Notice: We are currently performing maintenance to improve the italaw platform. The site remains fully accessible. Thank you for your patience.

NextEra Energy Global Holdings B.V. and NextEra Energy Spain Holdings B.V. v. Kingdom of Spain, Final Award

31 May 2019
NextEra Energy Global Holdings B.V. and NextEra Energy Spain Holdings B.V. v. Kingdom of Spain, ICSID Case No. ARB/14/11
Final Award
Document Details:
LISTED PARTICIPANTS
Final Award
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's law firm
Respondent's law firm
Other counsel
Claimant's expert
Claimant's expert firm
Respondent's expert
Respondent's expert firm
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Third-party funder
Country
Print reporter
Document Summary
Final Award
This summary note is machine-generated. Always consult the original materials.

Procedural Posture and Scope

This final Award, issued by an ICSID tribunal constituted under the Energy Charter Treaty (ECT), resolves the remaining issues of damages, interest, and costs in the arbitration between NextEra Energy Global Holdings B.V. and NextEra Energy Spain Holdings B.V. (Claimants) and the Kingdom of Spain (Respondent). The Award follows the Tribunal's Decision on Jurisdiction, Liability and Quantum Principles of 12 March 2019, which found that Spain had breached its fair and equitable treatment (FET) obligation under Article 10(1) of the ECT. This Award quantifies the final monetary relief owed to the Claimants.

Quantification of Damages and Interest

The Tribunal's primary task was to finalize the quantum of damages based on the principles established in its prior Decision. The Claimants submitted a recalculated damages claim of EUR 290.6 million, based on the Tribunal's formula of a return on the capitalized value of their assets using the WACC of the Termosol Plants plus a 200 bps premium. The Respondent did not contest the mathematical accuracy of this recalculation. Accordingly, the Tribunal accepted and awarded EUR 290.6 million as the principal amount of compensation.

A key issue was the determination of pre- and post-judgment interest. The Tribunal had previously ruled that interest would be based on the 5-year Spanish sovereign bond rate as at the date of the Award. However, observing that this rate was effectively zero at the time of rendering the Award, the Tribunal found that a zero-interest award would be inconsistent with its finding that interest was appropriate. To resolve this, the Tribunal decided to apply the 5-year Spanish sovereign bond rate that was in effect at the date of its earlier Decision on Principles, which was 0.234%. It ordered that pre-judgment interest be applied at this rate from the valuation date (30 June 2016) to the date of the Award, and that post-judgment interest accrue at the same rate on all awarded sums until full payment.

Allocation of Costs

Pursuant to Article 61(2) of the ICSID Convention, the Tribunal exercised its discretion to allocate the costs of the proceeding and the parties' legal expenses. The Tribunal noted that while the Respondent lost on jurisdiction and the merits, its jurisdictional arguments were not trivial, and the Claimants' primary basis for assessing damages had been rejected. This mixed outcome warranted a partial allocation of costs. The Tribunal ordered the Respondent to bear two-thirds of the costs of the proceeding and one-third of the Claimants' legal and expert fees. The Award directs Spain to pay the Claimants USD 132,368.86 for its share of the proceeding costs and a further USD 4,147,031.81 plus EUR 1,042,135.3 for its share of the Claimants' costs.