UNITED STATES DISTRICT COURT
DISTRICT OF COLUMBIA

PROCESS AND INDUSTRIAL
DEVELOPMENTS LIMITED,

Petitioner,

v.

FEDERAL REPUBLIC OF NIGERIA and
MINISTRY OF PETROLEUM RESOURCES
OF THE FEDERAL REPUBLIC OF NIGERIA,

Respondents

Civil Action No: 18-cv-594 (CRC)


JOINT STIPULATION TO STAY PETITIONER'S
PETITION TO CONFIRM ARBITRATION AWARD


Petitioner Process and Industrial Developments Limited (“P&ID”), and Respondents Federal Republic of Nigeria and the Ministry of Petroleum Resources of the Federal Republic of Nigeria (together “Nigeria”), by and through their undersigned counsel, hereby respectfully submit this Stipulation and [Proposed] Order to stay this action concerning P&ID's Petition to Confirm Arbitration Award (ECF 1) (the “Petition”). The parties respectfully submit this Stipulation and [Proposed] Order as their “joint proposal for further proceedings in this case”, which the Court directed the parties to file on or before May 26, 2022, by minute order on May 18, 2022, and which the parties reported that they would file by June 2, 2022 in their joint status report (ECF 64).

In support of this joint stipulation, the parties state as follows:

WHEREAS on March 16, 2018, P&ID filed the Petition for recognition and enforcement of an arbitral award against Nigeria issued on January 31, 2017 (the “Award");

WHEREAS the Award concerns P&ID's efforts to enforce a January 11, 2010 Gas Processing and Supply Agreement between Nigeria and P&ID (the “GSPA");

[Page 2]

WHEREAS on March 16, 2018, P&ID commenced enforcement proceedings in the High Court of Justice in London, England to enforce the Award (the “English Enforcement Application");

WHEREAS on August 16, 2019, the English Court granted the English Enforcement Application (the “English Enforcement Judgment”), which Judgment has been filed on the docket in this action for the Court's reference. See ECF 45-2;

WHEREAS on December 5, 2019, Nigeria commenced proceedings in London, England, pursuant to Sections 67 and 68 of the Arbitration Act 1996 for orders setting aside the Award and/or declaring the Award to be of no effect, and also commenced an application pursuant to Section 66 of the Arbitration Act 1996 for permission to resist enforcement of the English Enforcement Judgment (collectively, the “Set Aside Application");

WHEREAS on September 10, 2020, the English High Court of Justice issued its Judgment authorizing Nigeria to proceed with its Set Aside Application, which Judgment has been filed on the docket in this action for the Court's reference. See ECF 48-1;

WHEREAS the trial on Nigeria's Set Aside Application is scheduled to commence on January 23, 2023, and the parties anticipate that it will conclude in March 2023 with a judgment to be handed down by the English High Court of Justice thereafter (the “Expected English Judgment");

WHEREAS on December 31, 2020, Nigeria appealed this Court's order denying Nigeria's motion to dismiss to the D.C. Circuit (ECF 58), which the D.C. Circuit affirmed, Process and Industrial Developments Limited v. Federal Republic of Nigeria, 27 F.4th 771 (D.C. Cir. 2022) (the “D.C. Circuit Decision”); and

[Page 3]

WHEREAS the parties have consulted and agree that the Petition should be stayed through fourteen (14) days after the Expected English Judgment is handed down.

NOW THEREFORE, IT IS HEREBY STIPULATED AND AGREED, by and between the undersigned counsel for the parties as follows:

  1. Other than the status reports provided for in paragraph 2 below, the Petition and this proceeding shall be stayed until fourteen (14) days after the Expected English Judgment is handed down by the English High Court of Justice;
  2. The parties will file a joint status report every ninety days to apprise the Court of the status of the Set Aside Application, and within fourteen days after the Expected English Judgment is handed down by the English High Court of Justice;
  3. Nigeria shall not be required to provide any security as a condition of the stay;
  4. As consideration for P&ID's consent to the stay, Nigeria shall not file a Petition for Certiorari before the United States Supreme Court regarding the D.C. Circuit Decision; and
  5. Nigeria's written response to the Petition will be due sixty (60) days after the Expected English Judgment is handed down by the English High Court of Justice.

Dated: June 2, 2022
New York, New York

KOBRE & KIM LLP

By: /s/ Darryl G. Stein
Darryl G. Stein, Esq.
Michael S. Kim, Esq.
Josef M. Klazen, Esq.
800 Third Avenue
New York, New York 10022
Tel: (212) 488-1200

Attorneys for the Process and
Industrial Developments Limited

MEISTER SEELIG & FEIN LLP

By: /s/ Christopher J. Major
Christopher J. Major, Esq.
Alexander D. Pencu, Esq.
Austin D. Kim, Esq.
125 Park Avenue, 7th Floor
New York, New York 10017
Tel: (212) 655-3500

Attorneys for the Federal Republic of Nigeria
and the Ministry of Petroleum Resources the
Federal Republic of Nigeria

[Page 4]

So Ordered this ___ day of __________, 2022