This HTML version is machine-generated. Always consult the original document.Original document (PDF), opens in new tab

PCA CASE NO. 2020-21

IN THE MATTER OF AN ARBITRATION UNDER THE ARBITRATION RULES OF
THE UNITED NATIONS COMMISSION OF INTERNATIONAL TRADE LAW 1976
AND
PURSUANT TO PURSUANT TO THE AGREEMENT BETWEEN THE GOVERNMENT
OF THE REPUBLIC OF INDIA AND THE REPUBLIC OF MOZAMBIQUE FOR THE
RECIPROCAL PROMOTION AND PROTECTION OF INVESTMENT

Between:

PATEL ENGINEERING LTD.

Claimant

-and-

REPUBLIC OF MOZAMBIQUE and MOZAMBIQUE
MINISTRY OF TRANSPORT AND COMMUNICATIONS

Respondents


RESPONDENT REPUBLIC OF MOZAMBIQUE'S POST-TRIAL BRIEF


3 March 2023

Juan C. Basombrío
Dorsey & Whitney LLP
600 Anton Boulevard, Suite 2000
Costa Mesa, California 92626 U.S.A.
Telephone: 1-714-800-1405
[email protected]
Theresa Bevilacqua
Daniel J. Brown
Dorsey & Whitney LLP
50 South Sixth Street, Suite 1500
Minneapolis, MN 55402 U.S.A.
Telephone: 1-612-340-2600
[email protected];
[email protected]

Counsel for Claimants Republic of Mozambique and
Mozambique Ministry of Transport and Communications

[Page 1]

I. THE MOI'S ARBITRATION CLAUSE LIMITS THIS TRIBUNAL'S JURISDICTION

II. THIS TRIBUNAL LACKS TREATY JURISDICTION

[Page 2]

asset under Article 1(a) of the Treaty and hence a protected investment, would really go far beyond the concept of investment, even if broadly defined, as this and other treaties normally do.”). See SOD, at ¶¶ 362-419; Rejoinder, at ¶¶ 661-870.

1. The MOI is a preliminary and a conditional contract. PEL gets a “direito de preferência” if the PFS is approved. If the project is not viable, the parties negotiate another MOI.

[Page 3]

investor, a certain regularity of profit to the investor, and a contribution to the economic development of the host state. RL-7, Salini Construttori S.p.A. and Italstrade S.p.A. v. Kingdom of Morocco, ICSID Case No. ARB/00/4 (Decision on Jurisdiction, 23 July 2001) at ¶ 52; see also SOD, at ¶¶ 400-19; Rejoinder, at 830-34; Motion for Bifurcation, at 11.

[Page 4]

III. MOZAMBIQUE PREVAILS ON THE MERITS

[Page 5]

guided by the final contract and would not consider prior drafts or arguments that a party did not understand what they were signing.

[Page 6]

[Page 7]

[Page 8]

[Page 9]

663:2-3 (“CFM has administrative and financial autonomy. I can't force them to anything.”)

[Page 10]

Commissioner of Mozambique in India (who then writes to Mozambique's Ministry of Foreign Affairs). C-380 (citing C-20, C-23, C-28, C-266); Daga Tr. at 506-507.

[Page 11]

[Page 12]

IV. PEL'S DAMAGES CLAIMS MUST BE REJECTED

A. The Tribunal Does Not Have Jurisdiction Over The Damages Claims As Presented By PEL

The damages testimony presented by PEL itself demonstrates the lack of the Tribunal's jurisdiction to award the damages claimed.

B. The MOI At Most Provided For A Direito de Preferência, Which PEL Already Received

C. PEL's Damages Claims Are Baseless, Entirely Speculative, and Unsupported by Applicable Law

Even if the Tribunal ignored the undisputed fact that the MOI is not a concession and does not grant the right to a concession, PEL's damages claims are baseless for at least five reasons, each of which alone are sufficient to wipe out PEL's claims.

[Page 13]

1. PEL's Own 2012 Financials Show PEL's Proposed Project Was Not Viable

[Page 14]

2. TML's Project, Even if Considered Comparable, Has Been Substantially Altered and Will Not Be Built

[Page 15]

other option on the international market, such as Australia. H-12 p. 55; RER-9 ¶¶190-191; C-290, p. 9); Flores Tr. 1276:20-1280:25.

D. PEL's Array of Damages Theories Cannot Satisfy PEL's Burden to Prove Alleged Damages

1. PEL's Damages Based on Discounted Cash Flows (“DCF”) Analyses are Impermissible and Speculative

2. PEL's Ex-Ante Valuation is Flawed

[Page 16]

3. PEL's Ex-Post Valuation is Flawed

[Page 17]

[Page 18]

E. PEL's Damages Based on So-Called Loss of Chance are Conceptually and Factually Flawed

F. PEL's So-called Negotiation Damages are Flawed, Even More Speculative, and Inconsistent with PEL's Other Damages Theories

[Page 19]

G. Dearman's Damages Analysis Only Proves That The Project Was Not Viable And No Damages Are Owed

[Page 20]

H. PEL Has Not Satisfied Its Burden Regarding Damages, And Refused To Submit Any Non-Speculative Basis For An Award

$115.3M

$156.0M

$78.2M

$104.7M $140.4M

$40.9M $70.4M $65.9M 90.5M 143.7M

$24.9M $64.9M

$15.6M $31.2M 49.8 $74.8M $124.6M

$0 $18.7M $28.0M $46.7M $77.9M

[Page 21]

V. RELIEF REQUESTED BY MOZAMBIQUE

Based on the foregoing, Mozambique is entitled to and seeks an Award, as follows:

Dated: 3 March 2023

Respectfully submitted,

Signature

Juan C. Basombrío
Dorsey & Whitney LLP
600 Anton Boulevard, Suite 2000
Costa Mesa, California 92626 U.S.A.
Telephone: 1-714-800-1405
Email: [email protected]

Theresa M. Bevilacqua
Daniel J. Brown
Dorsey & Whitney LLP
50 South Sixth Street, Suite 1500
Minneapolis, Minnesota 55402 U.S.A.
Telephone: 1-612-492-6614
Email: [email protected]
[email protected]

Counsel for Respondent
Republic of Mozambique