total incl. VAT) | 7,441.43 | 4,009.82 | Profit margin of 20% on the above amount |
566 Report on Banana Imports into Argentina, Ref. No. ICS C/99/17141/ARG, dated 1 September 1999 (C-122, 263 pages). The invoice is found at CLEX-16, p. 382, and the supporting documentation for the invoice is C-101 (116 pages). ↩
567 Report on Banana Imports into Argentina, Ref. No. ICS C/99/17141/ARG, 1 September 1999, p. 255 (C-122); Report on Banana Imports into the Argentine Republic, 1 September 1999, pp. 01215-01221, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional - Ministerio de Economía s/ Proceso Ordinario", File No. 1948/12 (R-84). ↩
568 See supra paras. 282-320. ↩
569 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-101). ↩
[Page 111]
| 24,058.89 | Total owed ex-VAT | ||
| VAT paid | 6,240.82 | 5,052.37 | VAT paid |
| Total claimed | 35,959.00 | 29,111.26 | Total owed |
326. Date of the report: 8 June and 6 July 1999. Therefore, Resolution 1106/98 applies to this report.
327. Nature of the task: Even though the work is based on the physical inspection carried out by the Claimant's employees with respect to specific Inspection Certificates, the task was to identify and analyse flaws in the inspection process and devise improvements which could be implemented in the import pre-shipment audit programme.571 This task is distinct from auditing individual certificates. Therefore, this report qualifies as a Special Service.
328. Based on the findings made above,572 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced573 | Amount owed | ||
| Fees and costs | 29,715.60 | 29,715.60 | Alleged fees and costs |
| -2,971.56 | Average discount for defective proof | ||
| 26,744.04 | Fees and costs proven |
570 Reports on the Deficiencies Detected in the Issuance of Inspection Certificates, 8 June and 6 July 1999 (C-123, 202 pages). The invoice is found at CLEX-16, p. 390, and the supporting documentation for the invoice is C-102 (137 pages). ↩
571 Report on the Deficiencies Detected in the Issuance of Inspection Certificates, 8 June and 6 July 1999, pp. 123-124 (C-123). ↩
572 See supra paras. 282-320. ↩
573 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-102). ↩
[Page 112]
| Profit (approx. 25% of the 29,715.60 ex VAT) | 7,489.36 | 5,348.81 | Profit margin of 20% on the above amount |
| 32,092.85 | Total owed ex-VAT | ||
| VAT paid | 7,813.04 | 6,739.50 | VAT paid |
| Total claimed | 45,018.00 | 38,832.35 | Total owed |
329. Date of the report: 31 August 1998. Therefore, Resolution 1106/98, which was approved on 9 September 1998 without retroactive effect, does not apply to this report, so that no remuneration can be charged for it.575
330. Date of the report: 28 May 1999. Therefore, Resolution 1106/98 applies to it. However, this report comprises a number of letters pre-dating 9 September 1998.
331. Nature of the task: In any event, the nature of the task does not qualify as a Special Service. The Claimant did not specifically rebut the analysis presented by the Respondent in this respect.577 Therefore, this report does not qualify as a Special Service, so that no remuneration can be charged for it.
574 Special Audit Report concerning Importations from Asia, pp. 3-4 (C-124). ↩
575 Resolution 1106/98, Article 3 (C-8). ↩
576 Special Report on the Inspection Certificates not found in the Database of the Committee, 28 May 1999, p. 91 (C-125, 94 pages). The supporting documentation for the invoice is C-104. ↩
577 Statement of Defence, paras. 195-200. ↩
[Page 113]
v. “Kodak Study”578
332. Date of the report: July-August 1998. Therefore, Resolution 1106/98 does not apply to this report.
333. Nature of the task: In any event, the report was not requested by the Committee. The Claimant spontaneously recommended adding new products in the tariff norms and requesting the Claimant to prepare a report on this topic, in order to increase the goods subject to the Inspection Programme, as argued by the Respondent and not specifically rebutted by the Claimant.579 Therefore, this report does not qualify as a Special Service.
vi. “TDK Line Study”580
334. Date of the report: 18 May 1999. Therefore, Resolution 1106/98 applies to this report.
335. Nature of the task: As argued by the Respondent,581 the report reviews the quality of the services provided by pre-shipment inspection companies by studying a sample of Inspection Certificates relating to TDK and SAMSUNG products. The review revealed an important difference between the official price lists surveyed by the Claimant and the FOB values of the imported goods. The Claimant recommended that the Committee penalize inspection companies SGS and SOCOTEC. While the Claimant had to survey extrinsic evidence of prices, it is arguable that this kind of survey is part of the necessary work to audit Inspection Certificates for these products, and the Claimant has not shown the contrary. Therefore, this report does not qualify as a Special Service.
vii. “Chicken Imports Report SADIA S.A.”582
336. Date of the report: 11 February 1999. Therefore, Resolution 1106/98 applies to this report.
337. Nature of the task: The Claimant audited the quality of the Inspection Companies’ services based on four Inspection Certificates issued by Bureau Veritas. For this purpose, the Claimant had to “audit the quality, quantity, tariff classification and customs value of the goods in the certificates
578 Study Regarding Kodak Products, July – August 1998, p. 245 (C-126, 252 pages). The supporting documentation for the invoice is C-105. ↩
579 Statement of Defence, paras. 201-203. ↩
580 Special Report on the tariff codes No. 8523.11.10; 8523.13.20 and 8523.90.00, 18 May 1999, p. 1 (C-127). ↩
581 Statement of Defence, paras. 204-206. ↩
582 Report on Chicken Imports SADIA S.A., 11 February 1999, p. 4 (C-128). The supporting documentation for the invoice is C-107. ↩
[Page 114]
of Importer SADIA ARG S.A.” While the Claimant also had to review extrinsic evidence, it is arguable that this kind of survey is part of the work necessary to audit Inspection Certificates for these products, as asserted by the Respondent,583 and the Claimant has not shown the contrary. Therefore, this report does not qualify as a Special Service within the meaning of Resolution 1106/98.
viii. “Glass and Glassware Study”584
338. Date of the report: 18 August 1998. Therefore, Resolution 1106/98 does not apply to this report.
ix. "Marble and Granite San Luis S.A."585
339. Date of the report: 29 October 1998. Therefore, Resolution 1106/98 applies to this report.
340. Nature of the task: The Respondent describes this assignment as follows, which has not been specifically rebutted by the Claimant:
This alleged ‘special’ service consists of a two-page letter containing additional information on inspection certificate No. 1-98-013925-0 issued by Surveillance S.A. in regard to importer Mármoles y Granitos de San Luis S.A., with the sole purpose of analyzing the tariff classification.586
341. This work appears to be necessary to perform the audit of the Inspection Certificates. Remuneration for this work can be correlated with the audit fee. Therefore, this report does not qualify as a Special Service.
x. "Temporary Imports Study”587
342. Date of the report: 17 February 1999. Therefore, Resolution 1106/98 applies to this report.
343. Nature of the task: The purpose of this report was to analyse import operations under the Temporary Import Admission regime, which took place between February 1998 and January
583 Statement of Defence, paras. 207-209. ↩
584 Letter from the Claimant to the Committee on the Importations of Soifer Hnos. S.A.I.C. (referred to by the Claimant as Glass and Glassware Study), 18 August 1998, p. 1 (C-129). ↩
585 Letter from the Claimant to the Committee on Mármoles y Granitos San Luis S.A., 29 October 1998, p. 1 (C-130). The supporting documentation is C-109. ↩
586 Statement of Defence, paras. 213-214. ↩
587 Temporary Imports Study, 17 February 1999, p. 2 (C-131). The supporting documentation for the invoice is C-110 (468 pages). ↩
[Page 115]
1999. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
344. Based on the findings made above,588 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced589 | Amount owed | ||
| Fees and costs | 362,778.19 | 362,778.19 | Alleged fees and costs |
| -36,277.82 | Average discount for defective proof | ||
| 326,500.37 | Fees and costs proven | ||
| Profit (roughly 14% of the 423,163.64 total ex VAT) | 60,385.45 | 45,710.05 | Profit margin of 14% on the above amount |
| 372,210.42 | Total owed ex-VAT | ||
| VAT paid | 88,864.36 | 78,164.19 | VAT paid |
| Total claimed | 512,028.00 | 450,374.61 | Total owed |
588 See supra paras. 282-320. ↩
589 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-110). ↩
[Page 116]
xi. “Report on Iquique (Chile), Colonia and Montevideo, Uruguay Free Zone”590
345. Date of the report: 1999.591 Therefore, Resolution 1106/98 applies to it.
346. Nature of the task: The Claimant describes its task as follows:
Based on this item redistribution, we have focused the price research task on gathering information about cars and motorcycles, electronic devices, TDK blank cassettes, footwear, textile products and household items. [...] The prices of different products we obtained, the general listings of which are attached as Appendix II, are very useful to check the prices of goods imported from Iquique-Chile to the Argentine Republic.592
347. As the Respondent must admit,593 in this report, the Claimant performed an investigation aimed at determining the business operations pertaining to imports from Iquique (Chile), Colonia, and Montevideo (Uruguay) free zones in 1999. The report describes in some detail how the free zones operate and explains what the trading mechanisms were with respect to these zones, in order to evaluate whether there is undervaluation of the prices of vehicles exported from these zones.
348. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
349. Based on the findings made above,594 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced595 | Amount owed | ||
| Fees and costs | 44,015.20 | 44,015.20 | Alleged fees and costs |
590 Report on Iquique, Colonia and Montevideo Free Trade Zones, p. 17 (R-137). The supporting documentation for the invoice is C-111 (336 pages). ↩
591 Report on Iquique, Colonia and Montevideo Free Trade Zones, p. 17 (R-137). While some costs were incurred in December 1998, most of the costs and fees were incurred in the first quarter of 1999 (C-111), which confirms that the report was issued later in 1999. ↩
592 Report on Iquique, Colonia and Montevideo Free Trade Zones, pp. 7-8 (R-137) (translation by the Respondent). ↩
593 Statement of Defence, paras. 218-220. ↩
594 See supra paras. 282-320. ↩
595 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-111). ↩
[Page 117]
| -4,401.52 | Average discount for defective proof | ||
| 39,613.68 | Fees and costs proven | ||
| Profit (roughly 23% of the 44,015.20 total ex VAT) | 10,506.29 | 7,922.74 | Profit margin of 20% on the above amount |
| 47,536.42 | Total owed ex-VAT | ||
| VAT paid | 11,449.51 | 9,982.65 | VAT paid |
| Total claimed | 65,971.00 | 57,519.06 | Total owed |
xii. “Brazil Imports, October - December 1998 and January 1999”596
350. Date of the report: The cover letter produced in R-95 (consisting of only the text of the report of 15 pages without annexes) is dated 17 February 1999 (and this is the date used in relation to the quotation made by Respondent in the Statement of Defence at paragraph 221), but the cover letter produced in C-132 (consisting of the report and its volumes of annexes, totalling 739 pages) is dated 30 November 2000. Yet, the text of the report produced in the two exhibits is the same. No effort seems to have been made to reconcile the discrepancy between cover letters in the Parties’ submissions; while the cover letter produced in R-95 mentions Chapter 30, which is the topic of a second report prepared in relation to Brazil imports (see xiii infra), the latter report produced at C-133 has a cover letter of 7 December 2000. However, there is no need to investigate the matter further because, whichever cover letter is the correct one for the report produced at C-132 and R-95, this report was made at the earliest in 1999, so that Resolution 1106/98 applies to it.
