Notice: We are currently performing maintenance to improve the italaw platform. The site remains fully accessible. Thank you for your patience.

9REN Holding S.a.r.l v. Kingdom of Spain, Award

31 May 2019
9REN Holding S.a.r.l v. Kingdom of Spain, ICSID Case No. ARB/15/15
Award (English)
Award (Spanish)
Document Details:
LISTED PARTICIPANTS
Award (English)
Award (Spanish)
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's law firm
Respondent's law firm
Other counsel
Claimant's expert firm
Respondent's expert firm
Claimant's witness
Respondent's witness
Other witnesses
Tribunal assistant
Third-party funder
Country
Print reporter
Document Summary
Award (English)
Award (Spanish)
This summary note is machine-generated. Always consult the original materials.

Procedural Posture and Jurisdictional Findings

This document is the final award of an arbitral tribunal constituted under the auspices of the International Centre for Settlement of Investment Disputes (ICSID) in the case of 9REN Holding S.à.r.l. v. The Kingdom of Spain (ICSID Case No. ARB/15/15). The dispute arose from Spain's reforms to its renewable energy regulatory framework under the Energy Charter Treaty (ECT).

The Tribunal first addressed Spain's jurisdictional objections. Spain argued that, as an intra-EU dispute, the matter was outside the Tribunal's competence following the European Court of Justice's decision in Achmea. It also raised objections based on the ECT's denial of benefits clause (Article 17), the Claimant's indirect shareholding structure (the "corporate pyramid" objection), and the carve-out for taxation measures (Article 21) concerning Spain's 7% tax on electricity production (the "TVPEE"). The Tribunal unanimously dismissed all jurisdictional objections. It distinguished Achmea on the grounds that the ECT is a multilateral treaty to which the EU itself is a party. It further found that the Claimant conducted substantial business activities in Luxembourg, rejecting the denial of benefits claim, and affirmed its jurisdiction over claims by an indirect shareholder. While finding the TVPEE to be a tax measure, the Tribunal declined jurisdiction over claims related to it under the FET standard, citing the ECT's taxation carve-out.

Findings on Liability

On the merits, the Tribunal unanimously held that Spain had breached its obligation to accord Fair and Equitable Treatment (FET) under Article 10(1) of the ECT. The central issue was whether Spain's regulatory changes frustrated the Claimant's legitimate expectations. The Tribunal found that Spain's Royal Decree 661/2007, particularly its explicit "grandfathering" clause in Article 44(3), created a specific and clear representation of regulatory stability for the feed-in tariff (FIT) regime. This representation induced the Claimant's investment of €211 million in Spanish photovoltaic (PV) projects.

The Tribunal concluded that Spain's subsequent measures between 2010 and 2014, which dismantled the original FIT scheme and replaced it with a new regime based on a "reasonable rate of return," fundamentally altered the stable framework on which the Claimant had reasonably relied. This frustration of the Claimant's legitimate expectations constituted a violation of the FET standard. However, the Tribunal found that a later decree, RD 1578/2008, under which one of the Claimant's eight plants was registered, did not contain the same stability guarantee. The Tribunal dismissed the Claimant's claims for expropriation and breach of the umbrella clause.

Quantum, Costs, and Relief

By a majority, the Tribunal assessed the quantum of compensation at €41.76 million as of 30 June 2014. This amount was based on a discounted cash flow (DCF) analysis but included a 20% reduction from the Claimant's asserted loss of €52.2 million to account for various contingencies, including the lack of a stability guarantee for one plant and adjustments for operating life, illiquidity, and regulatory risk. The Tribunal ordered Spain to pay the compensation plus compound annual interest at a rate equivalent to the 5-year Spanish Government bond yield from 30 June 2014 until full payment. The Claimant was also awarded a significant portion of its legal and arbitration costs, amounting to US$4,814,570, €562,458, and US$299,908.16.