International Centre for Settlement of Investment Disputes
(ICSID)
LUPAKA GOLD CORP.,
Claimant,
v.
REPUBLIC OF PERU,
Respondent.
ICSID CASE No. ARB/20/46
Republic of Peru’s Statement of Costs
17 October 2023
[Page 1]
1. In its previous submissions in the present arbitration,1 the Republic of Peru (“Peru”) requested that the Tribunal exercise its authority and discretion under Article 841(1) of the Peru-Canada Free Trade Agreement (“Treaty”) and Article 61(2) of the ICSID Convention to order Claimant to pay all of Peru’s costs and expenses, including legal fees, as well as the costs and expenses of the members of the Tribunal and ICSID’s administrative fees and expenses (hereinafter “Costs and Expenses”). Peru hereby respectfully reiterates its request.
2. The present submission constitutes Peru’s Statement of Costs and is divided into the following sections: Section I provides an itemized schedule of Peru’s Costs and Expenses; Section II articulates the principles and factors to be applied concerning the allocation of costs; and Section III contains Peru’s request for relief concerning the allocation of costs.
3. As specified in this section, the total amount of Costs and Expenses incurred by Peru in the present arbitration is USD 4,005,002.67. These Costs and Expenses have been incurred and processed by Peru in this proceeding, as at 17 October 2023.2
4. The undersigned, as counsel for Peru, hereby certify that the figures presented below are compiled from (i) information provided to Arnold & Porter by Peru, and (ii) Arnold & Porter’s own time entries and the relevant invoices (and supporting documentation thereto) that it has submitted to Peru.
1 Counter-Memorial, § VI; Rejoinder, § VI; Peru’s Post-Hearing Brief, § V. ↩
2 Peru reserves the right to update the amount of Costs and Expenses reported in the present Statement of Costs, to reflect costs incurred or processed after 17 October 2023. ↩
[Page 2]
Table A: Summary of Peru’s Costs and Expenses
| Summary of Fees and Expenses | Amount (USD) |
|---|---|
| ICSID fees and expenses | 450,000.00 |
| Legal fees and expenses (Arnold & Porter, Garrigues) | 2,986,502.67 |
| Fees and expenses for damages expert (AlixPartners) | 482,000.00 |
| Fees and expenses for legal experts (Mr. Daniel Vela, Mr. Ivan F. Meini, Ms. Miyanou Dufour) | 86,500.00 |
| TOTAL COSTS | 4,005,002.67 |
Table B: ICSID Administrative Fees & Expenses
| Date of Payment to ICSID | Amount (USD) |
|---|---|
| 17 January 2023 | 200,000.00 |
| 9 March 2023 | 250,000.00 |
| ICSID Fees – Subtotal | 450,000.00 |
[Page 3]
Table C: Arnold & Porter’s Legal Fees
| Period of Service | Fees (USD) | Expenses (USD) |
|---|---|---|
| Initial Payment (May 2021) | 300,000.00 | - |
| June 2021 | 5,731.22 | 632.44 |
| July 2021 | 5,764.85 | - |
| August 2021 | 6,395.41 | 178.39 |
| September 2021 | 3,011.32 | - |
| October 2021 | 72,614.69 | 100.82 |
| November 2021 | 77,754.01 | 347.67 |
| December 2021 | 162,017.48 | 5,984.20 |
| Subtotal (2021) | 633,288.98 | 7,243.52 |
| January 2022 | 282,350.12 | - |
| February 2022 | 507,343.91 | - |
| March 2022 | 644,945.32 | 732.15 |
| April 2022 | 82,071.67 | 52,574.35 |
| May 2022 | - | 21,850.73 |
| June 2022 | - | 9,441.88 |
| July 2022 | - | 413.00 |
| August 2022 | - | 796.45 |
| September 2022 | - | 922.60 |
| October 2022 | - | 1,919.33 |
| November 2022 | - | 694.60 |
| December 1-19 2022 | - | 469.94 |
| December 20-31 2022 | 146,512.71 | - |
| Subtotal (2022) | 1,663,223.73 | 89,815.03 |
[Page 4]
| January 2023 | 390,987.29 | 4,864.40 |
| February 2023 | - | 3,650.59 |
| March-April 2023 | - | 103,521.83 |
| June 2023 | 1,300.00 | |
| Subtotal 2023 (as at 30 September 2023) | 390,987.29 | 113,336.82 |
| Arnold & Porter Legal Fees and Expenses – Subtotal | 2,897,895.37 | |
Table D: Garrigues Legal Fees and Expenses
| Period of Service | Fees (USD) | Expenses (USD) |
|---|---|---|
| October 2021 | 21,459.00 | |
| December 2021 | 1,000.00 | |
| January 2022 | 5,768.00 | |
| November 2022 | 2,647.40 | |
| December 2022 | 4,620.00 | 556.82 |
| January 2023 | 2,136.00 | |
| February 20023 | 3,190.00 | 686.91 |
| March 2023 | 40,965.00 | |
| March-April 2023 | 6,304.30 | |
| April 2023 | 3,600.00 | |
| Garrigues Fees and Expenses – Subtotal | 92,933.43 | |
[Page 5]
Table E: Experts’ Fees and Expenses
| Costs and Expenses (not including legal fees paid by Peru to its counsel team) |
Amount (USD) |
|---|---|
| Expert fees paid to Mr. Daniel Vela | 10,000.00 |
| Expert fees paid to Mr. Ivan F. Meini | 16,500.00 |
| Expert fees paid to AlixPartners | 482,000.00 |
| Expert fees paid to Ms. Miyanou Dufour von Gordon | 60,000.00 |
| Expert Fees and Expenses – Subtotal | 568,500.00 |
5. The total amount of Costs and Expenses incurred by Peru in the present arbitration is reasonable, especially considering the complexity of the legal and factual issues in the case, the voluminous documentary record, and the requirement for expert evidence on numerous Peruvian law issues and quantum.3 Peru managed this case as efficiently as possible, despite the above complexities, and the expansive nature of the dispute and allegations brought by Claimant.