596 Report on Imports from Brazil from December 1998 to January 1999, p. 7 (C-132). ↩
[Page 118]
351. Nature of the task: Assessing the impact that the devaluation of the Brazilian currency against the U.S. dollar had on imports to Argentina.597 The Claimant describes the task as follows:
The purpose of this job was to analyse the behaviour and pattern of the import operations from Brazil subject to pre-shipment, as per the request made by the Import Pre-shipment Executive Committee, as a result of the devaluation of the currency of the Federal Republic of Brazil (real), in January of this year. For this reason, we performed a structural analysis of all import pre-shipment inspection certificates (CIPI) issued by the inspection companies during the period between 1 October 1998 and 31 January 1999, the origin of the goods being the aforementioned country.598
352. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
353. Based on the findings made above,599 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced600 | Amount owed | ||
| Fees and costs | 170,659.52 | 170,659.52 | Alleged fees and costs |
| -17,065.95 | Average discount for defective proof | ||
| 153,593.57 | Fees and costs proven | ||
| Profit (roughly 37% of the 170,659.52 total ex VAT, or 22.3% of the 282,874 incl. VAT) | 63,120.64 | 30,718.71 | Profit margin of 20% on the above amount |
597 Statement of Defence, paras. 221-223; Brazil Imports Report, 17 February 1999, p. 01515, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-95). ↩
598 Brazil Imports Report, 17 February 1999, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-95), p. 01515 (translation by the Respondent). ↩
599 See supra paras. 282-320. ↩
600 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-112). ↩
[Page 119]
| 184,312.28 | Total owed ex-VAT | ||
| VAT paid | 49,093.83 | 38,705.58 | VAT paid |
| Total claimed | 282,874.00 | 223,017.86 | Total owed |
xiii. “Imports Chapter 30, October - December 1998 and January 1999”601
354. Date of the report: 7 December 2000. Therefore, Resolution 1106/98 applies to this report.
355. Nature of the task: The Respondent explained the nature of the task as follows:
This report was also prepared following the devaluation of the Brazilian currency against the U.S. dollar in 1999, and Claimant’s job again consisted in analysing inspection certificates and comparing them using graphs. The report focused on the tariff positions in Chapter 30 of the Mercosur Common Nomenclature (Pharmaceutical Products).602
356. The Claimant performed a structural analysis of all the Inspection Certificates issued from October 1998 to January 1999 for goods imported from Brazil, in order to identify all goods fitting the tariff position of Chapter 30 and evaluating the trend and the impact of the devaluation on a possible flood of imports into Argentina.
357. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
358. Based on the findings made above,603 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced604 | Amount owed |
601 Report on Imports Chapter 30 from Brazil from December 1998 to February 1999, pp. 7-8 (C-133, 575 pages). The supporting documentation is C-113 (184 pages). ↩
602 Statement of Defence, paras. 224-225. ↩
603 See supra paras. 282-320. ↩
604 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-113). ↩
[Page 120]
| Fees and costs | 128,028.73 | 128,028.73 | Alleged fees and costs |
| -12,802.87 | Average discount for defective proof | ||
| 115,225.86 | Fees and costs proven | ||
| Profit (roughly 28.7% of the 164,858.91 (costs and fees + VAT) | 47,353.09 | 23,045.17 | Profit margin of 20% on the above amount |
| 138,271.03 | Total owed ex-VAT | ||
| VAT paid | 36,830.18 | 29,036.92 | VAT paid |
| Total claimed | 212,212.00 | 167,307.94 | Total owed |
xiv. “Kiwi Imports Study”605
359. Date of the report: The report is undated, but the supporting documentation shows that the costs and fees were mostly incurred in June 1999, which shows that the report was issued later in 1999. Therefore, Resolution 1106/98 applies to this report.
360. Nature of the task: The purpose of the report was to analyse the past and future evolution of the international kiwi market, including supply (with a focus on Chile) and demand in Argentina.606
361. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
605 Kiwi Imports Study (C-134). The invoice is found at CLEX-16, p. 389. The supporting documentation is C-114 (126 pages), including an invoice breakdown at p. 5. ↩
606 Kiwi Imports Study, p. 4 (C-134). ↩
[Page 121]
362. Based on the findings made above,607 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced608 | Amount owed | ||
| Fees and costs | 18,266.06 | 18,266.06 | Alleged fees and costs |
| -1,826.60 | Average discount for defective proof | ||
| 16,439.46 | Fees and costs proven | ||
| Profit (roughly 23.5% of the 18,266.06 ex VAT) | 4,301.35 | 3,287.89 | Profit margin of 20% on the above amount |
| 19,727.35 | Total owed ex-VAT | ||
| VAT paid | 398.58 | 348.42 | VAT paid |
| Total claimed | 22,966.00 | 20,075.77 | Total owed |
xv. “Colonia Uruguay Free Zone Report”609
363. Date of the report: 20 May 1999. Therefore, Resolution 1106/98 applies to this report.
364. Nature of the task: The Claimant visited the administrative and operational offices of Inspection Companies in the free zone of Colonia in Uruguay to evaluate the quality of their services. By its nature, this work goes beyond the audit of, and its remuneration can therefore not be correlated
607 See supra paras. 282-320. ↩
608 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-114). ↩
609 Colonia Uruguay Free Zone Report, 20 May 1999 (C-135). The supporting documentation is C-115. ↩
[Page 122]
with, any individual Inspection Certificate. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
365. Based on the findings made above,610 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced611 | Amount owed | ||
| Fees and costs | 16,086.05 | 16,086.05 | Alleged fees and costs |
| -1,608.61 | Average discount for defective proof | ||
| 14,477.45 | Fees and costs proven | ||
| Profit (roughly 25.2% of the 16,086.05 ex VAT) | 4,054.24 | 2,895.49 | Profit margin of 20% on the above amount |
| 17,372.93 | Total owed ex-VAT | ||
| VAT paid | 355.72 | 306.84 | VAT paid |
| Total claimed | 20,496.00 | 17,679.77 | Total owed |
610 See supra paras. 282-320. ↩
611 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-115). ↩
[Page 123]
xvi. “Report regarding Compliance with CEPIPI Article 2, provision No. 4”612
366. Date of the report: The report is undated, but the supporting documentation shows that the work was performed in 1999, which confirms that the report was issued later in 1999. Therefore, Resolution 1106/98 applies to this report.
367. Nature of the task: The report concerned how best to optimize the functioning of the audit of the pre-shipment inspection programme, including interaction with customs, and ensure effective compliance by the Inspection Companies in view of the requirements introduced by Order No. 4/1999 of the Executive Committee, based on an evaluation of a sample of Inspection Certificates during the period from 15 August 1999 to 31 January 2000.613
368. The Respondent emphasizes that the Claimant acknowledged in this report that it was “responsible for expressing an opinion on the said certificates on the basis of [its] audit job”.614 However, this does not, when taken in context, mean that the preparation of the report was part of the ordinary audit work remunerated by the flat-percentage fee per Inspection Certificate. Furthermore, the scope of the report and the work performed to prepare it go beyond the audit of – and its remuneration can therefore not be correlated with – individual Inspection Certificates. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
369. Based on the findings made above,615 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced616 | Amount owed | ||
| Fees and costs | 172,970.05 | 172,970.05 | Alleged fees and costs |
612 Report regarding Compliance with Article 2, Provision No. 4 of the Committee (R-101). Invoice at CLEX-16, p. 391. The supporting documentation is C-116 (426 pages), including an invoice breakdown at p. 5. ↩
613 Report regarding Compliance with Article 2, Provision No. 4 of the Committee, p. 4 (R-101). ↩
614 Statement of Defence, paras. 230-232; Report regarding Compliance with Article 2, provision 4 of the Executive Committee, p. 01370, submitted by ICS as Appendix XXVII to its statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-101). ↩
615 See supra paras. 282-320. ↩
616 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-116). ↩
[Page 124]
| -17,297.01 | Average discount for defective proof | ||
| 155,673.05 | Fees and costs proven | ||
| Profit (approx. 25% of the 172,970.05 total ex VAT) | 43,594.44 | 31,134.61 | Profit margin of 20% on the above amount |
| 186,807.65 | Total owed ex-VAT | ||
| VAT paid | 32,407.51 | 27,954.59 | VAT paid |
| Total claimed | 248,972.00 | 214,762.24 | Total owed |
xvii. “Analysis of Imports among Related Companies”617
370. Date of the report: The report is undated, but the scope of work extends to January 2000. Therefore, Resolution 1106/98 applies to this report.
371. Nature of the task: The Respondent emphasizes that the Claimant acknowledged as follows:
As independent auditors, we inform about the certificates issued by importers who are related to the exporter. These certificates refer to the period from January 1998 to January 2000, this company being responsible for expressing an opinion on said certificates on the basis of our audit job, the scope of which was that specified in section I.C hereof.618
372. However, this is only the first paragraph of the conclusions in the report, which go on to explain that the task was different from ordinary audit work.619 In particular, the Claimant analysed
617 Analysis of Imports among Related Companies, November 1999 – January 2000 (C-136, 506 pages). The supporting documentation is C-117 (272 pages), including an invoice breakdown at p. 5. ↩
618 Analysis of Imports among Related Companies, p. 01727, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-102), p. 01750 (translation by the Respondent in Statement of Defence, paras. 233-235). ↩
619 Analysis of Imports among Related Companies, November 1999 – January 2000, p. 28 (C-136). ↩
[Page 125]
41,545 Inspection Certificates and identified the many countries of the related companies to draw conclusions and quantify the impact at a global level.
373. Therefore, the sentence quoted by the Respondent does not, when taken in context, mean that the preparation of the report was part of the ordinary audit work remunerated by the flat-percentage fee per Inspection Certificate. The scope of the report and the work performed to prepare it go beyond the audit of - and its remuneration can therefore not be correlated with – individual Inspection Certificates. Therefore, this report qualifies as a Special Service under Resolution 1106/98.
374. Based on the findings made above,620 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced621 | Amount owed | ||
| Fees and costs | 296,612.26 | 296,612.26 | Alleged fees and costs |
| -29,661.23 | Average discount for defective proof | ||
| 266,951.03 | Fees and costs proven | ||
| Profit (roughly 25% of the 296,612.26 ex VAT) | 74,756.54 | 53,390.21 | Profit margin of 20% on the above amount |
| 320,341.24 | Total owed ex-VAT | ||
| VAT paid | 59,875.20 | 51,648.11 | VAT paid |
| Total claimed | 431,244.00 | 371,989.35 | Total owed |
620 See supra paras. 282-320. ↩
621 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-117). ↩
[Page 126]
xviii. “Item 8703 Imports Investigation”622
375. Date of the report: The report in Exhibit C-137 is undated, but it is dated 26 December 2005 in Exhibit R-139. Therefore, Resolution 1106/98 applies to this report.
376. Nature of the task: As correctly contended by the Respondent, “[t]his alleged ‘special' service consists in customs clearance of automobile tariff positions entering Argentina through the red channel. This was clearly part of the auditing services that Claimant had to provide, for which it has already been duly paid.”623 Therefore, this report does not qualify as a Special Service.
xix. “Iquique 2 Report”624
377. Date of the report: The costs and fees have been incurred for this report appear to have been incurred over a period spanning 1999 and 2000. When it was proposed by the Claimant, the report was planned to be completed during March 2001.625 Therefore, Resolution 1106/98 applies to this report.
378. Nature of the task: In response to the Committee’s request of 2 March 2001,626 the Claimant sent a proposal on 16 March 2001, setting forth how the requested report will be realised and how much it will cost (USD 24,849.68), specifying that the report will be prepared pursuant to Article 2 of Resolution 1106/98.627
379. Exhibit C-138 does not contain the text of the report itself, only the annexes (621 pages), and Exhibit R-105 does not contain the report but the Claimant’s proposal to prepare the report. The text of the report itself appears to be missing from the record produced by the Parties.
