Notice: We are currently performing maintenance to improve the italaw portal. The site remains fully accessible. Thank you for your patience.

Frazer Solar v. Lesotho, Award

28 Jan 2020
Frazer Solar GmbH v. Kingdom of Lesotho
Document provided by: IAReporter
Award
Document Details:
LISTED PARTICIPANTS
Award
Participants listed are for this document only, and may not include all participants involved in the entire case. Always consult the original documents.
Claimant appointee
Respondent appointee
Tribunal/Panel chair
Arbitrator(s)
Sole Arbitrator
ICSID Annulment Committee president
ICSID Annulment Committee members
WTO Appellate Body members
WTO Appellate Body chair
Judges
Claimant's counsel
Respondent's counsel
Other counsel
Claimant's expert
Respondent's expert
Claimant's witness
Respondent's witness
Other witnesses
Tribunal secretary
Tribunal assistant
Country
Print reporter
Document Summary
Award
This summary note is machine-generated. Always consult the original materials.

Procedural History and Jurisdiction

This document is a final Arbitration Award rendered by a Sole Arbitrator, Vincent Maleka SC, in a dispute between Frazer Solar GmbH (Claimant) and the Kingdom of Lesotho (Respondent). The arbitration was conducted under the rules of the Association of Arbitrators (Southern Africa) NPC. A key procedural feature of the case was the Respondent's complete non-participation, having failed to respond to the notice of arbitration or file any submissions.

The Arbitrator first addressed his jurisdiction to proceed in the Respondent's absence. He affirmed his authority, relying on Article 30 of the applicable rules, which permits an arbitrator to continue proceedings where a party, after due notice, fails to participate. The Arbitrator also determined that South Africa's International Arbitration Act, 2017, incorporating the UNCITRAL Model Law, governed the proceedings, notwithstanding the Supply Agreement's reference to the domestic Arbitration Act, 1965. This conclusion was based on the international character of the dispute, as both parties were domiciled outside South Africa, the place of performance was in Lesotho, and the seat of arbitration was Johannesburg.

Tribunal's Findings on the Merits

The dispute arose from an alleged breach of a Supply Agreement dated 24 September 2018 for a renewable energy project in Lesotho. The Arbitrator found that the Kingdom of Lesotho had committed material breaches of the agreement. The central breach was the failure to execute the necessary Finance Agreement, which was a prerequisite for the project's implementation. The evidence, primarily from the Claimant's witness Mr. Frazer, indicated that Lesotho's Minister of Finance refused to sign the financing documents because he had committed to a competing renewable energy project in Mafeteng. The Arbitrator concluded that this failure constituted a breach of several warranty clauses (including 17.1.1, 17.1.3, and 17.2) that went to the root of the Supply Agreement, entitling the Claimant to terminate the contract and claim damages.

However, the Arbitrator dismissed the Claimant's claim for breach of Clause 18 of the Supply Agreement, which granted the Claimant a right of first opportunity for "all other renewable energy ... opportunities." The Arbitrator reasoned that the competing Mafeteng project was not an "other" or "additional" project but a direct rival whose selection caused the demise of the Claimant's project. Therefore, Lesotho's support for the Mafeteng project did not constitute a breach of this specific clause.

Analysis of Damages and Award

Based on these findings, the Arbitrator proceeded to assess the quantum of damages. The Claimant had advanced a main claim for liquidated damages of €50 million (under Clause 12) plus damages for loss of opportunity valued at €52.1 million. The Arbitrator awarded the €50 million in liquidated damages, finding the amount to be a reasonable and quantifiable pre-estimate of the loss flowing from the termination of the Supply Agreement. This was supported by expert evidence showing that the actual loss of profit was slightly higher, at €51.6 million.

Consistent with his finding on the merits, the Arbitrator dismissed the claim for €52.1 million related to the loss of opportunity from the Mafeteng project. The final award directed the Kingdom of Lesotho to pay the Claimant: (i) liquidated damages of €50 million; (ii) pre-award interest of €754,273; (iii) post-award interest at a rate of 1.7% per annum on the principal sum from the date of the award until payment; and (iv) the costs of the arbitration, including the Claimant's legal and expert fees, as well as the Arbitrator's fees.