This summary note is machine-generated. Always consult the original materials.
Procedural Context and Key Issues
This Procedural Order No. 5 addresses the Claimant's application to bifurcate the proceedings and the Respondent's corresponding opposition and alternative requests in an ICSID arbitration initiated under the Canada-Colombia Free Trade Agreement (FTA). The central issue before the Tribunal was whether to separate the determination of jurisdiction and liability from the quantification of damages, pursuant to ICSID Arbitration Rule 42.
The Parties' Respective Positions
The Claimant, Continental Gold Inc., requested bifurcation on the grounds that an evolving and unstable security situation at its mine made it impossible to present a complete and stable assessment of damages at this stage. It argued that bifurcation would promote procedural efficiency and is a common practice in ICSID arbitration.
The Respondent, the Republic of Colombia, opposed the application, contending it would be inefficient and would prolong the proceedings. Critically, Colombia argued that under Articles 819 and 820 of the FTA, a demonstration of loss or damage caused by an alleged treaty breach is a prerequisite to the Tribunal's jurisdiction. As the Claimant had not substantiated its damages, Colombia submitted that the Tribunal lacked jurisdiction. Colombia made several alternative requests, including an order compelling the Claimant to submit its full arguments on damages and causation.
The Tribunal's Analysis and Decision
The Tribunal first analyzed the jurisdictional argument advanced by the Respondent. It found that the language of the FTA suggests that the three elements of a claim—breach, damage, and causation—are constitutive for establishing jurisdiction on a prima facie basis. Accordingly, the Tribunal concluded that a preliminary presentation on damages and causation was necessary to ensure procedural fairness, enabling the Respondent to formulate its jurisdictional objections and the Tribunal to properly assess its jurisdiction.
Applying the criteria of ICSID Arbitration Rule 42(4) to the bifurcation request, the Tribunal determined that the Claimant had not met its burden. It found no certainty that bifurcation would reduce the time and cost of the proceeding. Furthermore, it held that the issues of damages and causation were inextricably linked to the questions of jurisdiction and liability under the specific terms of the FTA, militating against their separation. The Tribunal was not persuaded that the security situation completely prevented the Claimant from presenting at least a preliminary case on damages.
Operative Orders
The Tribunal rejected the Claimant's application for bifurcation. It ordered the Claimant to submit, within 60 days, an updated Memorial containing its allegations on damages and causation to the greatest extent possible under the current circumstances. If a full exposition is not possible, the Claimant must provide a well-founded explanation. The Tribunal affirmed the Claimant's right to update or modify its damages submissions at a later stage. The Tribunal deferred its decision on the Respondent's reservation of right to request summary dismissal and rejected all other pending requests, inviting the parties to agree on a revised procedural calendar.