This summary note is machine-generated. Always consult the original materials.
Procedural Posture
This document is the final Award in the ICSID arbitration between Qatar National Bank (Q.P.S.C.) and the Republic of South Sudan and the Bank of South Sudan. The Award incorporates by reference the Tribunal’s earlier Decision on Jurisdiction and Liability dated 5 January 2024, in which the Tribunal upheld its jurisdiction, found the Respondents in breach of the 2018 Facility Agreement, and held them jointly and severally liable for damages. Following that Decision, the Tribunal directed the Parties to submit a joint calculation of the sums due under the Facility Agreement and updated submissions on costs.
Principal Legal and Procedural Issues
The primary issues addressed in this Award concern the final quantification of damages, the determination of applicable post-award interest, and the allocation of the costs of the arbitration. The Tribunal was tasked with reviewing the Parties' joint calculations to ensure they accurately reflected the Tribunal's prior rulings on the treatment of default interest penalties, the number of days of accrued interest, and the application of partial repayments made by the Respondents.
Parties' Positions and Tribunal's Findings
Pursuant to the Tribunal's directions, the Parties submitted a joint calculation of damages that adopted the Respondents' approach for the number of days of accrued interest, the Claimant's approach for partial payments, and the Claimant's approach for the default interest penalty. The Tribunal accepted these agreed figures as accurate for determining the compensation due. The Tribunal also determined that the Claimant was entitled to post-award interest calculated on the same basis as the pre-award default interest rate stipulated in the Facility Agreement.
Regarding the allocation of costs, the Claimant argued that as the successful party, it should recover its full legal fees and arbitration costs. The Respondents contended that the Tribunal should consider their ongoing efforts to repay the loan facility during the proceedings and requested that their own costs be awarded. The Tribunal adopted the "costs follow the event" principle, finding no reason to depart from the general approach that the prevailing party should be reimbursed for its reasonable costs. The Tribunal rejected the Respondents' argument that their continued loan repayments should mitigate their cost liability, noting that such payments merely fulfilled existing contractual obligations.
Operative Directions
The Tribunal ordered the Respondents, on a joint and several basis, to pay the Claimant USD 1,021,282,210 as of 5 May 2024, comprising the outstanding principal, accrued interest, and a management fee, less repayments made to date. The Tribunal further awarded post-award interest on this sum at a rate of 6% plus 2% plus the applicable USD 3-month LIBOR. Finally, the Tribunal ordered the Respondents to pay GBP 999,329.78 for the Claimant's legal representation costs and USD 266,427.68 for the Claimant's share of the ICSID arbitration costs.