622 Statistics on Imports of Tariff Item 8703 (automobiles) (C-137, 621 pages). The invoice is found at CLEX-16, p. 413. The supporting documentation is C-118 (273 pages). ↩
623 Statement of Defence, paras. 236-237. ↩
624 Special Audit Report Concerning the Free Trade Zone of Iquique, 2001 (C-138, R-105). The supporting documentation is C-119 (266 pages). ↩
625 Special Audit Report Concerning the Free Trade Zone of Iquique, 2001, p. 01868 (R-105). ↩
626 Executive Committee’s letter No. 0485, 2 March 2001, p. 01860, submitted by ICS as Appendix XXVII to its amended statement of claim in proceedings “Inspection and Control Services c/ Estado Nacional – Ministerio de Economía s/ Proceso Ordinario”, File No. 1948/12 (R-104). ↩
627 Special Audit Report Concerning the Free Trade Zone of Iquique, 2001 (R-105). ↩
[Page 127]
380. However, the Respondent does not dispute that the report was produced and that it was consistent with the Claimant’s proposal of 16 March 2001. Rather, the Respondent takes issue with the characterization of the report as a Special Service, as follows:
This new report on the free zone of Iquique (Chile) was made following a publication of La Nación newspaper, which reported how goods that had been under-invoiced by Iquique entered the country. The Committee, exercising its powers, requested that Claimant “exhaustively audit the certificates issued by the inspection companies for operations carried out during 2000/20001 from the Iquique (Chile) free zone in order to determine if there were tax losses and the amount thereof”. The Contract provided for the possibility of the Committee giving instructions to audit specific operations. In addition, the job was closely related to the control of inspection certificates, which was one of the main activities of the audit firm. This was clearly part of the auditing services that Claimant had to provide and for which it has already received the respective fees.628
381. However, given that the Claimant’s proposal makes it clear that the report will be prepared as a Special Report under Resolution 1106/98, it is difficult to see how the Respondent can dispute this characterisation. Furthermore, judging by the Claimant’s proposal, as well as the supporting documentation, the scope of the report and the work performed to prepare it go beyond the audit of - and its remuneration can therefore not be correlated with – individual Inspection Certificates. It includes a review of all the Inspection Certificates of 2000-2001 for imports from the free zone of Iquique to perform analyses and surveys based on a sample of Inspection Certificates from the years 1999-2001. Therefore, this report qualifies as a Special Service.
382. Based on the findings made above,629 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
| Amount invoiced630 | Amount owed | ||
| Fees and costs | 17,436.22 | 17,436.22 | Alleged fees and costs |
| -1,743.62 | Average discount for defective proof |
628 Statement of Defence, paras. 238-240. ↩
629 See supra paras. 282-320. ↩
630 Supporting Files for the Special Services Reports, p. 5 (invoice breakdown) (C-119). There are two versions of the invoice (CLEX-16, pp. 392-393), as if one corrected the other due to an inversion of two figures in the number. The breakdown uses USD 24,849.68 (i.e., the number at p. 392), and not USD 24,894.68. ↩
[Page 128]
| 15,692.60 | Fees and costs proven | ||
| Profit (roughly 25% of the 17,436.22 total ex VAT) | 4,394.53 | 3,138.52 | Profit margin of 20% on the above amount |
| 18,831.12 | Total owed ex-VAT | ||
| VAT paid | 3,018.93 | 2,604.12 | VAT paid |
| Total claimed | 24,849.68 | 21,435.23 | Total owed |
xx. “Satellite Antenna Report”631
383. Date of the report: 24 January 2021. Therefore, Resolution 1106/98 applies to this report.
384. Nature of the task: The Claimant identified a strategic alliance with a close commercial relationship between exporter and importer since 1998. The Claimant determined the value of the satellite antennas on the international market and analysed the imports of such products into Argentina, to determine whether the FOB value reported in the Inspection Certificates was within a normal range of value for such goods (the answer being affirmative).632 Contrary to what the Respondent contends,633 it is not just a matter of simply verifying the price reported in five Inspection Certificates. The scope of the report and the work performed to prepare it go beyond the audit of - and its remuneration can therefore not be correlated with – individual Inspection Certificates. Therefore, this report qualifies as a Special Service.
385. Based on the findings made above,634 the amount claimed must be corrected to arrive at the amount owed by the Respondent as follows:
631 Letter from the Claimant to the Committee on the Values Certified by Surveyseed (Satellite Antenna Report), 24 January 2001 (C-139, 159 pages). The supporting documentation is C-120 (110 pages). ↩
632 Letter from the Claimant to the Committee on the Values Certified by Surveyseed (Satellite Antenna Report), 24 January 2001, p. 1 (C-139). ↩
633 Statement of Defence, paras. 241-243. ↩
634 See supra paras. 282-320. ↩
[Page 129]
| Amount invoiced635 | Amount owed | ||
| Fees and costs (montos netos) | 39,971.69 | 39,971.69 | Alleged fees and costs |
| -3,997.17 | Average discount for defective proof | ||
| 35,974.52 | Fees and costs proven | ||
| Profit (approx.. 22% of the 39,971.69 total incl. VAT) | 8,851.68 | 7,194.90 | Profit margin of 20% on the above amount |
| 43,169.42 | Total owed ex-VAT | ||
| VAT paid | 6,240.82 | 1,552.33 | VAT paid |
| Total claimed | 50,579.00 | 44,721.75 | Total owed |
xxi. “Rito Kosher Milk Report”636
386. Date of the report: 20 July 2001. Therefore, Resolution 1106/98 applies to this report.
387. Nature of the task: The Respondent correctly points out:
After analyzing inspection certificates, the Committee identified a reduction in the import prices of kosher milk from Uruguay and requested ICS to confirm in its database whether the reduction was justified. After a price audit, Claimant concluded that “USD 0.30 per certified litre is not reasonable". This job was clearly part of the auditing services provided by Claimant under the Inspection Programme, for which it has already received the respective fees.637
635 ICS, Invoices and collection documents, p. 415 (CLEX-16). ↩
636 Letter from the Claimant to the Committee on the Price of Kosher Milk, 20 July 2001 (C-140, 31 pages). The supporting documentation is C-121 (107 pages). ↩
637 Statement of Defence, paras. 244-246. ↩
[Page 130]
388. Therefore, this report does not qualify as a Special Service.
389. The Tribunal has concluded above that the Claimant was entitled to the remuneration it has claimed under the Contract and Argentine law, with the exception of the payment claimed on account of the following alleged Special Services (and a discount on account of defective proof):
390. Having held above that the Respondent’s obligations undertaken under the Contract are covered by the Umbrella Clause, and that the breach of these obligations under the Contract and Argentine law would also by extension constitute violations of the Umbrella Clause of the Treaty,638 the Tribunal now concludes that the Respondent has violated the Umbrella Clause, giving rise to a right to reparation under the Treaty and international law.
638 See supra paras. 231-233. ↩
[Page 131]
391. In the event that the Tribunal were to find any breach of the Treaty, the Respondent submits that the defence of necessity under customary international law precludes the unlawfulness of its conduct on account of the severe financial crisis in Argentina in 2001.639 On the other hand, the Claimant contends that the Respondent’s necessity defence is “of no relevance to the claims being advanced by the Claimant” and, in any event, fails to meet the conditions required under international law to invoke such defence.640
392. The Respondent submits that necessity may constitute a ground for precluding wrongfulness under customary international law.641 For the Respondent, the state of necessity forms part of the law applicable to the present dispute pursuant to Article 8(4) of the Treaty.642 According to the Respondent, the conditions for invoking the defence have been authoritatively laid down in Article 25 of ILC Articles:643
- Necessity may not be invoked by a State as a ground for precluding the wrongfulness of an act not in conformity with an international obligation of that State unless the act:
- Is the only way for the State to safeguard an essential interest against a grave and imminent peril; and
- Does not seriously impair an essential interest of the State or States towards which the obligation exists, or of the international community as a whole.
- In any case, necessity may not be invoked by a State as a ground for precluding wrongfulness if:
- The international obligation in question excludes the possibility of invoking necessity; or
- The State has contributed to the situation of necessity.644
639 Statement of Defence, para. 440. ↩
640 Reply, paras. 156, 164-168. ↩
641 Statement of Defence, para. 434; Hearing Tr., Day 1 (6 April 2021), 113:8-14. ↩
642 Statement of Defence, para. 439. ↩
643 Statement of Defence, para. 437; International Law Commission Draft Articles on Responsibility of States for Internationally Wrongful Acts, annexed to UN General Assembly Resolution 56/83, 12 December 2001, UN Doc. A/RES/56/83 (R-111). See also Hearing Tr., Day 1 (6 April 2021), 113:14-24. ↩
644 Statement of Defence, para. 437; International Law Commission Draft Articles on Responsibility of States for Internationally Wrongful Acts, Article 25, annexed to UN General Assembly Resolution 56/83, 12 December 2001, UN Doc. A/RES/56/83 (R-111). ↩
[Page 132]
393. The Respondent submits that the conditions for invoking the defence of necessity under Article 25 of the ILC Articles are fulfilled in the present case.645
394. First, the Respondent maintains that the emergency measures it undertook in response to the crisis were the “only way for the State to safeguard” its essential interests against a grave and imminent peril.646 It alleges that both the unprecedented recession that Argentina experienced since mid-1998 as well as the crisis that erupted in late 2001 posed “an extremely serious threat to its existence, its political and economic survival, to the possibility of maintaining its essential services in operation, and to the preservation of its internal peace”.647 The Respondent avers that a number of international tribunals have recognized as much, including the tribunals in LG&E v. Argentina, Continental v. Argentina, and Metalpar v. Argentina.648 The Respondent also refers to the statement of Eduardo Ratti, Legal and Administrative Secretary of the Ministry of Economy in 2002, who confirms that Argentina “had no choice but to adopt the emergency measures that ICS now challenges” and that “[o]ther responses would have resulted in an even deeper economic and financial crisis.”649 The Respondent submits that this view is shared by renowned economists and arbitral tribunals.650
645 Statement of Defence, para. 478. ↩
646 Statement of Defence, paras. 445-462. ↩
647 Statement of Defence, para. 442; LG&E Energy Corp., LG&E Capital Corp., LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, paras. 257, 259 (RLA-203). See also Ibid., paras. 445-453. ↩
648 Statement of Defence, paras. 445-452; LG&E Energy Corp., LG&E Capital Corp., LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, paras. 231-236 (RLA-203); Continental Casualty Company v. Argentine Republic, ICSID Case No. ARB/03/9, Award, 5 September 2008, para. 180 (RLA-232); Metalpar S.A. and Buen Aire S.A. v. Argentine Republic, ICSID Case No. ARB/03/5, Award, 6 June 2008, para. 108 (RLA-210). ↩