6. Peru notes that the total amount of Costs and Expenses that it has incurred (i.e., USD 4,005,002.67) is below the mean party costs incurred in ISDS proceedings by respondent State entities, which is approximately USD 4.7 million.4
7. In determining how to allocate the costs of a proceeding, previous tribunals have adopted different approaches. For example, some tribunals have applied the principle
4 Matthew Hodgson, Yarik Kryvoi, Daniel Hrcka, 2021 Empirical Study: Costs, Damages and Duration in Investor-State Arbitration, British Institute of International and Comparative Law, Allen & Overy, June 2021, p. 4. ↩
[Page 6]
that “costs follow the event” and have awarded costs to the successful party.5 Other tribunals have undertaken a fact-specific analysis that takes into account the individual circumstances of the case at hand, in addition to the ultimate relative success of the parties. This approach ensures that tribunals “exercise [their] discretion in a rational way.”6 As observed by the Burlington v. Ecuador tribunal, “the apportionment of costs requires an analysis of all of the circumstances of the case, including to what extent a party has contributed to the costs of the arbitration and whether that contribution was reasonable and justified” (emphasis added).7
8. Previous ICSID tribunals have adopted an approach that considers the following factors: (i) the parties’ respective requests for relief concerning the allocation of costs; (ii) the outcome of the parties’ respective claims, defenses and applications; (iii) the complexity or novelty of the issues raised in the arbitration proceeding; (iv) the submission of frivolous claims; (v) conduct that unnecessarily increased the expense of the proceedings; and (vi) the reasonableness of the parties’ legal costs.8
9. An additional factor taken into account by several tribunals is the good faith motives of the State in adopting measures that are alleged to constitute a breach of its treaty obligations. For example, the tribunal in Burlington Resources Inc. v. Ecuador took into account the respondent States’ motives and good faith:
In the Tribunal’s view, after a consideration of all the relevant circumstances, the principles above may be adjusted to take into account that the respondent is a sovereign State. In particular, it considers that, even if a tribunal finds that a Sate has breached its international obligations vis-à-vis an investor, consideration
5 See, e.g., CLA-008, Generation Ukraine, Inc. v. Ukraine, ICSID Case No. ARB/00/9, Award, 16 September 2003 (Salpius, Voss, Paulsson), ¶ 24.1. ↩
6 CLA-0103, UAB E Energia v. Republic of Latvia, ICSID Case No. ARB/12/33, Dissenting Opinion on Costs, 22 December 2017 (Reinisch), ¶ 12. ↩
7 CLA-0144, Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Reconsideration and Award, 7 February 2017 (Kaufmann-Kohler, Stern, Drymer), ¶ 620 (emphasis added); see also id. at ¶ 619. ↩
8 See e.g., CLA-0144, Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Reconsideration and Award, 7 February 2017 (Kaufmann-Kohler, Stern, Drymer), ¶ 620. ↩
[Page 7]
must be given to the State’s motives and good faith. In particular, where the actions of a State have been guided by its good faith understanding of the public interest and the State could reasonably doubt that it was breaching its international obligations, the Tribunal may consider it appropriate to apportion costs in a manner that alleviates the burden on the respondent State.9 (Emphasis added)
10. On the basis of the above principles, Peru respectfully submits that, in the event that Peru is the successful party in this arbitration, Claimant should be ordered to pay the entirety of Peru’s Costs and Expenses.
11. Conversely, in the event that Peru is not the successful party, Peru submits that the Tribunal should take into account the fact that, as Peru demonstrated in its pleadings, the relevant measures in this case were taken in good faith, with the aim of (i) preventing the escalation of the social conflict between Claimant and the Parán Community, (ii) securing a sustainable resolution to that dispute, and (iii) discharging Peru’s legal obligations under international and domestic law.10
12. Finally, Claimant’s conduct unnecessarily increased the length and cost of the proceedings in at least the following ways:
9 Burlington Resources Inc. v. Ecuador, ICSID Case No. ARB/08/5, Decision on Reconsideration and Award, 7 February 2017 (Kaufmann-Kohler, Stern, Drymer), ¶ 621. See also Krederi Ltd. v. Ukraine, ICSID Case No. ARB/14/17, Award, 2 July 2018 (Reinisch, Wirth, Griffith), ¶ 738. ↩
10 Counter-Memorial, § II.E; Rejoinder § II.C. ↩
[Page 8]
law arguments—necessitated that Peru dedicate additional resources to respond to these belated arguments and change of tack by Claimant;
13. The above, as well as other circumstances resulting from Claimant’s litigation tactics, have imposed a substantial burden on Peru, and should be considered when determining the allocation of costs in this case.
14. In light of the foregoing, Peru respectfully requests that the Tribunal order Claimant to pay:
[Page 9]
Respectfully Submitted,
Signature
Paolo Di Rosa
Patricio Grané Labat
Tim Smyth
Ana Pirnia
Arnold & Porter Kaye Scholer LLP
601 Massachusetts Avenue NW
Washington, DC 20001
Tower 42
25 Old Broad Street
London EC2N 1HQ
United Kingdom