Notice: We are currently performing maintenance to improve the italaw platform. The site remains fully accessible. Thank you for your patience.

Soprim Construction v. Djibouti, Judgment of the High Court of Justice of England and Wales, May 18, 2016

18 May 2016
Soprim Construction v. Republic of Djibouti, LCIA
Judgment of the High Court of Justice of England and Wales
Document Details:
LISTED PARTICIPANTS
Judgment of the High Court of Justice of England and Wales
Participants listed are for this document only and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Claimant's law firm
Respondent's counsel
Respondent's law firm
Other counsel
Claimant's expert
Claimant's expert firm
Respondent's expert
Respondent's expert firm
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Third-party funder
Print reporter
Document Summary
Judgment of the High Court of Justice of England and Wales
This summary note is machine-generated. Always consult the original materials.

Procedural Posture

This document is a judgment of the English High Court of Justice (Commercial Court) concerning a challenge brought by the Claimant under Section 67 of the Arbitration Act 1996. The Claimant sought to set aside an interim arbitral award on jurisdiction rendered by a sole arbitrator, which had concluded that the tribunal lacked substantive jurisdiction over the dispute.

Factual Background and Principal Issues

The underlying arbitration arises from a Concession Agreement governed by English law, under which the Respondent State granted a concession to construct and operate a container terminal. The Claimant, a sub-contractor, initiated arbitration seeking compensation for alleged politically motivated interference and seizure of equipment, relying on third-party rights to enforce tax and property protections under Article 12.1.3 of the Concession Agreement. The principal legal issue before the Court (the "addendum issue") was whether Article 1.2.5(a) of a subsequent Addendum extinguished the Claimant's statutory entitlement to enforce the original agreement under Section 1(1)(b) of the Contracts (Rights of Third Parties) Act 1999.

Court's Analysis and Reasoning

Conducting a de novo rehearing of the jurisdictional question, the Court analyzed the competing contractual interpretations of the Addendum's saving provision. The Respondent argued that the provision excluded all third-party rights except those expressly granted under Section 1(1)(a) of the 1999 Act. The Claimant contended that the saving provision preserved rights arising under Section 1(1)(b).

The Court observed that interpreting the contract is an objective exercise. It found the Respondent's interpretation untenable, as it would render the saving provision entirely devoid of purpose and irrationally strip away third-party rights—including those of project financiers—that had been intentionally conferred only months prior. While acknowledging that both proposed interpretations presented textual difficulties, the Court concluded that the Claimant's construction was the more commercially rational outcome and the lesser of two evils.

Decision

The Court ruled in favor of the Claimant, holding that Article 1.2.5(a) of the Addendum did not vary the Concession Agreement in a manner that extinguished the Claimant's right to enforce Article 12.1.3. Accordingly, the Court determined that the arbitral tribunal possesses substantive jurisdiction over the dispute.