649 Rejoinder, paras. 306-308; Ratti Witness Statement, paras. 14-16, 23-24; Hearing Tr., Day 1 (6 April 2021), 114:5-18. ↩
650 Statement of Defence, paras. 454-461; Barry Eichengreen Report submitted in Urbaser S.A. and Consorcio de Aguas Bilbao Bizkaia v. Argentine Republic, ICSID Case No. ARB/07/26, 20 May 2013, para. 7 (R-121); Paul Krugman, Reckonings; A Cross of Dollars, New York Times, 7 November 2001 (R-122); Paul Krugman, Argentina’s Money Monomania, December 2001 (R-123); Michael Mussa, Argentina needs effective not unthinking support, Financial Times, 9 November 2001 (R-124); Back from the brink?, The Economist Global Agenda, 16 November 2001 (R-125); LG&E Energy Corp., LG&E Capital Corp., LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 257 (RLA-203); Hearing Tr., Day 1 (6 April 2021), 114:19-115:15. ↩
[Page 133]
395. Second, the Respondent avers that “no essential interest of any other State or of the international community as a whole was impaired”.651
396. Third, the Respondent submits that it “did not contribute to the situation of necessity in such a way as to prevent it from invoking it as a ground for precluding wrongfulness under international law”.652 Quoting the Commentaries to the ILC Articles, the Respondent asserts that “[f]or a plea of necessity to be precluded [...] the contribution to the situation of necessity must be sufficiently substantial and not merely incidental or peripheral.”653 The Respondent asserts that the crisis did not result from its own actions but from “external shocks” that affected the country since 1997, in particular, the financial and economic crisis in Asia, Russia, and Brazil as well as the decision of the Federal Reserve Board of the United States of increasing interest rates.654 The Respondent asserts that from 1998 onwards it began implementing, with the support of international organizations, a number of measures to address the deep recession and avoid an economic collapse.655
397. Fourth, the Respondent submits that there is nothing in the Treaty “that excludes the possibility of invoking necessity or limits its invocation in any way”.656 To the contrary, the Respondent asserts that in accordance with Article 8(4) of the Treaty necessity forms part of the law applicable to this dispute.657
651 Statement of Defence, para. 477; LG&E Energy Corp., LG&E Capital Corp., LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 257 (RLA-203). ↩
652 Statement of Defence, paras. 463-474. ↩
653 Statement of Defence, para. 463; ILC Commentaries to its Articles on Responsibility of States for Internationally Wrongful Acts, Part One, Commentary to Article 25, in Report of the International Law Commission on the work of its 53rd Session, 2001, Chapter IV, U.N. Doc A/56/10 (RLA-84). ↩
654 Statement of Defence, paras. 466-473; Rejoinder, para. 312; Barry Eichengreen Report submitted in Urbaser S.A. and Consorcio de Aguas Bilbao Bizkaia v. Argentine Republic, ICSID Case No. ARB/07/26, 20 May 2013, paras. 8-16 (R-121); Joseph Stiglitz, “Whither reform? Towards a new agenda for Latin America”, ECLAC Review, 2003, vol. 80, p. 10 (2003) (R-127); Metalpar S.A. and Buen Aire S.A. v. Argentine Republic, ICSID Case No. ARB/03/5, Award, 6 June 2008, para. 195 (RLA-210); LG&E Energy Corp., LG&E Capital Corp., LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, paras. 256-257 (RLA-203); Urbaser & CABB v. Argentine Republic, ICSID Case No. ARB/07/26, Award, 8 December 2016, paras. 710-711, 714 (RLA-137). ↩
655 Statement of Defence, para. 466; Continental Casualty Company v. Argentine Republic, ICSID Case No. ARB/03/9, Award, 5 September 2008, para. 236 (RLA-232); Rejoinder, para. 312. ↩
656 Statement of Defence, para. 476. ↩
657 Statement of Defence, para. 476. ↩
[Page 134]
398. The Claimant contends that the Respondent’s necessity defence is “of no relevance to the claims being advanced by the Claimant”.658
399. The Claimant notes that Respondent’s necessity defence concerns the measures implemented during Argentina’s financial crisis of 2001-2002, specifically the enactment of the Emergency Law and Decree 214/02.659 None of these measures, the Claimant asserts, have been challenged by the Claimant in these proceedings.660 It is the Claimant’s submission that none of these measures applied to the Claimant’s rights under the Contract.661 The Claimant additionally contends that the Respondent’s imposition of the 10% Fee Cap and failure to pay for the special services are unrelated to the measures adopted due to the financial crisis of 2000-2001.662
400. In any event, the Claimant asserts that the Respondent has failed to show that its necessity defence meets the conditions required under international law, as set forth in Gabčíkovo-Nagymaros and in Article 25 of the ILC Articles.663
401. The Claimant notes that numerous tribunals have previously considered and dismissed the Respondent’s necessity defence with respect to the measures undertaken during the financial crisis of 2001-2002.664 In the Claimant’s view, a distinction should also be drawn between the
663 Reply, paras. 161-162; Gabčíkovo-Nagymaros Project (Hungary v. Slovakia) [1997] ICJ Rep 7, para. 51 (CLA-199); ILC Articles, Article 25 (CLA-55); Hearing Tr., Day 1 (6 April 2021), 37:19-21. ↩
664 Reply, para. 164; CMS Gas Transmission Company v. The Republic of Argentina, ICSID Case No. ARB/01/8, Award, 12 May 2005, para. 331 (CLA-16); Enron Corporation and Ponderosa Assets, L.P. v. Argentine Republic, ICSID Case No. ARB/01/3, Award, 22 May 2007, para. 313 (CLA-52); Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, para. 354 (CLA-22); BG Group Plc. v. The Republic of Argentina, UNCITRAL, Final Award, 24 December 2007, para. 411 (CLA-40); National Grid P.L.C v. The Argentine Republic, UNCITRAL, Award, 3 November 2008, para. 260 (CLA-10); Suez, Sociedad General de Aguas de Barcelona S.A., and InterAguas Servicios Integrales del Agua S.A. v. The Argentine Republic, ICSID Case No. ARB/03/17, Decision on Liability, 30 July 2010, para. 243 (CLA-202); Suez, Sociedad General de Aguas de Barcelona, S.A. and Vivendi Universal, S.A. v. Argentine Republic, ICSID Case No. ARB/03/19 and AWG Group Ltd. v. The Argentine Republic, UNCITRAL, Decision on Liability, 30 July 2010, para. 265 (CLA-12); Total S.A. v. The Argentine Republic, ICSID Case No. ARB/04/01, Decision on Liability, 27 December 2010, para. 484 (CLA-46); Impregilo S.p.A. v. Argentine Republic, ICSID Case No. ARB/07/17, Award, 21 June 2011, para. 359 (CLA-200); EDF International S.A., SAUR International S.A. and León Participaciones Argentinas S.A. v. Argentine Republic, ICSID Case No. ARB/03/23, Award, 11 June 2012, para. 1171 ↩
[Page 135]
cases concerning an “essential security” exception expressly provided in the applicable BIT665 and the cases like the present one in which no such provision is found in the relevant treaty, such that the necessity plea was raised under customary international law.666
402. According to the Claimant, the majority of the tribunals that considered the Respondent’s necessity defence on the basis of customary international law have found that the Respondent failed to fulfil the applicable requirements.667 In particular, the aforementioned tribunals held that (i) “the economic crisis did not meet the threshold of a grave and imminent peril required under Article 25”;668 (ii) “the measures adopted by Argentina were not the only way to address the crisis”;669 and (iii) “Argentina contributed to the crisis”.670 The Claimant submits that
665 (CLA-201); Hochtief AG v. The Argentine Republic, ICSID Case No. ARB/07/31, Decision on Liability, 29 December 2014, para. 301 (RLA-107); Hearing Tr., Day 1 (6 April 2021), 38:15-17. ↩
666 Reply, para. 164; Continental Casualty Company v. The Argentine Republic, ICSID Case No. ARB/03/9 (CLA-120); LG&E Energy Corp., LG&E Capital Corp., and LG&E International, Inc. v. Argentine Republic, ICSID Case No. ARB/02/1 (CLA-18).. ↩
669 Reply, para. 165(a); CMS Gas Transmission Company v. The Republic of Argentina, ICSID Case No. ARB/01/8, Award, 12 May 2005, paras. 321-322 (CLA-16); Enron Corporation and Ponderosa Assets, L.P. v. Argentine Republic, ICSID Case No. ARB/01/3, Award, 22 May 2007, para. 306 (CLA-52); Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, para. 348 (CLA-22); Total S.A. v. The Argentine Republic, ICSID Case No. ARB/04/01, Decision on Liability, 27 December 2010, para. 483 (CLA-46). ↩
670 Reply, para. 165(b); CMS Gas Transmission Company v. The Republic of Argentina, ICSID Case No. ARB/01/8, Award, 12 May 2005, para. 324 (CLA-16); Enron Corporation and Ponderosa Assets, L.P. v. Argentine Republic, ICSID Case No. ARB/01/3, Award, 22 May 2007, para. 308 (CLA-52); Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, para. 350 (CLA-22); Suez, Sociedad General de Aguas de Barcelona S.A., and InterAguas Servicios Integrales del Agua S.A. v. The Argentine Republic, ICSID Case No. ARB/03/17, Decision on Liability, 30 July 2010, para. 238 (CLA-202); Suez, Sociedad General de Aguas de Barcelona, S.A. and Vivendi Universal, S.A. v. Argentine Republic, ICSID Case No. ARB/03/19 and AWG Group Ltd. v. The Argentine Republic, UNCITRAL, Decision on Liability, 30 July 2010, para. 260 (CLA-12); EDF International S.A., SAUR International S.A. and León Participaciones Argentinas S.A. v. Argentine Republic, ICSID Case No. ARB/03/23, Award, 11 June 2012, paras. 1171-1172 (CLA-201); Total S.A. v. The Argentine Republic, ICSID Case No. ARB/04/01, Decision on Liability, 27 December 2010, para. 484 (CLA-46). ↩
Reply, para. 165(c); CMS Gas Transmission Company v. The Republic of Argentina, ICSID Case No. ARB/01/8, Award, 12 May 2005, para. 329 (CLA-16); Enron Corporation and Ponderosa Assets, L.P. v. Argentine Republic, ICSID Case No. ARB/01/3, Award, 22 May 2007. para. 312 (CLA-52); Sempra Energy International v. The Argentine Republic, ICSID Case No. ARB/02/16, Award, 28 September 2007, para. 354 (CLA-22); National Grid P.L.C v. The Argentine Republic, UNCITRAL, Award, 3 November 2008, para. 260 (CLA-10); Suez, Sociedad General de Aguas de Barcelona S.A., and InterAguas Servicios Integrales del Agua S.A. v. The Argentine Republic, ICSID Case No. ARB/03/17, Decision on Liability, 30 July 2010, para. 243 (CLA-202); Suez, Sociedad General de Aguas de Barcelona, S.A. and Vivendi Universal, S.A. v. Argentine Republic, ICSID Case No. ARB/03/19 and AWG Group Ltd. v. The Argentine Republic, UNCITRAL, Decision on Liability, 30 July 2010, para. 265 (CLA-12); Impregilo S.p.A. v. Argentine Republic, ICSID Case No. ARB/07/17, Award, 21 June 2011, paras. 353, 358 (CLA-200); EDF International S.A., SAUR International S.A. and León Participaciones Argentinas S.A. v. Argentine Republic, ICSID Case No. ARB/03/23, Award, 11 June 2012, paras. 1171, 1173 (CLA-201); El Paso
[Page 136]
“Argentina’s necessity plea in the present case is no different [...] and should be dismissed for the same reasons”.671
403. In any event, the Claimant posits that a state of necessity could have only justified the suspension of the Respondent’s obligations until the financial crisis subsided in mid-2003.672 Nor, the Claimant argues, would necessity have released the Respondent from its obligation to compensate the Claimant for the losses suffered as a result of the measures adopted by Argentina.673 The former was confirmed, the Claimant underscores, by the tribunals in LG&E v. Argentina and Urbaser v. Argentina.674
404. The Respondent’s defence of necessity seeks a finding precluding the wrongfulness of the measures taken in response to the severe financial crisis in Argentina in 2001, namely the Emergency Law and Decrees 214/02 and 1060/01. The Tribunal has, however, concluded above that the Claimant’s entitlements to remuneration under the Contract fell outside the scope of application of these measures.675 It is therefore unnecessary to decide whether the wrongfulness of such measures is precluded by the defence of necessity.
671 Energy International Company v. The Argentine Republic, ICSID Case No. ARB/03/15, Award, 31 October 2011, para. 656 (CLA-100); EDF International S.A., SAUR International S.A. and León Participaciones Argentinas S.A. v. Argentine Republic, ICSID Case No. ARB/03/23, Award, 11 June 2012, para. 1174 (CLA-201). ↩
672 Reply, para. 166; Hearing Tr., Day 1 (6 April 2021), 39:1-40:4. ↩
673 Reply, paras. 167-168; Hearing Tr., Day 1 (6 April 2021), 39:1-40:4. ↩
675 Hearing Tr., Day 7 (14 April 2021), 1023:6-17. ↩
See supra paras. 271, 280.
[Page 137]
405. The Claimant seeks full reparation of the harm that it has allegedly suffered as a result of the Respondent’s violations of the Treaty, in the form of full payment of the invoices issued under the Contract, plus interest.676 In support of its claim for compensation, the Claimant has filed two expert reports by Mr. Dellepiane.677 Mr. Dellepiane estimates that as of 10 June 2020, the Claimant’s total damages amount to USD 238,928,038.81.678
406. The Respondent requests that the Tribunal entirely reject the damages sought by the Claimant.679 Mr. Dapena, the Respondent’s quantum expert, considers that the Claimant’s claim for compensation is based on allegedly unpaid invoices that lack sufficient “evidentiary support allowing to treat such invoices as enforceable debt”.680 Mr. Dapena further disputes the artificially high compound interest rate in U.S. dollars applied by Mr. Dellepiane, which “would compensate for hypothetical risks that do not exist.”681 Mr. Dapena concludes that “there is no economic, financial or accounting reason to award compensation to Claimant.”682 However, in the event that compensation is to be awarded, Mr. Dapena presents a “Quantitative Model”, which estimates the Claimant’s damages as at 31 October 2020 as either ARS 17,931,118 or USD 7,449,296.683
407. The Claimant submits that the Respondent is under an obligation to fully compensate the Claimant for its alleged breaches of the Treaty and for the alleged loss caused by such breaches.684 The Claimant relies on Articles 31, 35 and 36 of the ILC Articles, as well as the Chorzów Factory case, where the PCIJ held that “reparation must, as far as possible, wipe out all the consequences
676 Statement of Claim, para. 206; Reply, para. 171. ↩
677 First Dellepiane Report; Second Dellepiane Report. ↩
678 Second Dellepiane Report, para. 75. ↩
679 Statement of Defence, para. 479; Rejoinder, para. 18. ↩
680 First Dapena Report, para. 18; Second Dapena Report, para. 16. ↩
681 First Dapena Report, para. 18. ↩
682 Second Dapena Report, paras. 21, 213. ↩
683 Second Dapena Report, Valuation Model, “Calculation” tab (Dapena-47). ↩
684 Statement of Claim, para. 205; Reply, para. 171. ↩
[Page 138]
of the illegal act and re-establish the situation which would, in all probability, have existed if that act had not been committed.”685
408. The Claimant submits that a total sum of USD 11,039,635.28 remains unpaid in respect of the Claimant’s invoices for ordinary and special services. This amount is composed of the following amounts in respect of each of the Claimant’s claims:
a) USD 4,538,571.58 in respect of amounts exceeding the 10% Fee [Cap];
b) USD 3,375,289.01 in respect of invoices wrongfully pesified by Argentina;
c) USD 90,703.01 in respect of Argentina’s wrongful application of [Decree] 1060/01; and
d) USD 3,035,071.68 in respect of Special Services performed by the Claimant.686
409. In addition, the Claimant claims damages “equivalent to the costs incurred (and yet to be incurred) by the Claimant in connection with the Argentine court proceedings which the Claimant was required to bring pursuant to Article 8 of the BIT before being able to commence these arbitral proceedings” which amounted to USD 210,884.40 as at 16 December 2015.687
410. The Claimant notes that the validity of the invoices in dispute is a legal question, and therefore not for Respondent’s quantum expert, Mr. Dapena, to opine on.688 The Claimant further avers that “[a] legal finding that liability has occurred and that that sum is due cannot be reversed by reference to an economic interpretation of the Contract.”689 In any event, the Claimant maintains that it has already demonstrated its legal right to the amounts sought under Argentine law and the Treaty, and that “Argentina’s withholding of those sums caused the Claimant a direct loss corresponding to the amounts withheld by Argentina.”690
411. Without prejudice to its position that it has not failed to comply with its obligations under the Treaty, the Respondent argues that the Claimant’s monetary claim does not satisfy the general
685 Statement of Claim, paras. 203-205; Reply, paras. 172-173, referring to Factory at Chorzów (Claim for Indemnity) (Germany v. Poland), Judgment (Merits), 13 September 1928, PCIJ Series A, No. 17 (1928), 40, para. 125 (CLA-56). ↩
686 Second Dellepiane Report, para. 70; Statement of Claim, para. 209; First Dellepiane Report, para. 38. ↩
687 Statement of Claim, paras. 213-214. ↩
688 Reply, paras. 175-176; Hearing Tr., Day 7 (14 April 2021), 1079:16-1084:7. ↩
689 Hearing Tr., Day 7 (14 April 2021), 1080:4-7. ↩
[Page 139]
principles applicable to determining damages.691 The Respondent outlines the following four requirements for State liability for compensation to arise as a result of unlawful behaviour:
a) the existence of duly evidenced, ascertained damage;
b) the possibility of legally attributing the behaviour to the State;
c) the existence of a causal link between the State’s behaviour and the damage claimed; and
d) the lack of consistent service in an irregular action or omission by the State.692
412. Applying the above-mentioned criteria to this case, the Respondent submits that the Claimant has failed to demonstrate the existence of ascertainable damage or a causal link between the conduct of Argentina and the alleged damage.693
413. First, the Respondent submits that every month of audit services performance was duly paid for.694 The Respondent states that, as explained by Mr. Dapena, out of the total amount claimed by the Claimant “approximately 59% is directly for amounts claimed under invoices submitted in January 2002 [...] The remaining 41% is mainly for items indirectly related to January 2002 billing, in connection with the alleged pesification and the application of Presidential Decree No. 1060/01.”695 The Respondent submits that these invoices were submitted once Decree 477/97 had expired and they deviated from the agreed provisions and criteria, and were therefore justifiably rejected.696
414. Second, the Respondent submits that there is no evidence of the existence of an outstanding debt. The Respondent, citing Mr. Dapena, states that “[t]he mere existence of an invoice does not mean there is an enforceable debt.”697 In this regard, the Respondent contends that notwithstanding the former, Mr. Dellepiane did not independently verify the invoices provided by the Claimant.698 Furthermore, the Respondent points out that this was confirmed by ICS’s external auditor, who justifiably raised questions about the alleged debts which led to corrections to ICS’s financial
692 Statement of Defence, para. 488. ↩
693 Statement of Defence, paras. 490-498; Rejoinder, paras. 328-329; Hearing Tr., Day 1 (6 April 2021), 65:23-66:6. ↩
694 Statement of Defence, paras. 499-503. ↩
695 Statement of Defence, para. 505; Rejoinder, para. 335; Dapena Second Report, paras. 67-68; Hearing Tr., Day 1 (6 April 2021), 117:16-119:1; Hearing Tr., Day 7 (14 April 2021), 1153:19-1159:18. ↩
697 Statement of Defence, para. 506; Rejoinder, para. 360; Hearing Tr., Day 1 (6 April 2021), 119:11-123:9. ↩
698 Statement of Defence, para. 481; Hearing Tr., Day 5 (12 April 2021), 711:1-15. ↩
[Page 140]
statements.699 In relation to the claims concerning the 10% Fee Cap, the Respondent contends that it is impossible to check the accuracy of the amounts the Claimant alleges it is entitled to as the Excel tables that the Claimant’s expert relied on to make this calculation did not form part of the monthly reports sent to the Committee.700
415. Third, the Respondent explains that ICS’s branch operated in Pesos and had no significant assets.701
416. Fourth, the Respondent submits that the Claimant’s claim for “special services” is manifestly inadmissible.702 In particular, the Respondent objects that (i) the amounts accrued in Pesos;703 (ii) the Claimant wrongly included tax items;704 (iii) the Claimant has not proven that its alleged costs for special services fell outside the scope of ordinary audit services for which ICS has already received its fees;705 and (iv) the Claimant has not proven that the amounts invoiced were in accordance with market values.706 The Respondent underlines that the average fees the Claimant seeks for the alleged special services (24.73% margin) is higher than those considered by Mr. Santamaría to by customary (15-20% margin).707
417. In any event, should the Tribunal award any damages to the Claimant, the Respondent argues that any such sums and calculations should be denominated in Pesos.708 The Respondent contends that the Claimant’s claim for compensation in U.S. dollars lacks any support.709 To the contrary, the Respondent argues that the fact that the Claimant issued invoices in Pesos and that it
699 Statement of Defence, paras. 508-512, 519; Rejoinder, paras. 364-369. ↩
700 Hearing Tr., Day 7 (14 April 2021), 1159:21-1160:11 ↩
701 Statement of Defence, para. 517; Rejoinder, paras. 354-356; Second Dellepiane Report, para. 44. ↩
702 Rejoinder, paras. 338-352; Hearing Tr., Day 1 (6 April 2021), 124:2-23; Hearing Tr., Day 6 (13 April 2021), 887:6-15. ↩
704 Rejoinder, paras. 344-345; Hearing Tr., Day 7 (14 April 2021), 1164:1-20, 1169:2-1171:11. ↩
705 Rejoinder, paras. 351-352; Hearing Tr., Day 7 (14 April 2021), 1163:13-22, 1164:21-1168:1. ↩
706 Rejoinder, paras. 349-350; Hearing Tr., Day 7 (14 April 2021), 1168:2-1169:1. ↩
707 Hearing Tr., Day 7 (14 April 2021), 1168:2-11; First Santamaría Statement, para. 41; Hearing Tr., Day 5 (12 April 2021), 726:7-727:20, 728:18-729-22. ↩
708 Statement of Defence, paras. 523-526; Rejoinder, paras. 380-382; Hearing Tr., Day 1 (6 April 2021), 123:10-124:1; Hearing Tr., Day 7 (14 April 2021), 1160:12-22. ↩
709 Hearing Tr., Day 1 (6 April 2021), 123:10-124:1. ↩
[Page 141]
performed its services in Argentine territory confirms that any compensation awarded to the Claimant should be denominated in Pesos.710
418. Moreover, the Respondent argues that the Claimant has failed to explain why it was entitled to U.S. dollar fees for the special services and the reductions applied pursuant to Decree 1060/01.711 The Respondent asserts, on the one hand, that 90% of the costs the Claimant alleges were incurred in connection with the special services were declared as incurred in Argentina.712 On the other hand, the Respondent contends that the 13% reduction under Decree 1060/01 was implemented through credit notes that were issued by the Claimant in Pesos.713
419. The Claimant submits that:
a) pre-award interest is required to ensure full reparation of the Claimant;
b) pre-award interest should be calculated by reference to weighted average cost of capital (“WACC”); and
c) compound interest should be applied.714
420. The Respondent disputes that the Claimant is entitled to any pre-award interest.715 The Respondent disagrees with calculating pre-award interest by reference to WACC, as well as the application of compound interest.716
421. In the Respondent’s view:
a) if the Tribunal decides to award interest, any potential calculation should be made in Pesos and calculated at the “lending rate published by the Banco de la Nación
710 Hearing Tr., Day 1 (6 April 2021), 123:10-18; Hearing Tr., Day 7 (14 April 2021), 1171:19-1174:11; Hearing Tr., Day 3 (8 April 2021), 460:22-461:2. ↩
711 Hearing Tr., Day 7 (14 April 2021), 1161:1-1162:12. ↩
712 Hearing Tr., Day 7 (14 April 2021), 1161:14-63. ↩
713 Hearing Tr., Day 7 (14 April 2021), 1161:24-1165:12. ↩
715 Statement of Defence, VII.E. ↩
[Page 142]
Argentina; or alternatively the borrowing rate published by the Banco de La Nación Argentina, that is a rate [...] frequently used by the Argentine courts”.717
b) if the Tribunal decides to use dollars, which the Respondent objects to, a short-term risk-free interest rate should be applied.718
c) Regardless of the currency used, simple interest should be applied.719
422. Relying on Article 38 of the ILC Articles as well as arbitral practice,720 the Claimant submits that the principle of full compensation requires pre-award interest to be awarded in cases where damages are assessed as at a date in the past.721
423. In the Claimant’s view, the long period of time elapsed means that pre-award interest is “crucial” in order to ensure full reparation of the Claimant.722 For instance, the Claimant indicates that in Santa Elena v. Costa Rica “almost 22 years had passed between the date of the wrongful act and the arbitration award, pre-award interest made up most of the total damages awarded.”723
717 Statement of Defence, paras. 533, 543. ↩
718 Rejoinder, para. 384(c). ↩
719 Rejoinder, para. 384(d). ↩
720 Reply, paras. 183-184; SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, paras. 183-184 (CLA-54); Crystallex International Corporation v. Bolivarian Republic of Venezuela, ICSID Case No. ARB(AF)/11/2, Award, 4 April 2016, para. 932 (RLA-238). ↩
721 Reply, paras. 181-182; Hearing Tr., Day 1 (6 April 2021), 66:14-67:4. ↩
722 Reply, paras. 185-186; Compañía del Desarrollo de Santa Elena S.A. v. Republic of Costa Rica, ICSID Case No. ARB/96/1, Award, 17 February 2000, paras. 95, 107 (RLA-262); Ioannis Kardassopoulos v. The Republic of Georgia, ICSID Case No. ARB/05/18, and Ron Fuchs v. The Republic of Georgia, ICSID Case No. ARB/07/15, Award, 3 March 2010, paras. 645, 665, 668 (CLA-143); Tenaris S.A. and Talta - Trading e Marketing Sociedade Unipessoal Lda. v. Bolivarian Republic of Venezuela, ICSID Case No. ARB/11/26, Award, 29 January 2016, paras. 571, 594 (CLA-204); Marvin Roy Feldman Karpa v. United Mexican States, ICSID Case No. ARB(AF)/99/1, Award, 16 December 2002, para. 205 (RLA-204). ↩
723 Reply, para. 185; Compañía del Desarrollo de Santa Elena S.A. v. Republic of Costa Rica, ICSID Case No. ARB/96/1, Award, 17 February 2000, paras. 95, 107 (RLA-262); Hearing Tr., Day 1 (6 April 2021), 67:14-22. ↩
[Page 143]
424. The Respondent argues that due to the Claimant’s delay in commencing the arbitration, interest should be excluded.724 The Respondent states that the conduct of the Parties, and in particular the timely commencement of an arbitration, may be taken into account in determining interest.725 The Respondent cites an example from the International Law Commission (“ILC”) and case law where interest was not awarded based on the conduct of the Parties, so as to prevent a claimant from benefitting from its own delay.726
425. The Respondent also contends that the Claimant’s interest claim is “completely disproportionate”, as it would increase the underlying claim by more than 21 times.727
426. The Claimant argues that the most appropriate rate of interest is its own WACC, citing Mr. Dellepiane’s report, ConocoPhillips v. PDVSA, and financial literature in support of this approach.728 The Claimant views the WACC as a “conservative approach”, seeing as Mr. Dellepiane observed “that the amount of pre-award interest calculated by reference to the Claimant’s WACC is in fact lower than Argentina’s cost of borrowing over the same period.”729
427. The Claimant objects to the short-term risk-free interest rate proposed by the Respondent, as it would “go against the well-established notion of risk and return and would not compensate the
724 Rejoinder, paras. 385-390; Hearing Tr., Day 1 (6 April 2021), 125:20-126:16. ↩
726 Statement of Defence, paras. 536-537, 540; Rejoinder, paras. 385-388; Papel del Tucumán v. Argentina, ICC Case No. 12364/ KGA/CCO/JRF/CA/ASM/JPA, Award, 5 March 2019, paras. 132-138 (RLA-261); Antoine Goetz et al. v. Republic of Burundi, ICSID Case No. ARB/01/2, Award, 21 June 2012, para. 302 (RLA-296); Hearing Tr., Day 1 (6 April 2021), 126:3-12; Draft Articles on Responsibility of States for Internationally Wrongful Acts with commentaries (2001), commentary to Article 38, para. 7 (RLA-84). ↩
727 Statement of Defence, paras. 527, 531; Rejoinder, para. 319; Hearing Tr., Day 1 (6 April 2021), 124:24-125:19. ↩
728 Statement of Claim, para. 211; Reply, paras. 188-193; Phillips Petroleum Company Venezuela Limited and ConocoPhillips Petrozuata B.V. v. Petróleos de Venezuela, S.A., ICC Case No. 16848/JRF/CA (C-16849/JRF), 17 September 2012, para. 295(ii) (CLA-206); S. Escher and K. Krueger, The Cost of Carry and Prejudgment Interest, 6 Litigation Econ. Rev. 12 (2003), p. 15 (CLEX-22); J. J. Gotanda and T. J. Sénéchal, 2009, Interest as Damages. Columbia Journal of Transnational Law, Volume 47:491-536 (CLEX-21); Hearing Tr., Day 7 (14 April 2021), 1086:6-1088:22. ↩
[Page 144]
Claimant for the risks it was exposed to”.730 However, in the event the Tribunal were to apply a risk-free rate, the Claimant submits that it should apply a 10-year U.S. T-Bond rate.731
428. The Claimant also objects to computing pre-award interest in Pesos according to the rate published by Banco de la Nación Argentina, since it insists that compensation is due in USD, and the interest rate should match the applicable currency.732
429. The Respondent submits that any damages should be calculated in Pesos and, consequently, that interest should be calculated using a peso-denominated rate, such as the lending rate published by the Banco de la Nación Argentina or the borrowing rate used by the Argentine courts.733 The Respondent underscores that the former rate was used by AFIP to pay interests to the Claimant when there was delay in the payment of its fees.734
430. The Respondent submits that, if any damages should be calculated in U.S. dollars, a short-term risk-free rate should be applied, such as the six-month or one-year Unites States Treasury Bond rate.735 The Respondent argues that the WACC is a “forward looking rate of return”, and therefore inappropriate.736 The Respondent contends that the use of a short-term risk-free rate is backed by international arbitration case law.737
730 Reply, paras. 195-197; Second Dellepiane Report, paras. 11, 47; Hearing Tr., Day 1 (6 April 2021), 68:14-25. ↩
731 Hearing Tr., Day 7 (14 April 2021), 1088:23-1089:20. ↩
732 Reply, para. 198; Second Dellepiane Report, para. 40; Hearing Tr., Day 1 (6 April 2021), 69:17-21; Hearing Tr., Day 7 (14 April 2021), 1090:9-13. ↩
733 Rejoinder, paras. 384(b), 410-419. ↩
734 Hearing Tr., Day 1 (6 April 2021), 129:22-130:11. ↩
735 Rejoinder, paras. 384(c), 426; Hearing Tr., Day 1 (6 April 2021), 130:12-131:11. ↩
736 Statement of Defence, para. 532; Dapena First Report, para. 85; Rejoinder, para. 421; Hearing Tr., Day 1 (6 April 2021), 131:12-132:11; Total S.A. v. Argentine Republic, ICSID Case No. ARB/04/1, Award, 27 November 2013, para. 256 (RLA-284). ↩
737 Statement of Defence, para. 534; Rejoinder, para. 422; Total S.A. c. República Argentina, ICSID Case No. ARB/04/1, Award, 27 November 2013, para. 256 (RLA-284); Sistem Mühendislik İnşaat Sanayi ve Ticaret A Ş v. Republic de Kyrgyzstan, ICSID Case No.ARB(AF)/06/1, Award, 9 September 2009, para. 194 (RLA-298). ↩
[Page 145]
431. The Claimant submits that pre-award interest should be applied on an annual, compound basis, as simple interest would be inconsistent with “fundamental economic principles” and “the mechanics of real-world transactions.”738 According to the Claimant, compound interest is now the “rule rather than the exception”, whereas simple interest has been rejected by modern tribunals as “overly simplistic and arbitrary”.739
432. The Respondent argues that only simple interest, if any, should be applied.740 The Respondent states that international law and Argentine law provide for the application of simple interest as a rule, unless there are special circumstances which are not present here.741 In this respect, the Respondent refers to the commentary to the ILC Articles,742 decisions of former investment treaty tribunals,743 Article 623 of Argentina’s Civil Code and Article 770 of Argentina’s Civil and Commercial Code.744
738 Reply, paras. 201, 207; Hearing Tr., Day 1 (6 April 2021), 69:1-16. ↩
739 Reply, paras. 202-206; Hrvatska Elektroprivreda d.d. v. Republic of Slovenia, ICSID Case No. ARB/05/24, Award, 17 December 2015, paras. 555-556 (CLA-213); Compañia del Desarrollo de Santa Elena S.A. v. Republic of Costa Rica, ICSID Case No. ARB/96/1, Award, 17 February 2000, para. 104 (RLA-262); Hearing Tr., Day 7 (14 April 2021), 1089:21-1090:8. ↩
740 Statement of Defence, para. 536; Rejoinder, para. 384(d). ↩
741 Statement of Defence, paras. 536-537; Rejoinder, paras. 398-405. ↩
742 Hearing Tr., Day 1 (6 April 2021), 126:20-127:8; Draft Articles on Responsibility of States for Internationally Wrongful Acts with commentaries (2001), commentary to Article 38 (RLA-84). ↩
743 Hearing Tr., Day 1 (6 April 2021), 127:9-18; Franck Charles Arif v. Moldova, ICSID Case No. ARB/11/23, Award, 8 April 2013, paras. 617, 619 (CLA-74, RLA-263); SGS Société Générale de Surveillance S.A. v. The Republic of Paraguay, ICSID Case No. ARB/07/29, Award, 10 February 2012, para. 187 (CLA-54); Occidental Exploration and Production Company v. Republic of Ecuador, LCIA Case No. UN3467, Final Award, 1 July 2004, para. 217 (CLA-17); Marvin Roy Feldman Karpa v. United Mexican States, ICSID Case No. ARB(AF)/99/1, Award, 16 December 2002, para. 206 (RLA-204). ↩
744 Argentine Civil Code, 25 September 1869, Article 623 (R-27); Argentine Civil and Commercial Code, 1 August 2015, Article 770 (R-26). ↩
[Page 146]
433. The Tribunal has held above that the Claimant was entitled to the amounts claimed as remuneration under the Contract, with the exception of the payment claimed on account of certain alleged Special Services and a discount on account of defective proof. The breach of this payment obligation, the Tribunal has also held, entailed a violation of the Umbrella Clause of Article 2(2) of the Treaty. The Claimant has further provided prima facie evidence of the loss attributable to the Respondent’s breaches of the Umbrella Clause, consisting of the invoices and underlying documentation submitted contemporaneously to the Respondent. The Respondent has not, under the circumstances, cast any substantial doubt on the conformity of such claimed remuneration in accordance with the Contract and Argentine law, taking into account the aforementioned holdings with respect to the Claimant’s entitlements.
434. Accordingly, four categories of principal amounts are due, namely those on account of the wrongful application of (i) pesification, (ii) the 10% Fee Cap, (iii) Decree 1060/01, and (iv) Resolution 1106/98 (regarding non-payment for Special Services). Mr. Dellepiane summarizes all four heads of damages in his first report,745 and they are later adjusted with respect to two invoices to a total of USD 11,039,635.28.746
435. This amount includes USD 3,035,071.68 for the Special Services. The Tribunal has, however, dismissed the claims for the following alleged Special Services:
745 First Dellepiane Report, para. 98. ↩
746 Second Dellepiane Report, para. 70; Hearing Tr., Day 5 (12 April 2021), 755:20-757:10. ↩
[Page 147]
436. The Tribunal has further discounted the remainder of the amounts claimed for Special Services on account of defective proof. The amounts due for the Special Services, in accordance with the Tribunal’s analysis above is therefore as follows:
| Special Service | Total Amount Due (USD) |
|---|---|
| “Banana Imports into Argentina” | 29,111.26 |
| “Analysis of Deficiencies Detected in the Issue of the CIPI” | 38,832.35 |
| “Temporary Imports Study” | 450,374.61 |
| “Report on Iquique (Chile), Colonia and Montevideo, Uruguay Free Zone” | 57,519.06 |
| “Brazil Imports, October - December 1998 and January 1999” | 233,017.86 |
| “Imports Chapter 30, October - December 1998 and January 1999” | 167,307.94 |
| “Kiwi Imports Study” | 20,075.77 |
| “Colonia Uruguay Free Zone Report” | 17,679.77 |
| “Report regarding Compliance with CEPIPI Article 2, provision No. 4” | 214,762.24 |
| “Analysis of Imports among Related Companies” | 371,989.35 |
| “Iquique 2 Report” | 21,435.23 |
| “Satellite Antenna Report” | 44,721.75 |
| TOTAL | 1,656,827.20 |
437. The new total for the Special Services thus reduces the total principal amount due to USD 9,661,390.80.
438. Additionally, the Claimant claims damages in connection with the costs incurred in the Argentine court proceedings which the Claimant was forced to bring pursuant to Article 8 of the BIT before being able to commence these arbitral proceedings. However, the Tribunal notes that, even if the requirement to bring an Argentine court action imposed significant costs upon the Claimant, it was in conformity with the terms of the BIT rather than in breach thereof. It does not result from wrongful conduct by the Respondent that would give rise to a right of compensation. This claim is therefore dismissed.
[Page 148]
439. The principal remaining point of difference between the Parties as to the quantum of compensation due concerns pre-award interest. Article 38 of the ILC Articles, concerning “Interest”, reads as follows:
1. Interest on any principal sum due under this chapter shall be payable when necessary in order to ensure full reparation. The interest rate and mode of calculation shall be set so as to achieve that result.
2. Interest runs from the date when the principal sum should have been paid until the date the obligation to pay is fulfilled.
440. The Respondent has objected to granting pre-award interest on the basis of the Claimant’s conduct, and in particular the delay in commencing this arbitration. However, to the extent that the Tribunal’s holdings on the Respondent’s preliminary defences do not dispose of this argument, the Tribunal finds that none of the circumstances of the present case warrant departing from the inclusion of pre-award interest as part of full reparation under Article 38 of the ILC Articles.
441. Whether the Respondent is liable to pay interest, and at what rate, is governed by international law because the amounts due for the Claimant’s auditing activity are replaced by a liability to compensate Claimant for the damage caused by Respondent’s breach of its obligation under the Umbrella Clause of the BIT to comply with its obligations under the Contract.
442. The BIT does not contain any agreement as to the type or rate of interest owed for late payment of monetary obligations by the State party. The late-payment interest paid by AFIP to the Claimant was calculated at a statutory rate set by the State, not agreed between the Parties to the Contract or to the BIT.747
443. Among the various interest rates advocated by the Parties, a basic distinction needs to be made between two kinds of interest. One is statutory interest, which becomes due automatically at a flat
747 Second Dapena Report, para. 56. ↩
[Page 149]
rate once an obligation to pay becomes overdue, without requiring proof of any specific damage; both rates primarily advocated by the Respondent under Argentine law belong to this category of interest, i.e., the lending rate published by Banco de la Nación Argentina, pursuant to AFIP regulations, or the borrowing rate applied by the Argentine courts.748
444. The other kind of interest is compensatory, i.e., based on liability for the damage caused by non-payment. The relief sought then forms part of the damages arising from the liability under international law to repair the particular damage caused by the breach of the Umbrella Clause of Article 2(2) of the Treaty. This liability requires proof of the damage that compensatory interest is asserted to compensate; the interest rates advocated by the Claimant belong to this category.
445. Pursuant to Article 38(1) of the ILC Articles, compensatory interest is owed “when necessary in order to ensure full reparation”, and “[t]he interest rate and mode of calculation shall be set so as to achieve that result”.
446. Within compensatory interest, a further legal distinction needs to be made according to the kind of damage to be proven in order to be compensated. On the one hand, interest can compensate for lost profits or cost savings that the creditor would have made if the debt had been paid in a timely manner (lucrum cessans, opportunity cost). On the other hand, interest can compensate for an actual loss that the creditor has suffered due to the delay in payment (damnum emergens).
447. To justify the interest rates claimed, the Claimant and its quantum expert, Mr. Dellepiane, have relied on various arguments pertaining primarily to an opportunity cost. However, the Claimant has not proven a specific opportunity that it has lost, either in the form of a profit that it would have obtained from a reinvestment or in the form of savings that it would have made by reimbursing certain borrowings or improving its equity position, if the Respondent had timely paid the Claimant.
448. The Claimant advocates interest at the rate of its WACC in relation to the Contract, which is based on the cost of funds for the Claimant to invest in the business of imports auditing services in
[Page 150]
Argentina. According to the Claimant, this WACC “appropriately captures the expected return and cost of said funds for equity holders and debt holders financing comparable investments”.749
449. The WACC is arguably useful for discounting future cash flows to the date of the award, as it reflects the expected return and cost to the investor to finance a certain investment, as measured ultimately by the ex ante expectations of the investor’s funders. However, the Claimant’s WACC for an investment in information technology services in Argentina during the period from 2002 to the present is not relevant, given that the project was completed in 2001 and that there is no proof that the Claimant would have re-invested the unpaid amounts in the same activity in Argentina. The Claimant’s general WACC is not relevant either for the same conceptual reason.
450. The Claimant has also not proven an actual loss in the sense of having had to borrow all or part of the unpaid amounts to satisfy its obligations.750 However, the Respondent’s continuous non-payment of the amounts due has caused the Claimant no longer to be a paid contractor entitled to payment for his services, but to be instead placed into the position of an unsecured long-term lender of the State of Argentina without receiving the interest that such a lender is entitled to receive.
451. The Respondent’s breach of its promise to pay under the BIT caused this damage and makes Argentina liable under international law to compensate the Claimant for the interest the latter should have received, but did not receive, as an unsecured long-term lender to the State of Argentina. The damage represented by the loss of such interest is thus proven.
452. The principal amounts on which the Claimant is entitled to receive compensation for not having been paid interest are amounts in U.S. dollars. The unpaid amounts are amounts in U.S. dollars, albeit invoiced in Pesos after conversion at the time of invoicing, because the Claimant’s remuneration is calculated as a percentage of the Inspection Companies’ remuneration, which is
749 First Dellepiane Report, para. 43. ↩
750 The Claimant is not basing its claim for damages on the temporary transfer of its receivables to obtain financing, which occurred in 2001-2007. See Award on Jurisdiction, paras. 290-311. ↩
[Page 151]
calculated as a percentage of the import valuation as per the value of the shipments in foreign currency.751
453. Even if one were to consider that the currency of the invoice becomes the currency of the obligation upon conversion, the Respondent would be liable for any currency loss as a debtor in default once the amounts became overdue. From the time the Respondent failed to pay the amounts due, it was in default and would have to bear any subsequent currency risk, including the depreciation of the peso due to the Emergency Law and pesification of U.S. dollar-denominated debts.
454. Compensatory interest on a debt in dollars can only be calculated by a dollar interest rate because the damage caused by the non-payment is suffered in U.S. dollars.
455. The Respondent’s breach of its obligation to pay the principal amounts has placed the Claimant in the same position as a holder of Argentine sovereign long-term U.S. dollar bonds. In that position, the Claimant has been entitled to receive the interest payable on such bonds, not contractually on the basis of a bondholder agreement, but as a consequence of Respondent’s liability for its breach of the BIT.
456. The measure of compensation being full reparation for an internationally wrongful omission, the rate of compensatory interest must be such as to restore the Claimant into the same position as it would have been as such a bondholder. The Respondent is therefore liable to compensate the Claimant fully for the loss of such interest.
457. It is sufficient to look at the Argentine sovereign long-term U.S. dollar debt to find how much interest the Claimant was entitled to as, in effect, an unwilling bondholder for the unpaid amounts, which the Respondent in effect borrowed unlawfully from the Claimant. This is the interest that the Claimant should have received on the unpaid amounts, and the non-payment of which entitles the Claimant to an equivalent reparation.
458. Evidence on this point was presented by Mr. Dellepiane, who dealt with this kind of compensation as an alternative method to determine the damage caused, and the compensation owed, to the Claimant for the non-payment of the amounts due by the Respondent:
751 See supra paras. 259-272. ↩
[Page 152]
An alternative view of the risk faced by the funds withheld by Respondent, on the other hand, could be that they are no longer related to the industry risk, but instead they have become a (‘forced’ or ‘coerced’) loan unwillingly granted by Claimant to Respondent. Under this alternative view, the risk of those funds would be the risk of the Argentine Government not paying its debts. If Claimant’s funds were locked-up in a debt owed by the Government of Argentina, then the risk they face is comparable to that faced by holders of Argentine sovereign debt. Hence, the relevant interest rate would be Argentina’s borrowing cost instead of Claimant’s cost of capital. Argentina’s borrowing cost is observed in the debt capital markets, which show the interest rate (yield to maturity) on traded, US$ denominated, Argentine Government bonds. (citations omitted)752
459. To calculate that rate, Mr. Dellepiane adds up two components: the rate of interest on ten-year U.S. Treasury bonds and a differential to account for the country risk of Argentina. Argentina’s country risk can be derived from the bond spread as measured by:
Argentina’s cost of borrowing based on the Emerging Markets Bond Index (EMBI) of Argentina, which measures the differential between the yields of Argentina’s sovereign debt securities as compared to US debt securities with the same maturity. Argentina’s cost of borrowing is therefore given by the sum of the yield to maturity of US Treasury Bonds and the EMBI of Argentina. (citations omitted)753
460. Alternatively, Mr. Dellepiane uses a 4.5 percent risk premium (which he discusses in the context of calculating a WACC) based on the fact that Argentina was rated mostly as a B1 country over the length of the Contract until the financial crisis and as such carried a country risk premium of approximately 4.5 percent.754
461. The Tribunal will use the rates of the 10-year US Treasury bonds,755 plus the Emerging Market Bond Index (“EMBI”) for the differential as being the empirically more precise evidence in the record.756
462. A further question is whether the interest rate should be: (i) the rates having existed each year during the period that the amounts remained unpaid; (ii) the average of these rates during this period; or (iii) the median of these rates during this period.757
463. The year-to-year and the average rates are not the most appropriate rates because, unlike bonds issued by the Respondent, the latter’s debt of reparation owed to the Claimant did not have a
752 First Dellepiane Report, para. 46. ↩
753 First Dellepiane Report, para. 58; Second Dellepiane Report, para. 81. ↩
754 Hearing Tr., Day 5 (12 April 2021), 668:21-669:7. ↩
755 See Ten-year Constant Maturity – US Securities yield data from the Federal Reserve Bank (CLEX-38). ↩
756 See Financial Times, Definition of EMBI (CLEX-24). ↩
757 Mr. Dellepiane correctly calculates the median rate as follows: “The median is the middle value in a given sequence of numbers ordered from lowest to highest, taken as the average of the two middle numbers when the sequence has an even number of values” (First Dellepiane Report, fn. 6). ↩
[Page 153]
specific maturity date, it was not known when it would be repaid, it has remained unpaid for over twenty years, and during this period the Respondent’s cost of borrowing varied widely, between a maximum of 61.9 percent758 and 6.4 percent.
464. The median rate is more appropriate, for the same reasons that Mr. Dellepiane explained in relation to using the median WACC rate. He further explained at the hearing (in relation to the WACC) that it was appropriate to use the median rate, as follows:
And so, in order to soften that or to actually mitigate entirely, I should say, the effect of that financial crisis, I’ve taken the median of 17 percent which is substantially lower than the average between all these numbers. The median is, as you’ll recall the midpoint in the central part of the distribution of all these numbers. The average [of Claimant’s WACC for its investment in the auditing services] would have been 23.5 percent, the median was 17 percent. That is the number that I have used for the base case damages because I believe that it actually captures all the risks and all the exposure that Claimant had to its funds stranded in Argentina.759
465. These reasons are just as valid when the reparation is measured, not by the WACC, but by reference to the Respondent’s cost of borrowing.
466. The Claimant, based on Mr. Dellepiane’s reports, stated that using its WACC yields a lower amount of damages than the Respondent’s cost of borrowing.760 The Claimant reiterated this argument during its closing at the hearing as follows:
Mr. Dellepiane has offered a variety of Risk Adjusted Rates to the Tribunal. Table 9 in his Second Report761 captures those, and it will come up on the screen at the moment. [...] You can see on this table that there are a variety of Cost of Capital approaches to Pre Award Interest, and virtually all of them, as you can see in the bottom line, are lower than the Respondent’s own average Cost of Debt. It will thus be cheaper for the Respondent to pay Pre Award Interest in this case according to a Risk Adjusted Rate in the first five options in this table than it would be for Argentina to have borrowed the same amount of money in 2001. This Tribunal should not incentivize a situation where a Respondent can profit from its breach by obtaining funds cheaper than its own borrowing rate.762
467. However, this comparison was biased. Using the Claimant’s median WACC rate of 17.0 percent obviously produces a higher amount of damages than if Respondent’s median cost of borrowing of 12.5 percent is used. Mr. Dellepiane made his comparison between the median WACC rate
758 This was when Argentina was facing a debt default in 2002 until it issued new bonds in 2005 in exchange for the bonds on which it had defaulted; this swap was not accepted by all bondholders (First Dellepiane Report, fn. 47). ↩
759 Hearing Tr., Day 5 (12 April 2021), 666:23-667:11. ↩
760 Second Dellepiane Report, para. 82. ↩
761 Second Dellepiane Report, p. 43, Table 9 – WACC and Alternative Rates in USD for the period 1999-2020. ↩
762 Hearing Tr., Day 7 (14 April 2021), 1087:17-1088:22. ↩
[Page 154]
and the average (rather than the median) for the Respondent’s cost of borrowing, but he corrected his statement at the Hearing on the Merits.763
468. Using the Respondent’s median cost of borrowing in U.S. dollars during the period from 1999 to 2023 yields an interest rate of 12.8 percent:
10-year US Treasury bonds + EMBI
| Year | 10-Yr US T-Bond + EMBI |
|---|---|
| 1999 | 12.84% |
| 2000 | 12.73% |
| 2001 | 20.55% |
| 2002 | 61.87% |
| 2003 | 59.86% |
| 2004 | 56.50% |
| 2005 | 31.75% |
| 2006 | 8.18% |
| 2007 | 7.83% |
| 2008 | 12.21% |
| 2009 | 15.25% |
| 2010 | 10.11% |
| 2011 | 9.65% |
| 2012 | 11.69% |
| 2013 | 13.02% |
| 2014 | 10.41% |
| 2015 | 8.04% |
| 2016 | 6.59% |
| 2017 | 6.45% |
| 2018 | 8.39% |
| 2019 | 15.28% |
| 2020 | 23.24% |
| 2021 | 17.23% |
| 2022 | 24.70% |
| 2023 | 26.50% |
| Median | 12.8% |
| Average | 19.6% |
(Updated version by the Tribunal, Second Dellepiane Report, Table 2; Updated Compensation
Calculations (BRG-1))
763 During the Hearing on the Merits, Mr. Dellepiane corrected para. 82 of his Second Report: “at Paragraph 82 of my Second Report. It should say in the second sentence, where it says ‘using the median of Argentina’s cost of borrowing,’ it should instead say, ‘using the annual or yearly Argentina’s cost of borrowing’” (Hearing Tr., Day 5 (12 April 2021), 655:16-20). ↩
[Page 155]
469. Like sovereign bonds yielding coupon payments annually (or semi-annually), the yearly interest carried by the debt owed to the Claimant by the Respondent, when not paid, must be added to the principal each year. Compensatory interest due as reparation must therefore be compounded annually.
470. Respondent relies on Argentine ordre public against compounding,764 but while this rule may be mandatory in domestic situations, it is not part of international ordre public, and international law does not prohibit compounding in any event.
471. Interest runs from the dates when each unpaid amount became overdue, subtracting the credits to be applied at various times. The due date of each invoice is the day of its initial presentation (even when it was reissued later for the full correct amount due), plus 30 days (as per the Contract), plus an additional 7 days.765 Based on the evidence in the record, the Tribunal accepts the spreadsheet of Mr. Dellepiane for the due dates of the principal amounts, although not for the rates of interest to be applied.
472. Mr. Dellepiane’s updated spreadsheet contains the daily computation of the daily interest for each amount due, the quantum of which will have to be adjusted in accordance with the rate of interest determined by the Tribunal.766 Contrary to the Respondent’s concern, the Excel spreadsheet of Mr. Dellepiane does not compound interest daily. Instead, it calculates the daily interest and adds them up.767
473. The Respondent and its quantum expert stressed that the total compensation calculated by the Claimant ends up being more than twenty times the initial total unpaid principal amount, and is therefore unreasonable. However, an interest rate of 17.1 percent compounded annually, although high, is not necessarily unreasonable in the circumstances – and the interest rate arrived at by the Tribunal of 12.8 percent compounded annually is even more reasonable by comparison. Rather,
764 Hearing Tr., Day 1 (6 April 2021), 127:19-128:23. ↩
765 Hearing Tr., Day 5 (12 April 2021), 659:17-22 (“And the result of that yields the $11,039,635 of nominal unpaid amounts, and you notice here there is no date of this table because there is many dates. These are nominal and took place these amounts due are due as of different dates, some in 2000, some in 2001 and some in 2002”); Second Dellepiane Report, para. 64. ↩
766 See BRG Updated Compensation Calculations, Tab “Timeline” (BRG-01). ↩
767 Second Dellepiane Report, paras. 103-111. ↩
[Page 156]
it is the fact that the Respondent chose not to pay the amounts due during more than 20 years that yields a compensation that is a multiple of the unpaid principal amounts.
474. The Respondent also makes the point that the unpaid amounts are sums certain carrying no risk. It is true that the legal fiction is that, notwithstanding the dispute between the Parties, the amounts due are deemed to have been sums certain as of the time they were due according to the present award, which does not create the debt, but declares what the debt was and when it was due. The principal unpaid amounts owed to the Claimant are thus legally deemed to have been certain as from the time they became due.
475. The fact that the amounts were certain does not mean that no remuneration is due by the Respondent for using these funds, as the Respondent asserted, and that it has no liability for depriving the Claimant of this remuneration. The legal risk (of winning or losing the present arbitration) is, however, neither an excuse for the debtor not to have paid, nor a risk to be compensated to the creditor.
476. The Claimant seeks “(d) an order that Argentina pay post-Award interest on all sums awarded at the maximum permitted rate until payment in full”.
477. The ILC Articles make no distinction between pre-award and post-award interest. Article 38, paragraph 2, states that interest runs “until the date the obligation to pay is fulfilled”. There is no reason why the compensatory interest rate should be different in international law before and after the award is issued. Interest simply keeps running at the same rate as for pre-award interest.
478. If the Claimant’s prayer for relief is to be interpreted as seeking an order to pay a total amount, which would be compounded as from the time of the award (i.e. post-award interest would run on that amount), such relief would be denied, as Article 38 of the ILC Articles implies that the same continuous interest applies, and no basis is asserted for a distinction between pre-award and post-award interest. Nor does the Claimant’s request for relief require the Tribunal to calculate the exact amounts of interest. The Claimant concludes its Reply by requesting inter alia as follows:
For the reasons set out above, the Claimant seeks the following relief:
[...]
(b) damages for breach of the BIT as set out in Section (D) above;
[...]
[Page 157]
(d) an order that Argentina pay post-Award interest on all sums awarded at the maximum permitted rate until payment in full;
[...]768
479. The Tribunal therefore limits itself to an order that the Respondent pay the principal amount due, plus compound interest calculated at the median rate of the Respondent’s cost of borrowing as explained above.
768 See supra para. 43; Claimant’s Reply, para. 209. The statement of the “(b) damages for breach of the BIT as set out in Section (D)”, which runs from pages 66 to 77, contains a recapitulation regarding the principal amounts due plus pre-award interest at the rate of the Claimant’s WACC (the Respondent’s cost of borrowing) compounded annually. ↩
[Page 158]
480. The Claimant requests the Tribunal to order Argentina to pay all costs incurred in connection with the arbitration, including the costs of the Tribunal, the appointing authority, and the fees and expenses incurred by the Claimant, including legal fees, expert fees, and the costs of the time spent by the Claimant’s employees.769
481. The Respondent requests the Tribunal to order the Claimant to “pay for all costs and expenses arising from these arbitration proceedings, including the fees and expenses incurred by Argentina”.770
482. Pursuant to Article 40(1) of the UNCITRAL Rules, the Tribunal must “fix the costs of arbitration”. These costs include (i) the fees of the arbitral tribunal; (ii) the reasonable travel and other expenses incurred by the arbitrators; and (iii) fees and expenses of the PCA which has acted as the Registry. The Parties each made deposits to cover the abovementioned costs of the arbitration in the amount of USD 600,000. The costs of arbitration covered from such deposits, taking into account the Terms of Appointment agreed upon by the Parties, the Tribunal, and the PCA, are as follows:
| TRIBUNAL | USD 878,893.00 |
| PCA | USD 141,072.32 |
| OTHER EXPENSES (including court reporting, catering, courier expenses, IT/AV support, hearing facilities, interpretation, translation, travel, VAT, etc.) |
USD 180,034.68 |
| TOTAL | USD 1,200,000 |
[Page 159]
483. Following the issuance of this Award, the PCA shall issue a statement of account for the costs covered from the deposit in accordance with Article 43(5) of the UNCITRAL Rules.
484. Article 42(1) of the UNCITRAL Rules provides that: “[t]he costs of the arbitration shall in principle be borne by the unsuccessful party or parties. However, the arbitral tribunal may apportion each of such costs between the parties if it determines that apportionment is reasonable, taking into account the circumstances of the case.”
485. In this case, the Respondent’s objections to jurisdiction have been dismissed and the Claimant has prevailed on its Umbrella Clause claims. However, at the same time, almost half of its Special Services claims have been dismissed, and the remainder discounted on account of defective proof. Accordingly, pursuant to the discretion granted by Article 42(1) on the apportionment of costs, the Tribunal finds it reasonable that each Party bear its own legal and other costs, including their respective halves of the costs of the arbitration proceedings covered from the deposits made with the PCA.
[Page 160]
486. For the reasons stated in this Award, the Tribunal decides:
Place of arbitration: The Hague, The Netherlands
Date of Award: 29 April 2024
|
Signature Mr. Pierre-Yves Tschanz |
Signature Prof. Dr. Domingo Bello Janeiro |
Signature
Mr. Jernej Sekolec
Presiding Arbitrator